Five key safety breaches identified at Grenfell

Aaron Morby 8 years ago
Share

Deficiencies in the windows, cavity barriers and the cladding system allowed Grenfell tower to be rapidly engulfed in the blaze that saw 71 people lose their lives.

A leaked interim report for the Metropolitan Police offers the most detailed assessment yet of the failures in the refurbishment of the building.

It concludes that the fire would not have spread beyond flat 16 on the fourth floor and would not have claimed even a single life if the original facade of the building had not been over-clad between 2014 and 2016.

Parts of the building were also close to collapse at the height of the blaze, but thicker than presently required floor slabs and columns appeared to have saved the building.

According to the London Evening Standard, which has seen a leaked copy of the draft report produced by experts at BRE Global, the refurbishment of the building failed to meet fire safety standards on several counts.

There were gaps of 15cm between the window frames and concrete columns. These were plugged with a rubberised membrane, rigid foam insulation and uPVC lightweight plastic panels, the paper reported.

These materials provided a fuel that allowed the fire originally to spread to the facade and later penetrate other flats as it spread up the exterior of the building.

Cavity barriers failed to seal the void between the original concrete building fabric and the external aluminium composite material cladding during the fire. These fire blocks were often too small, or incorrectly installed found investigators.

This allowed fire to spread rapidly through a chimney effect, particularly up exterior column lines.

The BRE report also finds insulation fitted to the outside of the building was combustible, allowing fire to spread up and across sections of the facade.

ACM cladding panels had flammable polyethylene or plastic cores this allowed fire to spread upwards and across the building ,with burning droplets of polyethylene also falling and igniting combustible materials below.

Taken together the failings in the cladding system proved of greater significance taken together than in isolation.

The report also identifies a lack on door closers which meant that as tenants fled many were left open allowing smoke and fire to spread through corridors, impacting on residents escape down the single stairwell.

It also says that Grenfell should have been fitted with a wet riser main to aid firefighting rather than a dry riser and only enough room around the building for single fire engine to get close to supply water.

The report has not explicitly concluded whether the design or installation was at fault and whether works were approved or inspected.

Latest news

Caldwell Construction collapses into administration

Insolvency specialist PKF Littlejohn appointed after rescue talks fail
2 days ago

£56bn hospital programme on track but delivery risks remain

NAO warns tight schedules and staff shortages could derail later waves
1 day ago

Modular firm backs ‘new chapter’ for Merit

Directors form new company after original offsite business crashed owing suppliers millions
1 day ago

A9 dualling switches to £1.9bn framework model

Bidding set to start for framework to deliver final five Highland sections
2 days ago

Kier set for £21m Edinburgh towers upgrade

15-storey buildings to get insulation upgrade
1 day ago

Rebar giant loses high court fight to save Chatham Docks base

High Court rejects judicial review paving way for Basin3 business park redevelopment
1 day ago

Heathrow kicks off third runway pre-planning design work

Airport targets 2029 consent with key policy calls looming in 2026
2 days ago

Civils firm Caldwell Construction files administration notice

Hundreds of workers sent home as Midlands firm says it is trying to find an investor
2 days ago

CW Plant Hire kit goes under hammer in fleet renewal sale

Euro Auctions to sell off used equipment next month
2 days ago

Henry creditors payout hangs on £31m family legal fight

Administrators say trade creditor dividend hinges on lawsuit against Henry directors and family
2 days ago

Ex-directors buy back Boutique Modern in £24k pre-pack deal

Modular housing firm reborn as BM Modular but creditors face £4.3m shortfall
2 days ago

Autumn Budget jitters knock construction output back

Uncertainty ahead of November statement triggers biggest quarterly fall since early 2023
2 days ago

Industry standards body racks-up huge loss

Accounts query invoices from firms linked to former leaders
3 days ago

Taylor Wimpey braces for margin squeeze this year

Lower opening order book and weaker margins shape cautious outlook
2 days ago

Green light for Ballymore 1,685 homes site

Go-ahead for latest redevelopment site in Royal Docks
2 days ago

Building boss fined for ignoring safety warnings

Court hands out fines after catalogue of safety concerns on pub conversion job
3 days ago

Treasury unlocks £1.1bn to revive Northern Powerhouse Rail

Cash to kick off design work on £45bn scheme ahead of 2030s build
4 days ago

Kier Construction appoints new southern region chief

Former Bouygues regional MD John Boughton joins Kier
3 days ago

Vistry saved by second half margin rebound to 8.4%

Cost control, site mix and partnership housing drive margin rebound
3 days ago

USA contractor acquires London super-prime specialist

Remian looks to expand in UK with deal for construction manager Rossco
3 days ago

McLaren takes 256-bed Leeds student tower job

Developer Pullans gets green light for Joseph’s Well student scheme
4 days ago

Milton Keynes plans £76m events venue

Operator chosen for 4,000-capacity scheme
3 days ago

Tower crane drivers set to strike

SItes could stop amid pay row with Wolffkran
4 days ago

Winvic wins £340m M&S mega shed at DIRFT

Low-carbon Midlands 1.3m sq ft twin sheds set to anchor food growth plans
5 days ago

Father-of-six dies in demolition site tragedy

Fatal accident while demolishing flats in Renfrewshire
5 days ago

Persimmon builds momentum with 12% jump in completions

House builder warns there will be no material uplift in market this year
4 days ago

Henry Boot seals planning for Goole 5.5m sq ft freeport

HBD partnership targets start on site this year for £130m first phase
4 days ago

FP McCann buys roofing products firm Easy-Trim

Concrete specialist acquires firm out of administration
4 days ago

Trade body BESA boots out five more firms in standards purge

Building engineering services body chief says race to the bottom is over
5 days ago

Bidders day set for £4.5bn Southern Construction Framework

Around 20 contractors brace for fight to retain places on sixth-generation mega deal
5 days ago