London roads upkeep JV loses court battle with TfL

Aaron Morby 7 years ago
Share

A joint venture working on road maintenance in central London has lost a High Court battle with Transport for London over work rates.

Colas, VolkerHighways and AECOM got involved in a rates row arguing that strict working time constraints placed on it by TfL delayed and prolonged work requiring extra shifts and added costs.

The CVU joint venture believed there would be a window for night-time noisy works of 4.5 hours between 7.30pm and midnight. In practice this was severely curtailed by permit conditions.

CVU argued it was therefore entitled to claim for the cost impacts of the restriction with revised rates and prices. But TfL maintained that agreed rates and uplifts in the existing agreements covered all limitations or restrictions on working conditions.

CVU announced that it was planning to quit its framework agreement in February, which was due to run to March 2021, but said this was due to removal of Government operating subsidies for road maintenance and not as a result of the rates dispute.

Ringway Jacobs has since taken on work and staff in the central London area where CVU was operating.

Now a High Court judge has ruled that TfL was right to argue that previously agreed rates applied under the London Highways Alliance Contract framework.

Justice O’Farrell said: “CVU makes a valid point that the framework agreement does not contain definitive hours and other conditions in which the works under task orders must be carried out.

“That introduces uncertainty as to the duration, scope and cost of work required. Any requirement by CVU to price such uncertainties would result in uncommercial high rates.

“There is a risk that contractors could include a premium for the risk of uncertain restrictions on working if forced to price them at the outset.”

The judge added: “However, that is balanced by the competitive tendering that applied for the framework agreement, and the volume and spread of works, from those at high risk of imposed restrictions to those at low risk of imposed restrictions. The inbuilt uncertainty introduced risk for both parties that could be assessed and evaluated.

“The purpose for which the schedule of rates was required was to provide consistency and certainty in the pricing of the works. The use of a schedule of rates enabled TfL to evaluate the tenders on a fair and equal basis. The fixing of rates and prices for the framework agreement provides opportunity and risk for both parties.

“If CVU undertakes the work instructed in a shorter duration or at lower cost than anticipated, it will receive a ‘windfall’ and TfL will have ‘overpaid’. If CVU incurs greater costs than anticipated, it will have to bear the loss and TfL will have made a saving.

“It was a matter for each party to assess the risks associated with permits issued and to price those risks accordingly.”

A spokeswoman for CVU said: “CVU would like to reiterate that they are in discussions with TfL to consider stepping down from core work in the central London area.  This action was agreed prior to the result of the recent court case being announced, and is in response to the removal of the government operating subsidy.”

Latest news

Brookfield gets green light for latest City office scheme

Retrofit-first approach will retain 70% of the original structure at 1 Moor Lane
2 hours ago

Ex-Lendlease boss seals £24bn Crown Estate mega sites JV

Crown Estate/Lendlease alliance to build out at Euston, Silvertown and Thamesmead sites
8 hours ago

Knauf commits £170m to build Deeside insulation plant

Work to start next year at former Shotton steelworks site
6 hours ago

Construction trade bodies vote to keep training levy

CITB gets green light to collect contractor's cash for another three years
7 hours ago

McLaren to build 2,400-bed worker campus at Sizewell C

Worker camp to raise the bar on site accommodation standards
10 hours ago

Soaring costs and work drought sunk historic scaffolding firm

Rodells had been in business since 1898
10 hours ago

Clarion set to tender £79m Kirkstall Road Phase 2

Bidding to start for Dyecoats blocks 1 and 3 after Graham bagged phase 1
10 hours ago

TfL seeks firms for £700m civils and station framework

Works include £80m South Kensington and £60m Elephant & Castle station upgrades
11 hours ago

Early market talks on £2.5bn Yorkshire mass transit plan

Supplier talks open for West Yorkshire’s biggest ever transport scheme
10 hours ago

Robertson starts Redcar town centre revamp

Culture and Leisure Anchor Attraction will enhance Redcar’s Esplanade
10 hours ago

Alun Griffiths set to rescue firm he sold for £36m

Tarmac to hand back Welsh civils contractor after five years of losses
3 days ago

Landsec to pump £2bn into new house building drive

Developer to build 6,000 homes as it sells offices to fund new schemes
3 days ago

Severfield to start steel on McAlpine car battery site

Specialist to start on £4bn site next month after steel package signed-off
3 days ago

Construction Manager of the Year crowned

Jason Hunt of Willmott Dixon wins for work on Bristol concert hall
3 days ago

Tide gets go-ahead for over 1,000-home London scheme

Volumetric expert gains planning for co-living homes scheme in Southwark
4 days ago

Vital Energi lands £250m Gatwick decarbonisation deal

Five-year programme to switch airport away from gas heating
3 days ago

Construction output flickers into life in March

First quarter activity flatlines after slow start to year
4 days ago

Skanska lifts margin to 4.3% as profit hits £78m

Infrastructure and FM drive near-tripling of profits
5 days ago

Mayor backs 46-storey student tower at Canary Wharf

City Hall overturns Tower Hamlets council rejection of 912-bed scheme
5 days ago

Plans go in for 100 acre Port of Tilbury expansion

Construction could start next year on site the size of 70 football pitches
4 days ago

Inland Homes creditors face £38m hit

Administrator confirms no cash for supply chain
5 days ago

Durkan dogged by legacy jobs despite return to trading profit

Durkan scales down new homes contracting to focus on retrofit work
5 days ago

Munnelly founder hands over CEO role to son

Paul David Munnelly steps up to CEO as father becomes chairman
4 days ago

Barking build to rent towers face rebuild

Major remedial work needed on resi scheme built by Shapoorji Pallonji UK Ltd
5 days ago

London new home starts plunge 38% as Building Safety Act bites

Capital only region to see Q1 fall in NHBC new home registrations
6 days ago

Sureserve swoops for rival compliance outfit Kinovo in £56m deal

Recommended cash offer will take AIM listed contractor private
5 days ago

Crown Golf tees up £1bn plan to build 3,000 homes on course land

Major housing plan for spare land on eight UK courses
5 days ago

Green light for Peterborough Station Quarter £48m revamp

First phase to start before the end of the year
5 days ago

Morgan Sindall starts £38m Caerphilly leisure hub

New swimming pool and health suite forms part of town regeneration plan
5 days ago

145 firms win places on £800m building safety framework

Fusion21 confirms latest winners: Full list
6 days ago

Contractor services