London roads upkeep JV loses court battle with TfL

Aaron Morby 6 years ago
Share

A joint venture working on road maintenance in central London has lost a High Court battle with Transport for London over work rates.

Colas, VolkerHighways and AECOM got involved in a rates row arguing that strict working time constraints placed on it by TfL delayed and prolonged work requiring extra shifts and added costs.

The CVU joint venture believed there would be a window for night-time noisy works of 4.5 hours between 7.30pm and midnight. In practice this was severely curtailed by permit conditions.

CVU argued it was therefore entitled to claim for the cost impacts of the restriction with revised rates and prices. But TfL maintained that agreed rates and uplifts in the existing agreements covered all limitations or restrictions on working conditions.

CVU announced that it was planning to quit its framework agreement in February, which was due to run to March 2021, but said this was due to removal of Government operating subsidies for road maintenance and not as a result of the rates dispute.

Ringway Jacobs has since taken on work and staff in the central London area where CVU was operating.

Now a High Court judge has ruled that TfL was right to argue that previously agreed rates applied under the London Highways Alliance Contract framework.

Justice O’Farrell said: “CVU makes a valid point that the framework agreement does not contain definitive hours and other conditions in which the works under task orders must be carried out.

“That introduces uncertainty as to the duration, scope and cost of work required. Any requirement by CVU to price such uncertainties would result in uncommercial high rates.

“There is a risk that contractors could include a premium for the risk of uncertain restrictions on working if forced to price them at the outset.”

The judge added: “However, that is balanced by the competitive tendering that applied for the framework agreement, and the volume and spread of works, from those at high risk of imposed restrictions to those at low risk of imposed restrictions. The inbuilt uncertainty introduced risk for both parties that could be assessed and evaluated.

“The purpose for which the schedule of rates was required was to provide consistency and certainty in the pricing of the works. The use of a schedule of rates enabled TfL to evaluate the tenders on a fair and equal basis. The fixing of rates and prices for the framework agreement provides opportunity and risk for both parties.

“If CVU undertakes the work instructed in a shorter duration or at lower cost than anticipated, it will receive a ‘windfall’ and TfL will have ‘overpaid’. If CVU incurs greater costs than anticipated, it will have to bear the loss and TfL will have made a saving.

“It was a matter for each party to assess the risks associated with permits issued and to price those risks accordingly.”

A spokeswoman for CVU said: “CVU would like to reiterate that they are in discussions with TfL to consider stepping down from core work in the central London area.  This action was agreed prior to the result of the recent court case being announced, and is in response to the removal of the government operating subsidy.”

Latest news

Morgan Sindall to build former Willmott Dixon leisure job

New contractor appointed on
15 hours ago

Graham consortium wins £400m Manchester job

Equitix consortium to now work up DBFO plans for University of Manchester’s Fallowfield Campus
11 hours ago

Keltbray looking to sell infrastructure business

£378m turnover rail, energy and highways business up for sale
22 hours ago

Innovative viaduct building method used for first time in UK

HS2 contractors will build nine viaducts in Delta Junction using special cantilevered process
22 hours ago

Unite buys London site to fast-track 444-bed student scheme

£800m to be spent on London development pipeline in next five years
22 hours ago

CITB awards £2.5m of contracts to management consultant

Three outsourced deals in the last year for "project leadership and management consultancy"
22 hours ago

Village centre approved for 6,000-home new town plan

Hampshire's Welborne Garden Village plan has been in the pipeline for two decades.
21 hours ago

£3m fine after cherry picker demolition death

Court rules after tragedy during decommissioning of gas rig
22 hours ago

BAM plans wave of job cuts at UK Construction arm

Co-op Live arena plunges Bam Construction to £19.5m first-half loss
2 days ago

Robot tunnel builder goes into administration

Hypertunnel was hoping to revolutionise how underground structures are built
2 days ago

Wates to build £86m Guildford Council housing scheme

40% of the 248 homes will become council homes under partnership deal
2 days ago

“Scrap CITB” say three quarters of construction firms

Payroll giant Hudson Contract calls for CITB to be absorbed into new Skills England training body
2 days ago

£100m Prestwich Village revival approved

Vinci and Willmott Dixon in chase for Muse-led regeneration scheme
2 days ago

Carbon negative asphalt aggregate trialled on M11

Skanska and Tarmac test CO2 absorbing aggregate material on stretch of Essex motorway
2 days ago

Father and son sentenced over covid construction loan fraud

Bristol builders given suspended jail sentences over bogus Bounce Back Loans
2 days ago

Beck Interiors files administration notice

Supply chain has suffered delayed payments from £139m-turnover luxury fit out specialist
3 days ago

Green light for York Central civil service office hub

£60m office project accelerates York Central goods yard redevelopment
3 days ago

Blenheim House Construction enters administration

Administrators looking at options on present projects
3 days ago

Profits rise at Esh Group with more to come

Contractor confident about year ahead as market conditions move in right direction
3 days ago

Piling specialist Van Elle sees housing orders rise 30%

Mark Cutler says firm on course to deliver 10% annual sales growth
3 days ago

HS2 to spend £100m shutting sites where work never started

Remediation of sites no longer needed for cancelled Phase 2 will take three years
4 days ago

Willmott Dixon wins £61m deal for new Army dog unit

Contractor to revamp Kendrew Barracks in Rutland
3 days ago

Stockport advances 4,000-home Town Centre East plan

Council seeks consultants to steer plan for 280-acre area in the city
3 days ago

ISG sale imminent as buyers set-up UK holding company

South African nutrition entrepreneur and Australian partner primed to take over
4 days ago

CR Construction wins £210m Manchester towers

Construction to start next year on four blocks ranging from nine to 34-storeys
4 days ago

Southern Housing to rationalise supply chain following merger

Firms put on alert for £1.7bn construction framework renewal
4 days ago

Decision delayed on 52-storey Isle of Dogs tower

Hong Kong developer plans 460 flats block next to Millwall Inner Dock
4 days ago

Go-ahead for £850m North London estate rebuild

Flagship Edmonton housing estate redevelopment will deliver 2,000 new homes
4 days ago

Mace lands £184m Oxford Science Park contract

Contractor to build trio of laboratory and office buildings
5 days ago

Worker paralysed in 30ft fall during electricity pylon demolition

Specialist firm fined £240,000 after court hears linesman attached lanyard to a loosened steel section
4 days ago

Contractor services