National Grid set to invite £1bn tunnelling programme bids

Aaron Morby 6 years ago
Share

National Grid is preparing to invite bids in July for a major underground power line tunnelling programme worth nearly £1bn.

Ahead of the invitation to tender, National Grid is calling on all potential supply chain partners to express an interest to participate in a pre-procurement early market engagement process.

This is open to the full potential supply chain including shaft and tunnelling contractors, tunnel boring machine manufacturers, concrete segment manufacturers, mechanical and electrical contractors and tunnel ventilation contractors.

The three major projects include the 33km London Power Tunnels 2 project in South London, in North Wales the 4km long Menai Tunnel and a 3.3km programme of tunnelling in Snowdonia as part of its £500m visual impact provision programme to remove overhead pylons in area of outstanding beauty.

The largest of these is the £750m investment to future proof London’s electricity supplies.

In summer 2019, National Grid plans to begin work on the construction phase of the LPT2 project, building cable tunnels stretching from Wimbledon in south west London to Crayford in south east London. The tunnels, which will be up to 4m in diameter, will largely be buried deep beneath the streets.

They are needed to replace three existing electricity circuits that are coming to the end of their life. The project is expected to take about eight years to complete.

LPT2 follows on from the successful first phase of the London Power Tunnels work that we completed earlier this year.

In North Wales, National Grid is planning a 4km underground tunnel to carry cables connecting Wylfa Newydd power station to the main network to avoid using pylons at the popular beauty spot.

Construction of the £100m tunnel project is expected to take around five years. It would be buried around 40m under the existing seabed, measuring around 5m in diameter with tunnel boring machines used to drill under the surface.

On each side of the Strait, the cables will be installed in a vertical shaft that will be accessed through a head house building. These tunnel head houses will contain important equipment such as ventilation fans, which help keep air circulating inside the tunnel and help with cooling.

The tunnel head houses and sealing ends will be located together in an area two acres in size.

Costings for the 4km Snowdonia VIP scheme (pictured above) have not yet been made public. The stretch of nearly a dozen overhead pylons to be removed runs from the west coast at the Dwyryd Estuary near Porthmadog past Cilfor before climbing up towards the summit of Moel Tecwyn and beyond, finishing at the western side of Ceunant Llennyrch Valley.

On-site works will start in spring 2021 and take around three years to complete.

Additional information can be obtained from Tracey Walton at National Grid Electricity Transmission in Warwick. tel:  07813357313.

Latest news

Plans go in for huge Olympic Park construction hub

Bow Goods Yard could deliver 3.5m tonnes of materials a year to sites across London
9 mins ago

Surgo Construction went down owing £4.5m

Biggest creditor is Bellway Homes after dispute on housing job
3 hours ago

Plan for £100m Liverpool Baltic station

Construction work could begin next year
4 hours ago

Vistry seals £157m West London housing deal

Around 575 homes to be built at Merrick Place scheme in Ealing
2 hours ago

Streamlined Watkin Jones returns to profit in first half

Multi-room specialist sees secured work pipeline hit £1.4bn
2 hours ago

Bellway hires ex-brickie as group construction chief

James Griffin to oversee move to the Future Homes Standard and timber frame.
3 hours ago

Persimmon under fire for delays to £10m relief road

West Suffolk Council serves Breach of Condition Notices after timetable slips again
3 hours ago

BAM wins £33m Kent secondary school job

Replacement Swanley academy to be built at live school site
3 hours ago

Aluminium cladding specialist collapses

Melton Mowbray-based firm worked for several main contractors
1 day ago

Brickwork contractor Lee Marley returns to profit

Affordable and rental homes demand lifts brickwork contractor
1 day ago

Housing contractor Durkan suffers second year of losses

More fire safety provisions tip firm into £3.9m loss
1 day ago

Farrans makes breakthrough on tricky tunnel job

Tunnel under Tees latest part of new £155m water pipeline job
1 day ago

Heidelberg buys aggregates and earthworks specialist B&A

Latest deal follows acquisition of Mick George
1 day ago

Flagship biodiversity net gain scheme flawed

NAO warns Government's flagship green development scheme at risk of failure
4 days ago

Plan in for £3bn Lincolnshire mega data centre

3.3m sq ft Humber Tech Park will be one of Europe's largest data centres
4 days ago

Green light for Digbeth 1,300 homes scheme

Warner’s Fields scheme to start with excavation and landscaping of the River Rea
4 days ago

£210m M3 Junction 9 upgrade gains consent

VolkerFitzpatrick to start work in early 2025 on Winnall roundabout, near Winchester
4 days ago

United Living wins 14-year L&Q homes repairs deal

Trafford housing upkeep deal worth £205m
4 days ago

£400m Lewisham resi-led scheme advances

Land deal paves way for Amro Partners' 1,000-home London scheme
4 days ago

McLaren gets go-ahead for Grade II listed Leeds student scheme

Springfield House to be revamped and two new wings added
4 days ago

Piling giant to fit people alarms on all rigs

Cementation Skanska upgrades site safety systems
4 days ago

Vistry to make £800m profit after subcontractor cost cuts

House builder bullish about shareholder returns after asking suppliers for discounts
5 days ago

Shareholders approve £2.5bn Barratt and Redrow merger

Final hurdle is for the competition regulator to approve the deal.
5 days ago

Green light for £80m Leith waterfront revamp

Build-to-rent homes and student accommodation scheme to be built
5 days ago

Tilbury Douglas clears Interserve legacy jobs to return to profit

Revenue tops £500m in first year as standalone contractor
6 days ago

Land deal paves way for Manchester civil service office hub

Government buys five acres at former Central Retail Park
5 days ago

Speller Metcalfe wins Wolverhampton library upgrade

Full works are due to start in the autumn
5 days ago

Skills shortage puts big infrastructure projects at risk

Government failing as an intelligent client and now over-reliant on consultancies
6 days ago

Contractors face further insulation board price hikes

Cost of PIR insulation boards set to rise another 10%
6 days ago

Henry Boot wins £36m Rotherham Markets job

Project involves upgrading existing market and building a new library
6 days ago

Contractor services