Aberdeen bypass now misses Xmas opening deadline

Aaron Morby 5 years ago
Share

Balfour Beatty and Galliford Try’s Aberdeen Western Peripheral Route consortium has failed to meet the latest big deadline to open all of the delayed project.

The Craibstone to Stonehaven section of the Aberdeen Western Peripheral Route opened last week but the the Don Crossing missed its latest completion deadline
The Craibstone to Stonehaven section of the Aberdeen Western Peripheral Route opened last week but the the Don Crossing missed its latest completion deadline

While 85% of the giant scheme is now open, the final key stretch at the Don Crossing continues to torment the Aberdeen Roads Ltd consortium.

Now Scottish Transport Secretary Michael Matheson has warned that his office will not release any further payments for the structure until it has received firm commercial assurances.

Sources have revealed to the Enquirer that the bridge problems all come from movement with foundations early on in the project.

Delays and engineering problems have seen the £745m project fell behind schedule, with the expected cost now expected to be more than £1bn.

Last month Galliford Try revealed that its share of delays had cost it an extra £143m.

Contractors had pledged to open the final 4.5 mile section between Parkhill and Craibstone before Christmas.

Matheson said: “This week, ARL informed us it was no longer able to meet its own deadline of concluding works at the Don Crossing before Christmas.

“This is just over a fortnight since it set this deadline publicly in Parliament. I have consistently urged caution and realism about ARL’s ambitious timescales. Unfortunately, as disappointing as this news is, it comes as no surprise to me it has been unable to achieve this.”

He added: “It is well known that ARL has experienced a series of technical issues during the construction of the Don Crossing.

“In order for this Government to protect the public purse, it is imperative that ARL provides the necessary technical and commercial assurances for the Don Crossing. We cannot and will not contemplate releasing payments for this structure without these critical assurances.

“In terms of an opening date for this section, although ARL are forecasting January 2019, they have been unable to provide a definitive date.”

All work on the 36-mile AWPR was initially set to be completed by spring, but it was delayed to autumn, and then until December.

 

Latest news

Carpenter killed by falling timber frame panels

Court fines specialist contractor £8,000 after site tragedy
2 days ago

Road sweeper specialist files administration notice

Go Plant lodges court notice
2 days ago

Anglian Homes rides in to finish crashed Everest contracts

Rival doubled glazed window specialist commits to complete orders
2 days ago

Final work starts to connect super sewer to London system

End in sight with 1.5m thick concrete wall to be demolished to link-up to Lee Tunnel sewer system
2 days ago

Legal challenge launched against £1.5bn A66 dualling

Balfour Beatty, Kier and Keltbray must now await outcome of court challenge
2 days ago

John F Hunt wins 24-storey Battersea tower

Specialist to carry-out demolition, enabling works and RC frame construction
3 days ago

William Hare wins steelwork on £500m Broadgate towers

Specialist to work on 2 Finsbury Avenue with McAlpine
3 days ago

McAlpine appoints MD to grow ventures business

Owain Thomas will build on private rental and healthcare development successes
3 days ago

BAM Co-op Live Arena opening delayed yet again

Another gig cancelled last night amid last minute safety concerns
3 days ago

National Grid unveils winners for £9bn network upgrade

New 'enterprise model' to deliver infrastructure schemes quicker and cheaper
4 days ago

Turkish insulation panel maker to build £45m UK factory

Assan Panel to open first UK plant at Freeport East
3 days ago

Expanding consultant Stantec swoops for Hydrock

Stantec UK business expands by a third as 950 staff join from Bristol-based engineer
4 days ago

Contractors wanted for £800m highways deal

Bids invited for Eastern Highways Alliance Framework 4
3 days ago

Galliford Try names group head of infrastructure

David Lowery promoted to Divisional Managing Director – Infrastructure.
3 days ago

Chigwell Group looks at stock market listing

Essex contractor registers as Public Limited Company
4 days ago

A57 Mottram Bypass clears final legal challenge

Balfour Beatty to get go-ahead to start shortly
4 days ago

100 jobs axed as Geoffrey Osborne confirms administration

Chairman Andrew Osborne calls it a 'sad day' as board loses fight for survival
5 days ago

Midgard set for Notting Hill office tower overhaul

Landmark project edges towards final approval after 10-year planning saga
4 days ago

Cumbrian civils firm clinches £40m Sellafield contract

Civils specialist Stobbarts will support McAlpine on groundworks and concrete
4 days ago

Designers named for London 2000-bed student rooms job

Bouygues will build £400m London School of Economics student scheme next to Tate Modern
4 days ago

£117m-turnover contractor files administration notice

ARJ Construction lodges court notice
5 days ago

£1bn London Blackfriars tower blocks approved

Trio of buildings rising to 45, 40 and 22 storeys approved by Southwark Council
5 days ago

Council decides to end Balfour deal after 13 years

Contractor has been maintaining roads across Herefordshire since 2013
5 days ago

Six civils clients to switch to low carbon concrete and steel

National Highways, Northumbrian Water and Sellafield sign fresh decarbonising pledge
6 days ago

Fortem extends homes repair deal across Birmingham

Willmott Dixon owned firm adds another two years to deal worth £170m
5 days ago

Kier wins £118m civil service Darlington hub

Work is expected to start towards the end of this year
6 days ago

Green light for 34-storey Digbeth apartments tower

480 flats will be delivered for Clarion housing association
5 days ago

LHC starts race for major retrofit and decarb framework

Hunt starts for firms to help with 6.1m social homes upgrade target
6 days ago

Windows giant Everest crashes into administration

Around 350 jobs at risk while hunt starts for a buyer to salvage business
6 days ago

Green light for £500m Newcastle health complex

Mixed use scheme will promote healthy living across all stages of life
6 days ago

Contractor services