AstraZeneca set to replace Skanska on delayed £500m HQ

Aaron Morby 4 years ago
Share

Pharmaceutical giant AstraZeneca is understood to be in talks to replace Skanska on its delayed flagship HQ project in Cambridge.

Costs have skyrocketed beyond £500m on the vast project, which now looks set to be completed nearly two years late.

Striking HQ saw-tooth roof, which carries on through to the facade, has presented challenges

Both AstraZeneca and Skanska refused to comment on the situation.

But rumours are rife that Mace could now be in called in to finish the project at the Cambridge Biomedical Campus.

The complex was originally due to be finished in the third quarter of 2017. Now the project is timetabled to finished in May next year.

But sources claim this second extended deadline may not be met with the pharma giant now looking at a phased occupation of the building for its near 2,500 staff.

Last year the Enquirer revealed the expected cost of the headquarters and R & D complex had soared from £330m to over £500m.

A source said:  “It seems the project is facing delays of approximately two years, caused by water ingress into the basement because of the high water table requiring a lot of remedial work.

“There have also been issues with design and roof loadings.

“There is a general amazement that after over two years the building still presents as a shell and core project with very little services, containment, switchgear or cabling installed.”

Skanska is understood to be working on a cost-plus basis and has been throwing resources at the site, including senior managers from its neighbouring Papworth Hospital project as this scales down.

Earlier this year Skanska applied to the local council to extend working time on the project by 25 hours a week, ramping up permitted working inside the building from  7am to 8pm on weekdays and 7am – 8pm on weekends.

This application blamed the overheated construction market and the inability to gain enough contractors to enable the construction timetable to be met.

The project management switch comes at a torrid time for Skanska, which posted £33m of writedowns last year and delivered a wave of job cuts at its UK headquarters in Maple Cross.

Skanska’s delayed AstraZeneca and Papworth hospital projects sit next to each other at the Cambridge Biomedical Campus

In June, Skanska suffered another major setback on its neighbouring £165m Papworth hospital project at the Cambridge Biomedical Campus after flammable cladding was found fitted to the building.

This project was expected to open in September but will be delayed for several months while the substandard cladding is replaced.

If Mace is confirmed as the new project lead at the AstraZeneca job, it would be the second time in a year that the firm has stepped in to take over a Skanska contract.

Mace also replaced Skanska on the £1bn+ Phase Two contract at the Battersea Power Station redevelopment in London after the client revised its contract strategy on the project to construction management to control costs more tightly.

 

 

Latest news

Hill gets go-ahead for North London estate rebuild

750 homes to be built at Douglas Bader Park estate in Colindale
8 hours ago

Bid race for £210m Huddersfield town centre revamp

Kirklees Council's Cultural Heart scheme will be split into two major projects
11 hours ago

£100m Darlington Station revamp enabling works start

Willmott Dixon set to deliver major station upgrade project
12 hours ago

Demolition worker gets huge payout after losing leg

Compensation settlement will fund latest prosthetic limb technology for site victim
11 hours ago

Plant hirer Vp abandons sale plan

Chairman Jeremy Pilkington says the plant hirer failed to find a suitable new owner.
10 hours ago

Turner & Townsend on board for Sheffield Supertram upgrade

Consultant to help deliver programme over next seven years after £570m funding deal
12 hours ago

Green light for new £33m Ipswich logistics park

Construction to start this October on latest Trebor Developments site
12 hours ago

Piling starts on pioneering double composite HS2 viaduct

Wendover Dean Viaduct ‘double composite’ structure will halve carbon emissions
12 hours ago

ISG pauses work on £300m gigaplant

Construction work rescheduled to reduce costs at giant car battery plant
1 day ago

Tory leadership battle delays bidding for HS2 phase 2a

Prequalification for £5.2bn-£7.2bn route to Crewe put back to September
2 days ago

Greswolde Construction goes under

Solihull contractor ceases trading with 24 jobs lost
4 days ago

Hanson on track for UK’s first net zero cement works

20 carbon capture projects shortlisted for £1bn funding
1 day ago

Plan in for Nottingham 967-room student scheme

Vita submits plan for second major purpose built student sh
1 day ago

Galliford Try gets go-ahead for next A47 dualling job

Early 2023 start for £200m section of A47 between North Tuddenham and Easton in Norfolk
1 day ago

Designs revealed for £1bn London Blackfriars tower blocks

Fosters design landmark green office skyscraper and two blocks of flats for Southwark site
4 days ago

Everton stadium job still on budget despite inflation

Club and Laing O'Rourke confident they can still build new ground for £500m
5 days ago

Construction output falls 1.4% halting 7-month growth spurt

Fresh output and orders figures confirm summer construction slowdown
4 days ago

McLaren gets green light for £85m build-to-rent scheme

Construction set to start this autumn on major city centre development
4 days ago

BAM limbers up for £25m Bedworth leisure centre

Pioneering Warwickshire health and fitness hub to start this autumn
4 days ago

Keepmoat to start four-year build in Wigan

Major regeneration scheme to start across four sites
4 days ago

Solihull contractor Greswolde heading for administration

New investors took over business 12 months ago
5 days ago

Duo win £500m canal and river main works deal

Kier and Bentley bag Canal & Rivers Trust's largest ever water engineering works deal
6 days ago

Construction Manager of the Year finalists revealed

70 of the industry's brightest talents: Full list
5 days ago

Willmott Dixon fills new strategic change director role

Vistry Group change director joins private builder to support future growth
6 days ago

Work starts on £42m Oldham Spindles overhaul

Willmott Dixon signs off £42m deal to create new market, offices and event space
6 days ago

Firms wanted for Telford & Wrekin £1.6bn building works DPS

Call up for dynamic purchasing system covering building and refurbishment work
5 days ago

Kier pulls off contracts league double in July

Contractor bags highest value of new work and tops rolling 12 months ranking
7 days ago

Hinkley Point C giant water intakes craned onto seabed

Video: contractors complete one of the world’s most complex marine engineering projects
6 days ago

Taziker revenue jumps 30% to record £73m

Multi-disciplinary engineering specialist boosts headcount to 366 staff
6 days ago

Consultant buys scaffolding contractor

RSK Group makes MG Scaffolding its latest acquisition
6 days ago

Contractor services