Concrete problems hit Hinkley Point tunnels

Grant Prior 7 years ago
Share

Contractors at Hinkley Point will have to replace 150 cubic metres of concrete poured on the site as part of work to form tunnels to contain pipes and cables.

Aerial view of the north office and galleries under construction
Aerial view of the north office and galleries under construction

Problems have been identified in sections of the concrete base slabs constructed above the galleries sections of tunnels which will contain site infrastructure.

The Enquirer understands that the problem concrete is local to a small stretch of the 8km network of galleries tunneling.

Only 150 cubic metres of material are affected from the first 60,000 cubic metres poured on the site so far.

Nothing has been built on the slab and it does not form part of the foundations for the main nuclear power plant building where work is not due to get underway for 18 months.

A joint venture of Kier and Bam Nuttall is main contractor on the site earthworks package.

GetImage-1

Work underway last month in the galleries

Hinkley delivery director Nigel Cann said: “We have decided to replace a small area of concrete poured as part of the work to create tunnels for the pipes and cables.

“This is in line with the uncompromising attitude to quality taken at the Hinkley Point C Project.

“It is a very small proportion of the concrete poured on site so far and has no impact on the project schedule.”

Site Progress so far:

2,000 workers are on site every day, 65,000 meals every month needed to feed the growing workforce.

1,500 bed “Campus” accommodation for workers under construction with 500 beds on the site and 1,000 in Bridgwater – supplied by Newark-based Caledonian Modular .

76 apprentices are already working on the project, which will create up to 1,000 apprenticeships during the build.

4 million cubic metres of earth have been excavated – that’s enough to fill Wembley Stadium.

Two concrete batching plants are now complete. Up to 2,000 tonnes of concrete a day can be produced on site. At least 3 million tonnes of concrete will be used – 75 times more concrete than was used to build the Millennium Stadium in Cardiff.

10,000 tonnes of rock has already been delivered by ship from Pembroke, for the site’s new 13.5 metres high seawall.

29km of ground nails have been installed – enough to loop the perimeter of Hyde Park six times. The steel rods, each measuring up to 12 metres long, are used to stabilise the ground. A total of 110km will be used during construction.

Project remains on track to meet the 64% UK supply contribution with nearly £9bn of contracts signed since final approval. The latest contract with ABB Group was signed last month for the main power transmission systems for both reactors.

49 piles have been installed for the 500m temporary jetty in the Bristol Channel. Each pile – the foundation legs for the jetty – is 36 metres long, 3.6 metres in diameter and weighs in at 140 tonnes. The jetty will allow 80% of the aggregate to be brought in by sea rather than by road and is due to be completed next year. Devon engineering firm Blackhill worked on its largest-ever project involving 550 tonnes of steel for the jetty.

Dozens of cranes of all sizes are already on site alongside 200 pieces of large-scale construction equipment, ranging from excavators capable of moving 30 tonnes of earth in a single scoop to giant dumper trucks. The tallest ‘tower’ crane is 40 metres tall and can lift 16 tonnes. At peak construction there will be 50 ‘tower’ cranes at site.

£15 million is being invested into education, employment and skills to help inspire the next generation and provide people with the necessary training and support to help them into long term careers. Multi-million pound investments into a Construction Skills Centre and an Energy Skills Centre are not only ensuring that local people are equipped with the skills they need for the future, but helping to fill a national skills gap.

Latest news

Historic property magazine to close

Estates Gazette has been in business since 1858
7 hours ago

M&S Marble Arch rebuild approved after three-year planning fight

Plans were delayed when Michael Gove backed carbon campaigners
1 day ago

£191m revamp funding approved for London Barbican Centre

Construction to start in 2027 on five-year programme
24 hours ago

RED Construction tops £100m turnover

Builder maintains profit margin at 1.7% as business nearly doubles in size
15 hours ago

Timber designs shortlisted for roads ‘footbridge of the future’

Three of five designs for National Highways propose timber structures over busy highways
16 hours ago

PM pledges to fast-track 150 infrastructure schemes

Fresh promise to speed up planning decisions on infrastructure and house building
1 day ago

Amey FM firm fined after legionella kills prisoner

Court fines company £600,000 for prison upkeep failures
15 hours ago

Buyers report boom in commercial work

Construction bucks slowdown in general economy
2 days ago

Plans in for £250m Stockport 8 housing-led scheme

Work to start on phase 1 by the end of next year
2 days ago

Galliford Try tops monthly contracts league

Contract awards slow down in November
2 days ago

Erith explosives set demolition record at Sizewell

Watch blast at former nuclear turbine hall: Video
2 days ago

Vistry to build 950 homes next to Olympic Park

Developer signed for £600m Pudding Mill Lane scheme in East London
2 days ago

Inflatable formwork used for 45m tall cement silo

Ground-breaking dome silo inflated at Tilbury Docks
2 days ago

Briggs & Forrester sells maintenance arm

100 engineers to move over to new owner
2 days ago

£2bn Edinburgh ‘West Town’ scheme approved

7,000 homes to be built at 205-acre site
2 days ago

Rayner approves Lancashire super prison

Communities secretary overrules planning inspector for 1,700 inmate prison.
3 days ago

Wates boss returns after collapse of his own contractor

Paul Nicholls was head of the failed Real construction group
3 days ago

Trio secure Birmingham deal to retrofit 3,000 homes a year

Specialist contractors to install insulation, efficient heating and solar panels
3 days ago

Costain confirms £400m HS2 tunnels win

Work to start early next year on tunnel and lineside mechanical and electrical systems
3 days ago

First nuclear reactor installed at Hinkley: Video

Watch precision operation at Somerset site
3 days ago

Winner named for Harbourside revamp

Local Irvine contractor to start transformation of beach front
3 days ago

New Fair Payment Code goes live today

Latest bid to get subcontractors and suppliers paid within 30 days
4 days ago

Lincolnshire concrete supplier files administration notice

Ever Readymix Concrete & Screed operates three depots and a fleet of 20 trucks
4 days ago

Graham lands first deal on Liverpool’s largest brownfield site

Contractor bags infrastructure package on 10.5 hectare site
4 days ago

Bouygues UK boss to step down

Fabienne Viala to leave after eight years at the helm
4 days ago

Galliford Try scoops £87m brace of London jobs

Firm will redevelop a prominent corner building on Sloane Street in Chelsea
4 days ago

New HS2 boss Mark Wild starts amid prep for final TBM drives

Former Crossrail CEO starts with a sharp focus on controlling costs
4 days ago

Ten consultants land Thames Water major upgrade places

Firms will share £400m of fee work over next five years
4 days ago

Rayner ultimatum to fix all unsafe tall buildings by 2029

Recladding work must start on all 18m+ resi buildings by 2027
4 days ago

ISG administrator finds just £35m to pay down £1.1bn debt

Failed firm was set to report £148m blackhole from legacy jobs
5 days ago

Contractor services