Number of private high-rises with flammable cladding soars

Aaron Morby 7 years ago
Share

The number of high-rise blocks  believed to be fitted with Grenfell-style cladding has soared following studies of over 6,000 buildings.

Neary 300 privately-owned high rises need to be reclad, with nearly three quarters without a remediation plan
Neary 300 privately-owned high rises need to be reclad, with nearly three quarters without a remediation plan

Latest estimates from the Government reveal there are now more private tower blocks of 18 storeys or above in need of remediation than social housing blocks.

The figure is more than double that believed at risk in May. Of the 297 high-rises expected to fail tests private owners of three quarters have failed to notify Government of plans to remediate despite warnings.

It also admitted this figure could rise further because the cladding status of another 170 private sector residential buildings is still to be confirmed.

Housing secretary James Brokenshire has unveiled fresh measures including a new expert taskforce to drive forward swifter action by building owners to remove potentially unsafe cladding on private sector high-rise residential buildings.

For the majority of these remaining buildings, enforcement notices have now been issued to get information on building construction from owners.

Based on current evidence and the identification rate to date, The Government expects 3-5% of the remaining buildings to have similar ACM cladding systems to those which have failed large-scale system tests.

Total high rise buildings with ACM cladding unlikely to meet building regs
14 June figs 22 May figs
Social-sector residential 159 159
Private-sector residential 297 138
(a)BRE tested 141 138
(b) Local authority confirmed 156 na
Publicly-owned buildings 14 14
Total ACM buildings 470 311

It said that only 19 of the total buildings have so far had their dangerous cladding replaced, leaving tens of thousands of people living in buildings at risk.

Brokenshire said: “I have been clear that leaseholders should be protected from unfair costs and we expect the industry to do the right thing. If they don’t, I will continue to explore other routes and I am not ruling anything out.”

He added that while remediation work has begun on 21 of these private buildings buildings, of which 4 have been completed, the government was determined to accelerate the pace of this work.

New measures

  • A new taskforce will oversee a national programme of remediation in the private sector and ensure plans are in place for every single building affected. The taskforce will be chaired by ministers and membership will include Local Government Association, National Fire Chiefs Council, London Councils and local authorities who have experienced the largest degree of impact and industry representatives.
  • A new inspection team, backed by £1m government funding, consisting of experts from environmental health, building control and fire inspection to support councils with enforcement action and ensure building owners take the necessary action and speed up the remediation process.
  • A follow-up industry roundtable next month so representatives can present their proposals on solutions to remove unsafe cladding from high-rise buildings without passing on the costs to leaseholders. In the meantime, the housing ministry will supporting local authorities to take more targeted action to identify and remediate affected buildings and recovering costs from those responsible for ensuring the safety of buildings; and supporting leaseholder enfranchisement.
  • Letters will be sent to all relevant private sector building owners to remind them of their responsibility to make their buildings safe.

Latest news

Berkeley’s £600m Borough Triangle project approved

Controversial scheme features two towers of 38 and 44-storeys
11 hours ago

HG to build 500-bed London Stratford student scheme

Work will start later this year subject to gateway 2 safety approval
11 hours ago

New rail property company to unlock land for 40,000 homes

First four sites released in Newcastle, Cambridge, Manchester, and Nottingham
20 hours ago

British Steel threatens closure of Scunthorpe blast furnaces

Chinese owners say sectional steel and rail supplies will be maintained
14 hours ago

Drainage specialist Subscan files administration notice

Specialist employing 131 people files court notice
20 hours ago

Four win Network Rail £300m engineering design deal

Eastern region deal will include design for Northern Powerhouse Rail
19 hours ago

Funding go-ahead for Banwell bypass after fresh cost hike

Galliford Try contract rises £14m to £64m after final design change
1 day ago

Graham wins Southport £75m Marine Lakes Centre

Firm replaces Kier which parted ways with backer Sefton Council
1 day ago

Chancellor unveils extra £2bn capital spend a year

Construction promised a defence dividend in military base and homes upgrade work
2 days ago

McLaren confirms subcontractor team on £135m warehouse job

Work starts on TN2 Gateway site in Kent.
2 days ago

Vistry profits slump after site costs reporting debacle

House builder launches internal whistle-blowing service in business culture review
2 days ago

Severfield chief to step down

Alan Dunsmore to leave structural steel group by end of June
2 days ago

Funding hurdle remains as Lower Thames Crossing gains consent

Government claims £9bn project may start in 2026 as private finance options explored
3 days ago

Mace wins £600m Euston Tower overhaul

1970s tower's foundations and core to be retained as floor plates extended
2 days ago

Summer start for main works on London green tower

Axa sanctions start at 50 Fenchurch Street 36-storey office block
2 days ago

Japan’s leading flats builder JVs with L&G for UK push

Partners plan to build over 1,000 rental homes in London
2 days ago

Wates submits plan for 1,000 homes Harrow council scheme

Former civic centre Poets' Corner site kicks off housing partnership
2 days ago

Morgan Sindall upgrades forecast for next 12 months

Overbury fit-out arm gets off to a flying start in 2025
3 days ago

Restructure underway at Henry Boot Construction

New management team restructures business after drop in turnover
3 days ago

Government pledges £2bn stop-gap funding for 18,000 homes

Funding avoids cliff-edge in social housing delivery before new grant programme agreed
3 days ago

Just two major new roads schemes to start this year

National Highways sets out one-year interim spending plan after RIS3 delay
3 days ago

Plans go in for £400m GRAHAM Manchester site

Demolition and enabling works underway with main construction set to start next year
3 days ago

Building safety levy rate set at up to £10,000 a home in London

Levy introduction pushed back a year to Autumn 2026 - list of new rates
4 days ago

BAM wins £100m revamp of Broadgate Tower in London

Front of tower 3-storey extension to use cross laminate time and re-used steel
4 days ago

£600m funding to train 60,000 construction workers

Government pledges massive cash injection to produce "site-ready" workers
5 days ago

Construction to start in May on £1bn port expansion

Work at London Gateway site will last four years
7 days ago

Utilities specialist Ipsum buys second power contractor

Acquisition of Wootton & Wootton strengthens service in Midlands and Wales
4 days ago

Councils will lose cash if they fail to fix potholes

Local authorities will have to publish road repair stats
4 days ago

Green light for London Euston Tower rebuild

British Land says nearly a third of original tower will be retained
7 days ago

Contractors struggling to keep-up with demand for data centres

More than half of clients fear supply chain will struggle
7 days ago

Contractor services