AstraZeneca set to replace Skanska on delayed £500m HQ

Aaron Morby 6 years ago
Share

Pharmaceutical giant AstraZeneca is understood to be in talks to replace Skanska on its delayed flagship HQ project in Cambridge.

Costs have skyrocketed beyond £500m on the vast project, which now looks set to be completed nearly two years late.

Striking HQ saw-tooth roof, which carries on through to the facade, has presented challenges

Both AstraZeneca and Skanska refused to comment on the situation.

But rumours are rife that Mace could now be in called in to finish the project at the Cambridge Biomedical Campus.

The complex was originally due to be finished in the third quarter of 2017. Now the project is timetabled to finished in May next year.

But sources claim this second extended deadline may not be met with the pharma giant now looking at a phased occupation of the building for its near 2,500 staff.

Last year the Enquirer revealed the expected cost of the headquarters and R & D complex had soared from £330m to over £500m.

A source said:  “It seems the project is facing delays of approximately two years, caused by water ingress into the basement because of the high water table requiring a lot of remedial work.

“There have also been issues with design and roof loadings.

“There is a general amazement that after over two years the building still presents as a shell and core project with very little services, containment, switchgear or cabling installed.”

Skanska is understood to be working on a cost-plus basis and has been throwing resources at the site, including senior managers from its neighbouring Papworth Hospital project as this scales down.

Earlier this year Skanska applied to the local council to extend working time on the project by 25 hours a week, ramping up permitted working inside the building from  7am to 8pm on weekdays and 7am – 8pm on weekends.

This application blamed the overheated construction market and the inability to gain enough contractors to enable the construction timetable to be met.

The project management switch comes at a torrid time for Skanska, which posted £33m of writedowns last year and delivered a wave of job cuts at its UK headquarters in Maple Cross.

Skanska’s delayed AstraZeneca and Papworth hospital projects sit next to each other at the Cambridge Biomedical Campus

In June, Skanska suffered another major setback on its neighbouring £165m Papworth hospital project at the Cambridge Biomedical Campus after flammable cladding was found fitted to the building.

This project was expected to open in September but will be delayed for several months while the substandard cladding is replaced.

If Mace is confirmed as the new project lead at the AstraZeneca job, it would be the second time in a year that the firm has stepped in to take over a Skanska contract.

Mace also replaced Skanska on the £1bn+ Phase Two contract at the Battersea Power Station redevelopment in London after the client revised its contract strategy on the project to construction management to control costs more tightly.

 

 

Latest news

McAlpine pulls out of £55m Carlisle Citadels project

University of Cumbria starts hunt for replacement contractor
57 mins ago

McLaren Living appoints HG Construction for £69m scheme

Build to Rent scheme will transform former vacant car park site in Leeds city centre
2 mins ago

Squibb liquidator probes £2m of “missing” plant

Machinery, cars and scrap metal have disappeared at demolition specialist
5 hours ago

Galliford Try to re-enter affordable homes market

Contractor sets out new five-year plan to build margin to 4%
5 hours ago

Former Sellar chief to lead civils contractor Kilnbridge

Owen Dannatt joins as new CEO as founder Dermot McDermott becomes Chairman
5 hours ago

Hunt starts for nuclear fusion plant construction partner

Fusion energy plant to be built at West Burton coal power station site.
5 hours ago

National Grid raises £7bn for big infrastructure upgrade

Rights issue to fund a major round of capital investment in energy infrastructure
4 hours ago

Grenfell police probe to last at least until end of 2025

19 companies and 58 individuals could eventually face charges
14 hours ago

Mace confirmed on £100m London office retrofit

Work underway on Helical's 100 New Bridge Street job near Ludgate Circus
1 day ago

Wylfa chosen for next big nuclear power station build

Government names Anglesey site for a large-scale gigawatt nuclear power plant.
1 day ago

Bowmer & Kirkland trading profit halves

Contractor buys HVAC specialist Adcock despite challenging market
1 day ago

Piling specialist Van Elle plans further job cuts

Piling specialist plans further cost savings in face of lower demand
1 day ago

Civils contractor A Catlow files administration notice

High voltage cable specialist lodges court notice
1 day ago

Green light for ARC Oxford lab campus

Work to start later this year on £40m Ascent building job
1 day ago

Stonehenge tunnel hit by another legal delay

Court upholds latest appeal against £1.7bn scheme by campaigners
2 days ago

Plans go in for huge Olympic Park construction hub

Bow Goods Yard could deliver 3.5m tonnes of materials a year to sites across London
2 days ago

40% affordable homes target for Labour’s new towns

Labour pledges to select new town sites by end of first year
2 days ago

Plan for £100m Liverpool Baltic station

Construction work could begin next year
2 days ago

Surgo Construction went down owing £4.5m

Biggest creditor is Bellway Homes after dispute on housing job
2 days ago

Vistry seals £157m West London housing deal

Around 575 homes to be built at Merrick Place scheme in Ealing
2 days ago

Streamlined Watkin Jones returns to profit in first half

Multi-room specialist sees secured work pipeline hit £1.4bn
2 days ago

Bellway hires ex-brickie as group construction chief

James Griffin to oversee move to the Future Homes Standard and timber frame.
2 days ago

Persimmon under fire for delays to £10m relief road

West Suffolk Council serves Breach of Condition Notices after timetable slips again
2 days ago

BAM wins £33m Kent secondary school job

Replacement Swanley academy to be built at live school site
2 days ago

Aluminium cladding specialist collapses

Melton Mowbray-based firm worked for several main contractors
3 days ago

Brickwork contractor Lee Marley returns to profit

Affordable and rental homes demand lifts brickwork contractor
3 days ago

Housing contractor Durkan suffers second year of losses

More fire safety provisions tip firm into £3.9m loss
3 days ago

Farrans makes breakthrough on tricky tunnel job

Tunnel under Tees latest part of new £155m water pipeline job
3 days ago

Heidelberg buys aggregates and earthworks specialist B&A

Latest deal follows acquisition of Mick George
3 days ago

Flagship biodiversity net gain scheme flawed

NAO warns Government's flagship green development scheme at risk of failure
6 days ago

Contractor services