Scottish clients failing to enforce supply chain payment

Aaron Morby 8 years ago
Share

Only a third of public sector contracting bodies in Scotland are meeting new public sector procurement rules to ensure prompt payment through the entire supply chain.

The new research has prompted the Specialist Engineering Contractors’ Group for Scotland to call on the Government to set up a new construction regulator role to ensure tier two and three subcontractors are being paid on time.

In April 2016, contracting authorities in Scotland with large annual procurement budgets became statutorily bound to declare in their procurement strategies how they intended to ensure 30-day payments along their supply chains.

Research conducted by SEC Group Scotland using the Freedom of Information Act revealed that 18 months into Scotland’s new payment regime,  just nine client bodies from a sample of 29 had sought to ensure 30-day payments throughout the supply chain.

Contracting authorities deemed to be compliant

• NHS Fife • Western Isles NHS Board6 • Edinburgh Napier University • University of Strathclyde • University of Edinburgh • NHS Borders • Scottish Fire and Rescue Service • Disclosure Scotland • University of Glasgow

It claims 45% or 13 public sector clients have failed to comply with Scottish Government rules on protecting payment periods, with the balance either introducing measures or operating under terms that did not look sufficient to support good payment practice for sub-sub contractors.

Specialist contractors north of the border plan to present the damning report to the Scottish Government, which is required under the new Procurement Reform (Scotland) Act to report annually on procurement activity.

Specialists’ recommedations to support Procurement Reform (Scotland) Act 2014

  • Scottish Government should appoint a “Construction Regulator” with powers to proactively challenge non-compliance.
  • Every contracting authority should have a compliance “hotline” to deal with complaints.
  • Scottish Government should insist project bank accounts are used by contracting authorities to comply with supply chain payment rules “unless there are compelling reasons not to do so”. Such reasons should be published on an authority’s website and, if necessary, capable of being challenged by a Construction Regulator.
  • In any event the statutory guidance should be re-visited to deal with some uncertainty surrounding the use of the phrase, “reasonably practicable”, in section 15 (5)(d).
  • Scottish Government should consider introducing a statutory obligation in all construction contracts that payments are discharged within 30 days from invoice or payment application.
  • The statutory guidance should also be amended so that it deals with the release of retention monies. It is suggested that contracting authorities ensure that in all their contracts, and in sub-contracts and sub-sub-contracts that: • the first half of retention monies are released on handover of the works; • the second half of the retention monies is released within 12 months of handover of the works.

Latest news

Contractors courted for £1.7bn London DLR extension job

Firms urged to register for Thamesmead extension talks next month
2 days ago

Multiplex scales contracts league with London tower job

£400m city Dovetail Building deal tops October ranking
2 days ago

Vidi Construction went down owing £6m to subbies

Failure of main client sunk Coventry contractor
2 days ago

J&D Pierce founder hands reins to new MD duo

Joint managing directors named as Derek Pierce moves up to chairman role
2 days ago

Willmott Dixon plugs fire safety gap for CLT builds

First certified fire tests pave way for cross laminate timber builds
2 days ago

Green light for new £1.3bn neighbourhood in Salford

Ten resi towers to be built alongside 15 retail units
3 days ago

Buyers report fastest activity decline in five years

Construction hopes for better New Year
3 days ago

Ten high-rise schemes in limbo after building control firm folds

BSR pledges to reallocate cases and keep Gateway 2 clear-up on track.
3 days ago

Vistry sees demand start to return for new social housing

New build demand from housing associations rises as Government support starts to kick-in
3 days ago

Travis Perkins suppliers stunned as payment times increase

Builder's merchant giant could now take nearly three months to pay bills
3 days ago

Costain natural resources boss heads to Mitie

Sam White joins Mitie to lead 16,000-strong Technical Services arm
3 days ago

Willmott Dixon gets green light for Kirkby school rebuild

Contractor to start phased construction schedule at Nottinghamshire site
3 days ago

£60m homes plan for Sheffield city centre scrubland

Capital&Centric pushes ahead with 192-home Fitzwilliam project
3 days ago

Sizewell C financial close unlocks full-scale construction

13-bank consortium backs £5.5bn debt finance to launch full build phase in Suffolk
5 days ago

SDM Fabrications files administration notice

East Anglian steelwork contractor lodges court notice
4 days ago

Winners of £1.6bn social housing decarbonisation deal

Procure Plus awards huge retrofit and renewables framework
4 days ago

Stepnell hires Vinci development chief for Midlands push

Graham Lambert joins as regional director to drive growth
4 days ago

First data centre plans at Blackpool’s Silicon Sands site

Development aims to turn Fylde Coast into hub for digital innovation
4 days ago

Race starts for £1.5bn LHC building framework

Lower barriers and regional focus aim to draw SMEs in for PB4 deal
4 days ago

Social housing workers suffer at hands of vibrating tools

Nottingham City Homes prosecuted after builders exposed to risks
4 days ago

Building control giant Assent ceases trading

Shockwaves to hit Building Safety Regulator approval process
5 days ago

McLaren Living signs deal for £250m Reading regen

Minster Quarter to deliver 600 homes and new civic square
5 days ago

London ready-mix sales dive 32% amid housing slump

Building Safety Regulator bottlenecks blamed for steepest regional fall in the country
5 days ago

£200m plan lodged to transform Huyton town centre

Genr8 Kajima advances council HQ, hotel and 72 flats scheme
6 days ago

Luxury London developer acquires £180m Stanmore site

North west London site bought from Notting Hill Genesis
5 days ago

McAleer & Rushe wins £30m Tottenham student living job

287-room student room Printworks scheme to be built near Spurs Stadium
6 days ago

MoD rolls out £9bn plan to fix forces housing

£600k-a-day windfall from Annington buy-back reinvested in new and improved housing.
6 days ago

Statom lands frame deal on Kier Barlinnie prison job

Specialist wins major package on £684m Glasgow super prison
6 days ago

Balfour set to start £200m final stretch of Lincoln ring road

Hope for for early 2026 construction start on North Hykeham Relief Road
6 days ago

DfE greenlights £270m of school and college builds

Kier, Tilbury Douglas and B+K among winners
6 days ago