Super sewer contingency budget raided due to cost pressure

Aaron Morby 6 years ago
Share

Thames Tideway is rolling out a cost-saving plan after having to raid much of the project contingency budget even before tunnelling has started.

First of eight TBM's started central section drive last week amid concern about soaring costs in preparation works
First of eight TBM's started central section drive last week amid concern about soaring costs in preparation works

A catalogue of engineering challenges during cofferdam and shaft construction has left the project team looking for major cost-savings.

The project’s holding company, Bazalgette Holdings Group, confirmed the total project spend so far has reached £1.48bn amid unforeseen cost pressures early on in the project.

Now contractors are being pressed to find savings and raise productivity as a value engineering exercise is undertaken and overheads are cut.

The 25km tunnel is due to be completed by 2023 at a cost £4.2bn and Tideway said it was confident the project would be completed on time and to budget.

Cost pressures were revealed as former Crossrail finance boss Mathew Duncan joined the project last week as new finance director replacing Mark Corben, whose intention to stand down was announced last year.

Key sites facing engineering challenges are at Blackfriars, where two large Victorian gas mains have caused problems, cofferdam construction at King Edward Memorial Park and Albert Embankment and shafts at east area sites.

In a statement just after the first tunnelling started last week, the firm said: “Following significant progress on the project and now having mobilised on 20 of our 21 sites, Tideway has identified several cost pressures in the programme.

“Taken together with general cost pressure across the programme this has substantially eroded available contingency.

“To mitigate the cost pressures Tideway has begun to implement cost-saving measures in partnership with our contractors and remains focussed on achieving the baseline target.

“These cost-saving measures include working with our contractors to eliminate overlap, taking measures to increase productivity, undertaking value engineering and delivering overhead savings.

“It is too early to conclude the extent to which these measures will mitigate the cost pressures, and an update will be provided on these and the cost savings programme in Tideway’s annual report and accounts next March.”

A spokeswoman for Tideway added: “There have been a number of complex engineering challenges and risks to overcome in the early stages of the project.

“With these behind us and having put in place several measures to reduce cost, our budget is intact. Tunnelling for the project started last week from our site in Battersea and we are set to complete the project on schedule and to budget.”

Latest news

Morgan Sindall to build former Willmott Dixon leisure job

New contractor appointed on
14 hours ago

Graham consortium wins £400m Manchester job

Equitix consortium to now work up DBFO plans for University of Manchester’s Fallowfield Campus
11 hours ago

Keltbray looking to sell infrastructure business

£378m turnover rail, energy and highways business up for sale
21 hours ago

Innovative viaduct building method used for first time in UK

HS2 contractors will build nine viaducts in Delta Junction using special cantilevered process
22 hours ago

Unite buys London site to fast-track 444-bed student scheme

£800m to be spent on London development pipeline in next five years
22 hours ago

CITB awards £2.5m of contracts to management consultant

Three outsourced deals in the last year for "project leadership and management consultancy"
22 hours ago

Village centre approved for 6,000-home new town plan

Hampshire's Welborne Garden Village plan has been in the pipeline for two decades.
21 hours ago

£3m fine after cherry picker demolition death

Court rules after tragedy during decommissioning of gas rig
22 hours ago

BAM plans wave of job cuts at UK Construction arm

Co-op Live arena plunges Bam Construction to £19.5m first-half loss
2 days ago

Robot tunnel builder goes into administration

Hypertunnel was hoping to revolutionise how underground structures are built
2 days ago

Wates to build £86m Guildford Council housing scheme

40% of the 248 homes will become council homes under partnership deal
2 days ago

“Scrap CITB” say three quarters of construction firms

Payroll giant Hudson Contract calls for CITB to be absorbed into new Skills England training body
2 days ago

£100m Prestwich Village revival approved

Vinci and Willmott Dixon in chase for Muse-led regeneration scheme
2 days ago

Carbon negative asphalt aggregate trialled on M11

Skanska and Tarmac test CO2 absorbing aggregate material on stretch of Essex motorway
2 days ago

Father and son sentenced over covid construction loan fraud

Bristol builders given suspended jail sentences over bogus Bounce Back Loans
2 days ago

Beck Interiors files administration notice

Supply chain has suffered delayed payments from £139m-turnover luxury fit out specialist
3 days ago

Green light for York Central civil service office hub

£60m office project accelerates York Central goods yard redevelopment
3 days ago

Blenheim House Construction enters administration

Administrators looking at options on present projects
3 days ago

Profits rise at Esh Group with more to come

Contractor confident about year ahead as market conditions move in right direction
3 days ago

Piling specialist Van Elle sees housing orders rise 30%

Mark Cutler says firm on course to deliver 10% annual sales growth
3 days ago

HS2 to spend £100m shutting sites where work never started

Remediation of sites no longer needed for cancelled Phase 2 will take three years
4 days ago

Willmott Dixon wins £61m deal for new Army dog unit

Contractor to revamp Kendrew Barracks in Rutland
3 days ago

Stockport advances 4,000-home Town Centre East plan

Council seeks consultants to steer plan for 280-acre area in the city
3 days ago

ISG sale imminent as buyers set-up UK holding company

South African nutrition entrepreneur and Australian partner primed to take over
4 days ago

CR Construction wins £210m Manchester towers

Construction to start next year on four blocks ranging from nine to 34-storeys
4 days ago

Southern Housing to rationalise supply chain following merger

Firms put on alert for £1.7bn construction framework renewal
4 days ago

Decision delayed on 52-storey Isle of Dogs tower

Hong Kong developer plans 460 flats block next to Millwall Inner Dock
4 days ago

Go-ahead for £850m North London estate rebuild

Flagship Edmonton housing estate redevelopment will deliver 2,000 new homes
4 days ago

Mace lands £184m Oxford Science Park contract

Contractor to build trio of laboratory and office buildings
5 days ago

Worker paralysed in 30ft fall during electricity pylon demolition

Specialist firm fined £240,000 after court hears linesman attached lanyard to a loosened steel section
4 days ago

Contractor services