EastEnders set rebuild soars £27m over budget

Aaron Morby 6 years ago
Share

The BBC has been slammed for allowing the cost of the EastEnders set rebuild to spiral out of control.

Its E20 project to replace and enlarge the external EastEnders set and improve infrastructure at BBC Elstree Centre is now expected to cost £87m, rather than £60m as first planned.

The overall project will also take an extra two and a half years to complete.

Most of this increase relates to the higher cost of the Front Lot contract involving the rebuilding of Albert Square being delivered by Wates.

According to the spending watchdog, National Audit Office, the BBC now estimates this part will cost £56m – £23.5m more than planned.

The NAO takes aim at failures in the early planning stages where 70 late design changes were made and delays in the procurement process.

The project team also encountered asbestos and obstructions in the ground at various stages of the programme, which the NAO says should have been picked up with more detailed surveying work by spending more money during the planning phase.

The BBC had to switch from a single-stage tender in 2016 to two-stage bid process in 2017 because of limited market interest.

It then took 11 months for the BBC and Wates to agree on the final contract price from stage one selection, more than twice as long as planned.

This delay, higher than expected industry cost inflation, and new brick specification saw Wates’ fixed price contract agreed in August 2018 come in £9.5m more than consultant AECOM planned at £24m.

The BBC now expects the Albert Square rebuild to be completed at the end of March 2021, 22 months later than first planned in 2015, with the wider E20 project completed 31 months late.

Amyas Morse, head of the NAO, said: “The BBC will not be able to deliver value for money on E20 in the way that it originally envisaged. It is surprising that some of the reasons for this were built in from the beginning.

“Despite recent project management improvements, E20 is late and over budget against its 2015 plans. We believe that the planned benefits are still broadly achievable, but given the high-risk nature of E20 it will need close scrutiny until it is finished.”

Aerial view of Albert Square – the set for BBC’s Eastenders at Elstree Studios

The BBC built the external filming set for EastEnders in 1984, and originally planned to use it for two years.

It has lasted for 34 years but is no longer fit for purpose.

The poor condition of the set means the BBC cannot film in high-definition, degradation has led to increasing filming delays owing to stoppages in production due to health and safety concerns, and there are ongoing maintenance costs to ensure filming can continue.

Latest news

M&S Marble Arch rebuild approved after three-year planning fight

Plans were delayed when Michael Gove backed carbon campaigners
6 hours ago

PM pledges to fast-track 150 infrastructure schemes

Fresh promise to speed up planning decisions on infrastructure and house building
9 hours ago

Buyers report boom in commercial work

Construction bucks slowdown in general economy
13 hours ago

Plans in for £250m Stockport 8 housing-led scheme

Work to start on phase 1 by the end of next year
12 hours ago

Galliford Try tops monthly contracts league

Contract awards slow down in November
16 hours ago

Erith explosives set demolition record at Sizewell

Watch blast at former nuclear turbine hall: Video
15 hours ago

Vistry to build 950 homes next to Olympic Park

Developer signed for £600m Pudding Mill Lane scheme in East London
15 hours ago

Inflatable formwork used for 45m tall cement silo

Ground-breaking dome silo inflated at Tilbury Docks
15 hours ago

Briggs & Forrester sells maintenance arm

100 engineers to move over to new owner
1 day ago

£2bn Edinburgh ‘West Town’ scheme approved

7,000 homes to be built at 205-acre site
1 day ago

Rayner approves Lancashire super prison

Communities secretary overrules planning inspector for 1,700 inmate prison.
2 days ago

Wates boss returns after collapse of his own contractor

Paul Nicholls was head of the failed Real construction group
2 days ago

Trio secure Birmingham deal to retrofit 3,000 homes a year

Specialist contractors to install insulation, efficient heating and solar panels
2 days ago

Costain confirms £400m HS2 tunnels win

Work to start early next year on tunnel and lineside mechanical and electrical systems
2 days ago

First nuclear reactor installed at Hinkley: Video

Watch precision operation at Somerset site
2 days ago

Winner named for £14m Harbourside revamp

Local Irvine contractor to transform beach front
2 days ago

New Fair Payment Code goes live today

Latest bid to get subcontractors and suppliers paid within 30 days
3 days ago

Lincolnshire concrete supplier files administration notice

Ever Readymix Concrete & Screed operates three depots and a fleet of 20 trucks
3 days ago

Graham lands first deal on Liverpool’s largest brownfield site

Contractor bags infrastructure package on 10.5 hectare site
3 days ago

Bouygues UK boss to step down

Fabienne Viala to leave after eight years at the helm
3 days ago

Galliford Try scoops £87m brace of London jobs

Firm will redevelop a prominent corner building on Sloane Street in Chelsea
3 days ago

New HS2 boss Mark Wild starts amid prep for final TBM drives

Former Crossrail CEO starts with a sharp focus on controlling costs
3 days ago

Ten consultants land Thames Water major upgrade places

Firms will share £400m of fee work over next five years
3 days ago

Rayner ultimatum to fix all unsafe tall buildings by 2029

Recladding work must start on all 18m+ resi buildings by 2027
3 days ago

ISG administrator finds just £35m to pay down £1.1bn debt

Failed firm was set to report £148m blackhole from legacy jobs
4 days ago

Redesign needed on Colas “bridge to nowhere”

Technical challenges continue as £38m scheme faces further delays
4 days ago

Skanska UK shakes-up boardroom team

Four new board appointments as two directors step down
4 days ago

Ultra rich clamour for Mace super prime resi scheme

Topping out at £2bn 1 Mayfair scheme where homes start at £35m
4 days ago

Watkin Jones wins £48m St Helen’s affordable homes deal

Firm to build nearly 300 homes for housing association
4 days ago

Barratt sets start date for High Barnet station scheme

Latest scheme to be delivered by the £1.9bn West London Partnership
4 days ago

Contractor services