Centre Point Tower developer claws back £1m from McAlpine

Aaron Morby 4 years ago
Share

The developer behind London’s Centre Point tower conversion into luxury apartments has clawed back a £1m payment to Sir Robert McAlpine in the High Court.

Developer Almacantar and McAlpine became pitched against each other following a bust-up over delivering the project as a design and build job.

McAlpine was working on the £100m-plus project under a pre-construction service agreement (PCSA) signed in Spetember 2012. But by June 2014 ahead of moving to the next main contract stage, McAlpine said it would no longer entertain a design and build contract and proposed a construction management or management contract form of procurement.

Almacantar rejected the offer and the contract was terminated in September. Three months later Almacantar appointed Multiplex as the main contractor for the job.

The two then became embroiled in a dispute about whether the contract terms allowed a final part of McAlpine’s fee to be released under the PCSA agreement.

McAlpine contended that the previous two-stage contract terms allowed it to be paid a remaining 50% tranche of fee when any main contractor was appointed.

Almacantar argued that the terms of releasing the second part of the fee only applied once a main contract was agreed with McAlpine, not any other contractor.

Initially an adjudicator ruled in McAlpine’s favour, but the High Court has now backed Almacantar, ordering McApine to repay the £1.1m including interest awarded in the adjudication.

Justice Jefford said: “This is not a contract under which, if Almacantar exercised its right to terminate, it would, with impunity, avoid paying the second 50% of the fee.

“The purpose of the PCSA was to put Almacantar in a position to proceed with a well-planned design and build contract with developed contractor’s proposals and a robust contract sum.

“In most circumstances in which Almacantar terminated SRM’s engagement, Almacantar would to a greater or lesser extent lose those benefits and have to go back to the drawing board with another contractor.

“That would be the position if the parties could not reach agreement, if Almacantar was dissatisfied with SRM or if, as happened, SRM did not wish to proceed.”

Justice Jefford added: “The only circumstance in which Almacantar would have a windfall  – but a fairly valueless one – and SRM would be unfairly out of pocket would be if Almacantar decided not to proceed with the project at all.

“If on the other hand SRM’s construction of the PCSA were right, they would receive the second 50% of the fee even if its services had been of no benefit to Almacantar in engaging with another contractor.”

 

 

Latest news

Hill gets go-ahead for North London estate rebuild

750 homes to be built at Douglas Bader Park estate in Colindale
9 hours ago

Bid race for £210m Huddersfield town centre revamp

Kirklees Council's Cultural Heart scheme will be split into two major projects
11 hours ago

£100m Darlington Station revamp enabling works start

Willmott Dixon set to deliver major station upgrade project
13 hours ago

Demolition worker gets huge payout after losing leg

Compensation settlement will fund latest prosthetic limb technology for site victim
12 hours ago

Plant hirer Vp abandons sale plan

Chairman Jeremy Pilkington says the plant hirer failed to find a suitable new owner.
11 hours ago

Turner & Townsend on board for Sheffield Supertram upgrade

Consultant to help deliver programme over next seven years after £570m funding deal
12 hours ago

Green light for new £33m Ipswich logistics park

Construction to start this October on latest Trebor Developments site
13 hours ago

Piling starts on pioneering double composite HS2 viaduct

Wendover Dean Viaduct ‘double composite’ structure will halve carbon emissions
12 hours ago

ISG pauses work on £300m gigaplant

Construction work rescheduled to reduce costs at giant car battery plant
1 day ago

Tory leadership battle delays bidding for HS2 phase 2a

Prequalification for £5.2bn-£7.2bn route to Crewe put back to September
2 days ago

Greswolde Construction goes under

Solihull contractor ceases trading with 24 jobs lost
4 days ago

Hanson on track for UK’s first net zero cement works

20 carbon capture projects shortlisted for £1bn funding
1 day ago

Plan in for Nottingham 967-room student scheme

Vita submits plan for second major purpose built student sh
2 days ago

Galliford Try gets go-ahead for next A47 dualling job

Early 2023 start for £200m section of A47 between North Tuddenham and Easton in Norfolk
2 days ago

Designs revealed for £1bn London Blackfriars tower blocks

Fosters design landmark green office skyscraper and two blocks of flats for Southwark site
5 days ago

Everton stadium job still on budget despite inflation

Club and Laing O'Rourke confident they can still build new ground for £500m
5 days ago

Construction output falls 1.4% halting 7-month growth spurt

Fresh output and orders figures confirm summer construction slowdown
4 days ago

McLaren gets green light for £85m build-to-rent scheme

Construction set to start this autumn on major city centre development
5 days ago

BAM limbers up for £25m Bedworth leisure centre

Pioneering Warwickshire health and fitness hub to start this autumn
5 days ago

Keepmoat to start four-year build in Wigan

Major regeneration scheme to start across four sites
4 days ago

Solihull contractor Greswolde heading for administration

New investors took over business 12 months ago
5 days ago

Duo win £500m canal and river main works deal

Kier and Bentley bag Canal & Rivers Trust's largest ever water engineering works deal
6 days ago

Construction Manager of the Year finalists revealed

70 of the industry's brightest talents: Full list
6 days ago

Willmott Dixon fills new strategic change director role

Vistry Group change director joins private builder to support future growth
6 days ago

Work starts on £42m Oldham Spindles overhaul

Willmott Dixon signs off £42m deal to create new market, offices and event space
6 days ago

Firms wanted for Telford & Wrekin £1.6bn building works DPS

Call up for dynamic purchasing system covering building and refurbishment work
5 days ago

Kier pulls off contracts league double in July

Contractor bags highest value of new work and tops rolling 12 months ranking
7 days ago

Hinkley Point C giant water intakes craned onto seabed

Video: contractors complete one of the world’s most complex marine engineering projects
6 days ago

Taziker revenue jumps 30% to record £73m

Multi-disciplinary engineering specialist boosts headcount to 366 staff
6 days ago

Consultant buys scaffolding contractor

RSK Group makes MG Scaffolding its latest acquisition
6 days ago

Contractor services