Number of private high-rises with flammable cladding soars

Aaron Morby 5 years ago
Share

The number of high-rise blocks  believed to be fitted with Grenfell-style cladding has soared following studies of over 6,000 buildings.

Neary 300 privately-owned high rises need to be reclad, with nearly three quarters without a remediation plan
Neary 300 privately-owned high rises need to be reclad, with nearly three quarters without a remediation plan

Latest estimates from the Government reveal there are now more private tower blocks of 18 storeys or above in need of remediation than social housing blocks.

The figure is more than double that believed at risk in May. Of the 297 high-rises expected to fail tests private owners of three quarters have failed to notify Government of plans to remediate despite warnings.

It also admitted this figure could rise further because the cladding status of another 170 private sector residential buildings is still to be confirmed.

Housing secretary James Brokenshire has unveiled fresh measures including a new expert taskforce to drive forward swifter action by building owners to remove potentially unsafe cladding on private sector high-rise residential buildings.

For the majority of these remaining buildings, enforcement notices have now been issued to get information on building construction from owners.

Based on current evidence and the identification rate to date, The Government expects 3-5% of the remaining buildings to have similar ACM cladding systems to those which have failed large-scale system tests.

Total high rise buildings with ACM cladding unlikely to meet building regs
14 June figs 22 May figs
Social-sector residential 159 159
Private-sector residential 297 138
(a)BRE tested 141 138
(b) Local authority confirmed 156 na
Publicly-owned buildings 14 14
Total ACM buildings 470 311

It said that only 19 of the total buildings have so far had their dangerous cladding replaced, leaving tens of thousands of people living in buildings at risk.

Brokenshire said: “I have been clear that leaseholders should be protected from unfair costs and we expect the industry to do the right thing. If they don’t, I will continue to explore other routes and I am not ruling anything out.”

He added that while remediation work has begun on 21 of these private buildings buildings, of which 4 have been completed, the government was determined to accelerate the pace of this work.

New measures

  • A new taskforce will oversee a national programme of remediation in the private sector and ensure plans are in place for every single building affected. The taskforce will be chaired by ministers and membership will include Local Government Association, National Fire Chiefs Council, London Councils and local authorities who have experienced the largest degree of impact and industry representatives.
  • A new inspection team, backed by £1m government funding, consisting of experts from environmental health, building control and fire inspection to support councils with enforcement action and ensure building owners take the necessary action and speed up the remediation process.
  • A follow-up industry roundtable next month so representatives can present their proposals on solutions to remove unsafe cladding from high-rise buildings without passing on the costs to leaseholders. In the meantime, the housing ministry will supporting local authorities to take more targeted action to identify and remediate affected buildings and recovering costs from those responsible for ensuring the safety of buildings; and supporting leaseholder enfranchisement.
  • Letters will be sent to all relevant private sector building owners to remind them of their responsibility to make their buildings safe.

Latest news

Lonsdale went down owing £65m to supply chain

More than 600 firms owed money as reduced credit rating sinks M&E giant
2 hours ago

Hunt for delivery partner to revive New Hospital Programme

Programme delivery partner to get £600m fee to get plans back on track
13 hours ago

Green light for new £780m Essex garden village

3,700 homes and four new schools to be built at Dunton Hills
10 hours ago

Laing O’Rourke makes a £288m loss

Rampant inflation on fixed-price jobs and problem contracts blow hole in accounts
18 hours ago

Keltbray, OCU and Clancy clinch £1bn electricity network upgrade

Scottish and Southern Electricity Networks awards biggest ever deals for central southern England
2 days ago

G&T enlisted for commercial review of HS2 main civils contracts

Phase 1 Main Works Civils Contracts to come under cost scrutiny
16 hours ago

TClarke order books doubles to top £1bn for first time

M&E specialist on track to exceed £500m turnover this year
17 hours ago

Wates signs Government safety remediation pact

Private builder belatedly signs fire safety developer remediation contract
18 hours ago

Liverpool all-electric industrial park approved

McLaren and Caddick in chase for Sefton 800,000 sq ft Atlantic Park scheme
1 day ago

Former Buckingham Group MD to join John F Hunt

Simon Hyams is new Managing Director for Contracting
2 days ago

Three in race for retendered £150m A9 dualling job

Bidders take another look after client takes on more risk
2 days ago

Clancy tops £300m revenue in fifth year of growth

Civils contractor delivers £13.5m pre-tax from water and energy sector work
2 days ago

Tower crane collapses on Edinburgh resi site

Jib falls onto apartment block under construction: Video
3 days ago

Salboy drops office space from Viadux Phase Two

Developer to focus on Manchester residential towers of 76 and 23 storeys
3 days ago

Warwick Uni plan for science and engineering campus

370,000 sq ft science and engineering precinct submitted for planning
2 days ago

Morgan Sindall chalks up Greater Manchester schools treble

Bury, Stockport and Wythenshawe school jobs will create 1,600 pupil places
2 days ago

Plans in for £65m Blackpool multiversity campus

Council leads plan for Talbot Gateway learning campus
2 days ago

Laing O’Rourke wins first phase of £700m Oxford R&D district

Landmark Red Hall and two labs to be built in phase 1a of Oxford North scheme
4 days ago

Ardmore wins retrofit deal on £200m Chancery Lane office

Building will be transformed to provide 105,637 sq ft of office space
3 days ago

Construction’s “Leading Lights” recognised

More than 50 winners in latest Considerate Constructors Scheme awards
3 days ago

Balfour Beatty clinches £20m Norfolk coastal defence jobs

Firm will install rock armour at Cromer and Mundesley
3 days ago

Architects join construction union Unite

Section of Architectural Workers forms official branch
4 days ago

Boot to build £20m lightweight aviation composites factory

Work starts on Sheffield University's COMPASS R&D facility
3 days ago

GMI secures £27m Leeds City College job

Site clearance underway for new Mabgate campus
4 days ago

Balfour signs deal with Koreans for UK power transmission jobs

Contractor strengthens large-scale onshore power transmission capability
4 days ago

36 storey south London build to rent flats tower approved

Construction to start next year on £220m Croydon scheme
4 days ago

Hunt for firms for £400m volumetric offsite deal

Procurement for Housing aims to expand its pool of firms on major offsite framework
4 days ago

Graham wins £87m Jock’s Lodge junction upgrade

Spring start for East Riding A164 improvement scheme near Beverley
7 days ago

Giant concrete pour at HS2 Curzon Viaduct: Video

Over 2,000 cubic metres create the first two 90 metre viaduct deck structures,
4 days ago

Cladding safety contractors told to wear body cameras

Insurance giant AXA to record remedial work
4 days ago

Contractor services