Industry awaits verdict as cladding fire tests completed

Aaron Morby 3 years ago
Share

The Government has pledged to set out clear advice on the use of high-rise cladding systems after completing seven large-scale fire tests on popular aluminium composite cladding systems.

ACM with a limited combustibility filler (A2) with mineral wool insulation passes BRE fire test
ACM with a limited combustibility filler (A2) with mineral wool insulation passes BRE fire test

Until this is published, building owners are being left in limbo despite four cladding systems failing the BRE testing regime needed to demonstrate compliance with Building Regulation fire performance.

So far 228 residential buildings over 18m have been identified to be fitted with cladding systems that fail performance tests.

But with the results all in, designers and contractors are warning that manufacturers’ descriptions of the performance of materials could still create confusion.

A cladding industry source said: “These results must be welcomed because they bring some clarity to what systems comply with Building Regulation requirements.

“But the use of the terminology used by manufacturers around combustibility of fillers used in aluminium cladding needs to be addressed to end market confusion.”

Cladding system tests Result 18m-plus buildings
ACM with unmodified polyethylene filler (PE) with PIR foam insulation Failed 82
ACM with unmodified polyethylene filler (PE) with mineral wool insulation Failed 111
ACM with a fire retardant polyethylene filler (FR) with PIR foam insulation Failed 13
ACM with fire retardant polyethylene filler (FR) and phenolic foam insulation Failed 22
ACM with fire retardant polyethylene filler (FR) with mineral insulation Passed 13
ACM with a limited combustibility filler (A2) with PIR foam insulation Passed 0
ACM with a limited combustibility filler (A2) with mineral wool insulation Passed 0

The final test involving the least combustible combination of components passed the latest fire test as expected.

This involved a wall cladding system consisting of ACM cladding with a limited combustibility filler (A2) in combination with stone (mineral) wool insulation.

Announcing the result, the Government advisory panel said that this combination of materials were compliant when installed and maintained properly.

A statement said: “While government has not been informed of any tall buildings over 18 metres in England using this particular combination of materials in their wall system, it could offer a possible solution for some buildings with other cladding systems which have been identified as a fire hazard through previous large-scale tests.

“The clear advice from the expert panel remains that building owners need to continue to take professional advice regarding remedial work that takes into account the specific circumstances of their building.”

It added: “The purpose of this testing programme is to develop a better understanding of how different types of cladding panels behave with different types of insulation in a fire.

“This is so building owners and their professional advisors can make informed decisions. Results of all seven large-scale tests are available and government will shortly publish consolidated advice to landlords based on all the seven tests.”

Latest news

Plans go in for 42 acre London food market

Billingsgate, Spitalfields and Smithfield to get a new home in Dagenham
4 hours ago

Premier Inn restarts construction work on 35 sites

Hotel giant committed to long term expansion plans
5 hours ago

Leading brick makers to axe 600 jobs

Ibstock and Forterra restructure businesses to meet forecast fall in demand
10 hours ago

Kier Highways and Seddon reinstated to Prompt Payment Code

Contractors now keeping to pledge to pay 95% of suppliers within 60 days
9 hours ago

London fit-out firm Square Metre in administration

Fifty jobs cut as lockdown tips £32m fit-out firm over the edge
10 hours ago

Last webinar for contractors interested in £600m plant

Final procurement information event before OJEU notice next month
10 hours ago

Offsite system to cut staircase construction times by 80%

New integrated balustrade system added before precast stairs lifted into place on site
1 day ago

Arup bags job to re-open Cardiff city centre

Arup plans to improve public spaces, repurposed streets and digital infrastructure
1 day ago

Hard-hat mounted cough guard will help protect site workers

New product from JSP will help keep sites safe
1 day ago
JSP Ltd

Keep the industry updated by joining the Enquirer Directory

Membership lets construction know you are open for business now or in the future
2 years ago

Balfour Beatty to start £355m Hull A63 scheme

All systems go for delayed Castle Street upgrade to transform Hull
1 day ago

Contractors face data danger fighting covid contract disputes

Redundancies could see project knowledge lost
1 day ago

Mace bags role on £39bn Northern Powerhouse Rail plan

Firm takes lead on project controls, project, stakeholder and commercial management
2 days ago

Cash flow fears spark call for another delay to VAT changes

Thousands of firms unaware tax change could cut cash flow by 20%
2 days ago

Driver unveils changes at the top

Mark Wheeler takes helm as Gordon Wilkinson steps down as CEO
1 day ago

ISG mobilises for £17m north London town hall fit-out

First phase of £150m Waltham Forest Town Hall redevelopment starts
1 day ago

Morrison wins £42m Scottish factory of the future

Work to start this summer on National Manufacturing Institute Scotland.
1 day ago

London mayor loans Mount Anvil £50m to boost building

New partnership to boost housing and construction in the capital
2 days ago

Henley Construct lands £12m Croydon housing contract

Demolition to start imminently to revamp street market site
1 day ago

Piling problems force BAM to tear down building frame

Major construction issues delay new £65m Sheffield University faculty building
2 days ago

Industry leaders draw up roadmap to recovery

Construction able to bounce back stronger and more productive within two years
3 days ago

Leaking diamond synchrotron roof to be replaced

Hunt starts for roofing contractor to strip and replace vast circular roof
2 days ago

ISG director leaves to head-up Structure Tone London division

Danny Blakeston joins rival as London managing director
2 days ago

Balfour sets-up “New Normal” Covid-19 taskforce

Contractor focuses on cash discipline and improving productivity on sites
2 days ago

Hinkley C team hits key target despite Covid-19 curbs

BYLOR delivers record pour on second reactor base with reduced workforce
2 days ago

Seven win new highways geotechnical framework

Highways England's new geotechnical framework worth £91m over four years
2 days ago

Plans lodged for £120m Nottingham hotel scheme

Grade II listed Guildhall to become 162-bed luxury hotel
2 days ago

Fit-out firm fined £1.1m after ladder fall

Engineer needs transfusion after massive blood loss caused by fall injury
5 days ago

SIG management blunders rack-up £112.7m loss

New boss promises growth strategy after PwC called in to investigate divisional forecasts
5 days ago

Union calls for construction workers to wear masks

Unite demands revisions to Construction Leadership Council guidelines
6 days ago

Contractor services