Faulty tower scaffold led to fatal roof fall

Grant Prior 7 years ago
Share

A Maidstone company has been sentenced after a maintenance worker fell five metres through a roof and died.

Folkstone Magistrates’ Court heard that on, 23 September 2015, Justin Hewitt fell through an opening that was being created on the roof of the premises of Maidstone Studios Ltd.

An HSE investigation found the tower scaffold used to access the roof was damaged, had not been correctly erected and had been purchased second hand by Maidstone Studios Limited with no manufacturer’s instructions.

No formal planning had been recorded for the work, which was outside the scope of the general maintenance duties of the team.

The work had been discussed, and planned to be carried out from below, but no-one identified the errors with the towers, ladder sections being the wrong way round, damaged bracing or the inadequate guardrails.

The towers were erected by Hewitt, but he had been given no formal training on how they should be erected safely.

Although he was supervising the work, no checks were made of how it was actually being carried out.

Maidstone Studios Ltd pleaded guilty to safety breaches and was fined £30,000 and ordered to pay costs of £6,487.76.

HSE inspector Stephen Green said: “Had the work been properly planned with suitable access equipment, correctly placed and erected, by those with adequate training, the work could have been done safely and this tragedy could have been averted.

“Falls from height remain one of the most common causes of work related fatalities in this country and the risks associated with working at height are well known.”

Latest news

Go-ahead for City of London’s tallest tower

1 Undershaft building will equal the Shard in height
2 days ago

Construction T Level scrapped due to lack of demand

Courses canned after less than 100 sign-up for latest round
3 days ago

Five firms clinch £300m Greenwich Uni framework deal

McLaren, Wates, Morgan Sindall, Vinci and Willmott Dixon secure places
2 days ago

Hill Group strikes first Build to Rent deal

House builder agrees finance with Lloyds Living to start Stevenage scheme
2 days ago

Construction output hit by fall in repair and maintenance

Industrial and commercial new work grows despite wider fall in activity
2 days ago

Wates transfers pension scheme to “superfund”

Pension management specialist Clara to take charge of £210m fund
2 days ago

Muse hires new development director for North West

Tom Darby joins from developer Bruntwood
2 days ago

Bid rigging probe launched into school repair work

Firms raided this week with focus on roofing contracts
4 days ago

McLaren hires ex-ISG regional boss for north east expansion

Andrew Beaumont becomes MD of new Yorkshire and North East business
3 days ago

Government commits to four new prisons in seven years

£2.3bn pledged for new prison build programme
4 days ago

Road and rail delays hit revenue at Van Elle

Turnover drops 5% as markets remain challenging for piling specialist
3 days ago

Boot reports ‘noticeable improvement’ in planning system

Government planning reforms already unblocking council planning
3 days ago

Go-ahead to revamp former London city hall

Project will straighten the building's leaning profile with terraces to every level
4 days ago

United Living to divert Midlands gas pipeline

600m pipeline diversion clears way for M54 to M6 link road construction
3 days ago

Credit insurance saves Billington from ISG hit

Steel specialist puts on extra shifts at its plants to cope with demand
4 days ago

M&E specialist Dodd doubles profit on retrofit surge

Family-owned Telford specialist delivers record revenue of nearly £250m
4 days ago

Go-ahead for 800-home Croydon dual towers

One Lansdowne Road build to rent scheme to cost £260m to build
4 days ago

Construction inflation set to return raising tender prices

End of 2024 to mark the bottom of present inflationary trough
4 days ago

Start date for vast Balfour and Costain carbon capture power job

£4bn Teesside project to start construction next year creating 3,000 jobs
5 days ago

Plans go in to start revamp of North Finchley town centre

Developer Regal unveils first details of Barnet masterplan
4 days ago

Glencar bags £18m Big Yellow London store

Six-storey stoarage centre to be built at Staples Corner
4 days ago

Plan unveiled for 31-storey London Fenchurch Street tower

Demolition work to start in 2026 for new office tower
5 days ago

Vinci Building buys tower cranes for first time

Contractor invests in two WOLFFKRAN all-electric cranes at £138m Sheffield site
5 days ago

30 local firms land United Utilities £500m framework

Minor works deal win for North West civils and M&E specialists
5 days ago

Restructure pays off as Higgins returns to profit

Housing contractor recovers from £25.9m loss last year
5 days ago

Former Heathrow boss joins Mace in board rejig

Firm completes string NED appointments to expanded group board
6 days ago

Planning officers to get powers to bypass committee stage for housing

Rayner reform plan to cut out local council planning committees
6 days ago

National Insurance hike to delay construction recovery

Arcadis paints varied picture with full recovery delayed until 2026
6 days ago

Gratte Bros rides out cost rises with profit increase

M&E specialist warns of further upward pressure on wage costs
6 days ago

Sellar’s 36-storey London City office tower approved

Demolition work to start in 2026 at 60 Gracechurch Street site
1 week ago

Contractor services