Murphy to install 60km underground power cable

Aaron Morby 8 years ago
Share

J. Murphy & Sons is to install the entire 60km underground onshore cable route for the £2bn Triton Knoll wind farm.

A key part of the engineering challenge will see over 300 obstacles crossed by individual horizontal direction drills – three times more than what is believed to be the previous UK record for an infrastructure project.

Previously the most ever carried out in the UK to date was 100 during the widening of the M25.

As preferred contractor, Murphy will design and install the project’s critical onshore cable circuits, which will stretch from the point of landfall near Anderby Creek in Skegness, to a new-build substation at Bicker Fen, near Boston, to feed into the national grid.

In preparation for the works, Murphy will set up a new project office close to the cable route, which is eventually likely to house over 100 UK staff.

In addition, the civil engineering and specialist excavation and drilling works required will attract a large UK-based workforce for the duration of the installation.

Murphy CEO Steve Hollingshead said: “This is one of the biggest power projects that Murphy will have worked on and it’s a real marker of the upward direction in which our business is going, as we continue to develop and grow.
triton-knoll-kicks-off-archaeological-campaign-in-lincolnshire-768x628

Triton Knoll Project Director James Cotter said: “This will be an unprecedented engineering challenge, where Triton Knoll and Murphy are pushing the boundaries of innovation and technology to deliver one of the longest ever underground cable installations linked to an offshore wind farm.

“Our arrangement with Murphy really demonstrates how we are working towards delivering our target of at least 50% UK content across the lifecycle of the project.

“We anticipate important opportunities for local businesses both in terms of traditional sub-contracted works and wider support services.  We are determined that local companies will have visibility of contracts and the opportunity to bid for work on our project and we believe that local companies can be successful.

Triton Knoll wind farm scheme

 

Triton Knoll is being developed by German-based Innogy. The wind farm is located 32kms off the Lincolnshire coast. It has a planned installed capacity of 860MW, capable of supplying the equivalent of over 800,000 UK households per year, with renewable electricity.

Triton Knoll was awarded a Contract For Difference in September 2017, and expects to trigger a capital expenditure investment of around £2bn into much needed UK energy infrastructure. This will enable the delivery of some of the lowest cost energy generation for UK consumers.

The project is now progressing towards a financial investment decision likely in 2018 with full onshore construction starting shortly after, and offshore construction starting in 2020.First energy generation could be as early as mid-Q1 2021, with the project expecting to begin commissioning in 2021.

Latest news

HS2 first as giant bridge slid across live motorway

Watch timelapse footage of pioneering 4,600-tonne viaduct installation
40 minutes ago

Gilbert Ash breaks ground on £120m Wilde aparthotel

Staycity’s biggest London scheme gets underway in Shoreditch
51 minutes ago

Bennett wins brace of retirement home deals

Contractor to build more than 200 apartments for investor Octopus Capital
1 hour ago

Developer showed “total disregard” for site safety

Property firm fined £45,000 for failing to meet basic standards
1 hour ago

Watkin Jones takes £8.7m hit but eyes brighter 2026

A £2bn pipeline and stronger deal flow help rebuild confidence after a year of impairments
1 hour ago

Project manager caught running false invoice scam

Suspended sentence and ban for director after probe into offices to resi scheme
20 hours ago

Cardo nails £52m Sussex council homes roofing deal

Firm beats 14 rivals to take Lewes and Eastbourne roofing programmes
1 day ago

Bachy turnover sinks by over £100m as HS2 surge fades

Piling specialist reports slow year as mega projects step down
1 day ago

Van Elle finds buyer for loss-making Canadian arm

Two-year North America foray ends with £2.6m exit deal
1 day ago

£100m student halls to replace derelict London Crown Court

IQ student project gets go-ahead at Blackfriars court building site
1 day ago

Safety green light for Newcastle student scheme

Gateway 2 approval process delays construction start by a year
1 day ago

Plans go in for next phase of Manchester Waters

New neighbourhood planned for island site
1 day ago

JRL names new fit-out lead to drive expansion

Graham Ardley steps up to drive next phase of commercial and residential growth
1 day ago

Construction output yo-yos as growth falters again

Quarterly output down 0.3% amid cautious investor sentiment
4 days ago

Free school build plans axed to fund £3bn SEND expansion

Education secretary scraps 28 free schools to plug SEND shortfall
4 days ago

McLaren seals £160m funding for Manchester student tower

737-bed Upper Brook Street student scheme forward funded by L&G
4 days ago

Former McAlpine boss lined up for Royal BAM board role

Paul Hamer to replace Paul Sheffield on Dutch group supervisory board
5 days ago

Plans go in for £650m retail park to resi scheme

Construction could start in early 2027 on new neighbourhood for Lewisham
5 days ago

Lovell launches Midlands refurb division

Renew Central to be headed by Carl Yale
4 days ago

M Group muscles into top five contractors after growth spurt

Private-equity backed infra giant builds £8.8bn work mountain
5 days ago

Plans in for first major build phase of £2bn York Central scheme

Developers table plans for nearly 1,000 homes, parkland and York’s new western station gateway
5 days ago

Lords push for staged Gateway 2 approval to aid design and build

Inquiry warns BSR’s over-detailed Gateway 2 demands are freezing D&B process
5 days ago

CITB wage bill tops £52m as staff numbers jump 13%

Accounts show 182 people at training body earn £60,000+ a year
5 days ago

Peterborough electrical specialist files administration notice

EML Electrical Contractors lodges court notice
5 days ago

Ant Yapi UK lands latest Chelsea Barracks deal

Fit-out work on Building 7 will last until summer 2027
5 days ago

Go-ahead for plan to level Cambridge retail park for life-science hub

Minister overturns council refusal as Railpen’s scheme promises £600m economic uplift
6 days ago

Subcontractor competition keeps build costs flat at Berkeley

"Highly competitive tendering" expected to continue next year
6 days ago

Industry calls grow to scrap the CITB

Latest training cuts final straw for a lot of contractors
6 days ago

Green light for major Oxford Circus mixed use scheme

Construction to start in 2029 on revamp of BHS and London College of Fashion site
6 days ago

Coventry to back build of Very Light Rail street pilot

Council set to approve 800m twin-track route in push for rapid-build transport revolution
6 days ago