The government has confirmed another 111 buildings do not comply with building regulations following the latest round of detailed fire safety tests in the wake of the Grenfell disaster.

The latest tests focused on wall cladding systems consisting of Aluminium Composite Material (ACM) cladding with a polyethylene filler (category 3) with stone wool insulation.

A government update confirmed: “The results show this combination does not meet current building regulation guidance.

“111 buildings are currently known to have this combination of materials in their wall cladding systems – 90 of which are local authority or housing association owned or managed.”

A guidance note adds: “Wall systems with these materials therefore present a significant fire hazard on buildings over 18m.”

The failures follow the first round of detailed tests last week on a wall cladding system consisting of ACM with polyethylene filler (Category 3) and foam insulation, with fire breaks and cavity barriers in place.

That combination failed to meet current building regulations guidance and 82 buildings are currently covered in it.

Cllr Simon Blackburn, Chair of the Local Government Association’s Safer and Stronger Communities Board, said: “Councils will continue to get on with what they need to do to ensure people are safe in their homes. This includes replacing materials on high-rise blocks affected by these fire safety tests.

“The tragedy at Grenfell Tower has clearly exposed a systemic failure of the current system of building regulation.

“The Government must commit to meet the full cost to councils of removing and replacing cladding and insulation systems.

“It is also imperative that this testing process moves quickly to identify what landlords should be replacing these systems with as soon as possible.

“With these latest test fails affecting buildings owned by a range of different landlords across the country, the Government also needs to make sure there is capacity within the housebuilding industry to take quick action to carry out the scale of remedial work that looks likely to be needed.

“We also continue to call on the Building Research Establishment and the industry to release results of previous safety tests, including desktop studies.

“Everything must be out in the open and this needs to happen as soon as possible.”

Latest news

Wates and Mount Anvil seal deal to deliver 1,100-plus London homes

Site deal with Southwark Council includes 360 council houses
8 hours ago

Contractor hunt begins for £5.7bn Thames Water reservoir

Main works tender issued for Oxfordshire White Horse Reservoir job
15 hours ago

Worker dies on Winvic warehouse site

Fatal accident on £15m Kent job
15 hours ago

£74m refit of landmark Bristol office to go-ahead

Summer start for low-carbon overhaul of Grade II Canons Wharf
16 hours ago

Birmingham City Hospital site set for 750-home rebuild

Homes England and Vistry seal deal to kick-off demolition and rebuild
16 hours ago

Barhale promotes trio in senior leadership shake-up

Contractor creates new executive director role in Southern restructure
17 hours ago

£1.5bn funding to tackle cultural buildings repair backlog

Museums, libraries and arts venues set for major repair works
17 hours ago

JJ Rhatigan lands £78m City office conversion

Main works will start on Barbican site following Gateway 2 approval
1 day ago

Muse scoops 1,350-home Barrow docks regeneration

Developer picked for Marina Village waterfront plan
1 day ago

£15bn Warm Homes Plan maps out mass retrofit drive

Government pledges insulation, solar and heat pumps for up to five million homes
2 days ago

FK Facades and Construction placed into administration

40 jobs axed as Man City stadium and Elephant & Castle facade jobs stall
2 days ago

Galliford Try lifts profit outlook for first half

Firm upgrades full-year profit outlook backed by £211m cash pile and a £4.1bn order book
2 days ago

Chinese mega-embassy plan in London approved

Royal Mint Court scheme approved opposite the Tower of London
2 days ago

Winvic targets data centres market

Contractor looks to expand into new sector
2 days ago

South West civils firm Roadform files administration notice

£31m turnover contractor lodges court notice
2 days ago

Plans in for Derby Market Place regeneration

VINCI and ION push forward flagship city revival project
3 days ago

Kier returns to monthly net cash for first time in over a decade

Balance sheet turnaround comes as order book hits record £11.6bn
3 days ago

Strabag UK snaps up failed HV transmission contractor

Austrian giant makes move on UK energy market after GTDS pre-pack deal
3 days ago

Mace name to disappear from UK contracting

Construct arm to be renamed as consultancy takes Mace badge
3 days ago

Motorway closed after road repair kit breaks down

Traffic chaos on M62 as broken-down plant shuts junction near Huddersfield
3 days ago

Align closes out civils on longest HS2 tunnel

10-mile Chiltern Tunnel moves to fit-out after near five-year long civils job
3 days ago

Legal expert rises to head Balfour Beatty regional civils

Kay Slade steps up after reshaping North West operations
3 days ago

Tilbury Douglas regional chief joins Caddick to head civils arm

Ellenor is tasked with growing third-party work and widen the firm's regional footprint.
3 days ago

Six scoop £2bn Southern Housing upkeep deal

Big name firms miss out on 10-20 year framework deal
4 days ago

Hercules delays annual results announcement

Auditors still working on labour supplier's numbers after string of acquisitions
4 days ago

Benniman to finish logistics park at former MG Rover plant

13-unit industrial package marks final chapter of Longbridge West transformation
4 days ago

Flannery to sell old fleet after £107m new kit investment

Huge auction of machines in March after massive investment by plant hire giant
4 days ago

Liverpool mayor sets out £2bn plan to unlock 64,000 homes

300-site pipeline targets stalled urban schemes
4 days ago

Graham lands £37m Leicestershire school rebuild

Castle Rock School overhaul will accommodate more than 1,500 pupils
4 days ago

Caldwell Construction collapses into administration

Insolvency specialist PKF Littlejohn appointed after rescue talks fail
1 week ago