London roads upkeep JV loses court battle with TfL

Aaron Morby 7 years ago
Share

A joint venture working on road maintenance in central London has lost a High Court battle with Transport for London over work rates.

Colas, VolkerHighways and AECOM got involved in a rates row arguing that strict working time constraints placed on it by TfL delayed and prolonged work requiring extra shifts and added costs.

The CVU joint venture believed there would be a window for night-time noisy works of 4.5 hours between 7.30pm and midnight. In practice this was severely curtailed by permit conditions.

CVU argued it was therefore entitled to claim for the cost impacts of the restriction with revised rates and prices. But TfL maintained that agreed rates and uplifts in the existing agreements covered all limitations or restrictions on working conditions.

CVU announced that it was planning to quit its framework agreement in February, which was due to run to March 2021, but said this was due to removal of Government operating subsidies for road maintenance and not as a result of the rates dispute.

Ringway Jacobs has since taken on work and staff in the central London area where CVU was operating.

Now a High Court judge has ruled that TfL was right to argue that previously agreed rates applied under the London Highways Alliance Contract framework.

Justice O’Farrell said: “CVU makes a valid point that the framework agreement does not contain definitive hours and other conditions in which the works under task orders must be carried out.

“That introduces uncertainty as to the duration, scope and cost of work required. Any requirement by CVU to price such uncertainties would result in uncommercial high rates.

“There is a risk that contractors could include a premium for the risk of uncertain restrictions on working if forced to price them at the outset.”

The judge added: “However, that is balanced by the competitive tendering that applied for the framework agreement, and the volume and spread of works, from those at high risk of imposed restrictions to those at low risk of imposed restrictions. The inbuilt uncertainty introduced risk for both parties that could be assessed and evaluated.

“The purpose for which the schedule of rates was required was to provide consistency and certainty in the pricing of the works. The use of a schedule of rates enabled TfL to evaluate the tenders on a fair and equal basis. The fixing of rates and prices for the framework agreement provides opportunity and risk for both parties.

“If CVU undertakes the work instructed in a shorter duration or at lower cost than anticipated, it will receive a ‘windfall’ and TfL will have ‘overpaid’. If CVU incurs greater costs than anticipated, it will have to bear the loss and TfL will have made a saving.

“It was a matter for each party to assess the risks associated with permits issued and to price those risks accordingly.”

A spokeswoman for CVU said: “CVU would like to reiterate that they are in discussions with TfL to consider stepping down from core work in the central London area.  This action was agreed prior to the result of the recent court case being announced, and is in response to the removal of the government operating subsidy.”

Latest news

Thames Water seeks tunnelling contractors

Bidding launched for £242m Teddington drought resilience scheme
2 days ago

UK’s biggest data centre plan breaks cover in Lincolnshire

Plans submitted for £7.6bn AI hyperscale build near Scunthorpe
2 days ago

Government seizes control to fast-track £5bn reservoir plan

Ministers bypass local planners for Lincolnshire and Fens reservoir projects
2 days ago

London council unveils £150m housing estate revamp plan

Hackney gears up to deliver 341 infill homes at De Beauvoir estate
2 days ago

Worker injured during prep work at Persimmon site

Houlihan & Co worker airlifted to hospital
3 days ago

Morrisroe sales slide 15% but group edges back into profit

Turnover hit by safety regulator brake on new high rise resi projects
3 days ago

First platforms installed at HS2 Old Oak Common station

Balfour Beatty VINCI SYSTRA starts station fit-out work: Video
2 days ago

Murphy hikes profit 25% to £84m as orders smash £5.4bn

Order book jumps by nearly two-thirds as firm extends global reach
3 days ago

Cladding specialist EAG files administration notice

Sister firm of failed contractor Alucraft lodges court notice
3 days ago

John Lewis wins battle to build four resi towers above store

Ardmore in frame for landmark £240m Ealing towers plan above new Waitrose
3 days ago

Restructure pays-off for HG Construction

Turnover down but profit up as Building Safety Act delays schemes
3 days ago

Mace confirmed for £100m Natural History Museum job

Construction to start imminently at Thames Valley site
4 days ago

McAleer & Rushe starts £90m Birmingham student rooms job

Selly Oak project will transform derelict supermarket site
4 days ago

20 firms win £577m public estate maintenance framework

Procurement Assist signs off four-year framework for cyclical works
3 days ago

Cubby in talks over rescue restructure after civils job setback

Carlisle contractor hit by Carlisle Southern Link Road losses
4 days ago

Rayner rips up rules to get small builders building

Wildlife habitat rules and building safety levy dropped on sites up to 49 homes
4 days ago

Cladding costs recovery helps Willmott Dixon return to profit

Contractor claimed back £20m from third parties last year
4 days ago

£35m Hereford Western Bypass job to go to tender

Phase 1 tender set for September with design element included
4 days ago

GEG Capital swoops for high-voltage cable contractor APS

Inverness investor continues market expansion with deal for St Helens cable firm
4 days ago

Blackburn seeks bidders for £250m framework

Council starts tender process for major eight-year deal
4 days ago

House builders to face fines for dragging feet on site starts

New powers will let councils penalise slow developers and reclaim stalled plots
5 days ago

HS2 investigation into labour supply pay rates

Probe follows claims that self-employed workers were charged out at PAYE rates
5 days ago

Rydon narrows losses as £27m spent on fire safety repairs

Post-Grenfell work provisions increased to £19m
5 days ago

McLaren lands Boxing Academy school

Contractor starts work on East London site
5 days ago

Firms wanted for £1.5bn green housing retrofit deal

Procure Plus opens bidding for low-carbon housing upgrades framework
5 days ago

Waterloo Station revamp plan advances with new regeneration pact

15-year improvement scheme back on track with new partnership deal
5 days ago

Groundworks firm Corbyn goes under

£33m-turnover specialist now in hands of administrators
1 week ago

Home office says sorry to FP McCann after site raid

Precast concrete contractor wins damages over "entirely erroneous and unfounded allegation"
1 week ago

Race on for £60m London Gateway container yard job

Civils and M&E job up for grabs at Berth 5
1 week ago

How Construction Enquirer can boost your business

Promote your business to a vast industry audience
1 week ago

Contractor services