Interserve fined after M&E blunders at animal lab

Grant Prior 8 years ago
Share

Interserve’s facilities management arm has been fined after multiple safety failings at a laboratory site for the Animal Health and Veterinary Laboratories Agency in Weybridge.

Hove Crown Court heard how, on Sunday 21 September 2014, mains power was lost at the site which includes high containment laboratory facilities required to safely handle high hazard pathogens that are a serious risk to human health and the environment.

Interserve Facilities Management Ltd was contracted to the site and was responsible for delivery of maintenance activities for many of the mechanical and electrical systems.

The court heard that when mains power was lost, of the twelve generators in place to supply emergency power to the site, two failed to operate and two started but subsequently failed in operation, one of which also caught fire.

The emergency escalation system was triggered, and the Fire and Rescue Service attended the site. Power was fully restored later that day.

As a result of the emergency generator failures, the court was told all power was lost to a number of high containment facilities for several hours, affecting the site’s safety systems.

An HSE investigation found a number of failings of the contractor in relation to the maintenance activities undertaken on standby generators that could have resulted in employees being exposed to a risk of harm from biological agents.

Interserve (Facilities Management) Ltd pleaded guilty to safety breaches and was fined £93,600 and ordered to pay £32,056 costs.

Speaking after the hearing, HSE Intervention Programme Manager and lead investigator in the case, Dr Keith Stephenson said: “Interserve Facilities Management failed to effectively maintain the standby generators that were a key emergency control measure needed to work safely.

“Fortunately, the consequences of the multiple generator failures were significantly reduced by the timing of the incident, both in terms of the day of the week and the laboratory studies being undertaken at that time.

“Had the incident happened on a different day or when different studies were being undertaken, staff and the nearby environment could have been exposed to high hazard biological agents with serious consequences.”

Latest news

Supply chain hunt starts for hospital construction boom

Work up for grabs on five schemes across the East of England
13 hours ago

Laing O’Rourke and HMJV lead £1bn Grid upgrade for AI boom

North London power capacity upgrade to support five new data centres
13 hours ago

Willmott Dixon joins £150m Great Yarmouth waterfront bid

Planning in for major mixed-use North Quay waterfront regeneration project
14 hours ago

R G Carter eyes rebound after turnover falls to £215m

Firm says stronger order book will drive growth this year after softer 2025
13 hours ago

Manchester developer lands £185m funding boost

Forshaw secures institutional backing to accelerate housing delivery
13 hours ago

Morgan Sindall lures North East director from Willmott Dixon

Nick Corrigan joins rival as area director
1 day ago

Housing groundworks crisis deepens as JAO ceases trading

Somerset firm of over 100 staff adds to wave of housing supply chain failures
2 days ago

Plans in for striking HSBC Canary Wharf tower revamp

Project billed as the world's largest office building transformation
2 days ago

Costain predicts “step change” in financial performance

Contractor set to see profits jump from next year
2 days ago

Avant Homes seals Government fire safety payment deal

Deal spreads legacy remediation costs and eases liquidity pressure
2 days ago

Scaffolding firm Blencowe files administration notice

South of England specialist employs 55 people
2 days ago

Formwork panel hits Hinkley worker after falling 29 metres

Improvement notices issued by nuclear regulator extended
2 days ago

Focus on growing markets pays off for Balfour Beatty

Strong set of half-year results with momentum expected to continue for 2026
3 days ago

Ardmore directors fight to save property firms with CVA plan

Seven firms seek CVA lifeline as Ardmore fights BLO ruling in Court of Appeal
3 days ago

Investment giant acquires Phoenix ME

Deal set to accelerate growth strategy at M&E specialist
3 days ago

Structure Tone revenue almost triples to record £449m

London fit-out boom swells order book to £1.3bn
3 days ago

Kier inks second Derwent London office scheme for £99m

Firm lands repeat business on flagship Oxford Street redevelopment
3 days ago

Hill hires former Telford Homes boss

John Fitzgerald to oversee Eastern Residential and Western businesses
3 days ago

Willmott Dixon kicks off Oldham town centre regen

Firm picked for £28m first phase of Prince's Gate for developer Muse
3 days ago

VINCI UK profit jumps 51% after group overhaul

Highways, civils and FM Conway acquisition lift earnings as turnover approaches £3bn
4 days ago

Clancy Consulting administration move sheds historic liabilities

70 jobs safeguarded as core civil and structural engineering business survives
4 days ago

Multiplex gets start date for City Road 36-storey tower

Main construction to get underway this quarter
4 days ago

Bellway beats build target despite weaker buyer demand

CEO calls for Stamp Duty cuts and first-time buyer help to revive housing market
4 days ago

Trade credit insurer could cut cover for Vistry suppliers

Allianz Trade reportedly reduces credit limits as house builder battles to cut £470m net debt
4 days ago

Bricklayer breaks back after falling through roof

Contractor fined £20,000 for safety failures
4 days ago

M&E specialist ACES files administration notice

Avon Combined Electrical Services expanded into the capital last year to win larger jobs
5 days ago

Portsmouth picks ECF for 2,300-home city centre regeneration

Council finally advances ambitious City Centre North regen plan
5 days ago

Newcastle office block plan unveiled

12-storey scheme to be latest addition to One Founders Place
5 days ago

Eric Wright to start £65m Tebay-style M56 services

Yates starts groundworks on Cheshire motorway services
5 days ago

Plans in for retrofit of London Charing Cross office icon

Major retrofit plan keeps 90% of iconic 1990s office building
5 days ago