Mace confirms further delays at Spurs stadium

Grant Prior 3 years ago
Share

Mace has told Spurs its new stadium won’t be ready to play in until the end of February at the earliest.

The club made an announcement on Tuesday following a post-Christmas/New Year update from main contractor Mace over continuing work on safety systems.

Spurs said: “The past month has seen remedial works take place, software issues resolved and corrected safety equipment installations increase. Testing has also continued.

“We are now liaising with the contractors and building control at Haringey Council to determine a schedule of commissioning, building test dates and building control sign-offs, along with formal test event dates.”

Premier League games against Watford, Newcastle United  and Leiceter City in January and February will now be played at Wembley plus the Champions League match against Borussia Dortmund.

Daniel Levy, Chairman, said: “I should like to apologise to our fans and thank you for your continued patience.

“We shall now seek clarity in respect of building test schedules and test event dates and provide further information on these in the next two to three weeks.”

Latest news

Structural steel price jumps another £50 a tonne

British Steel blames New Year's price hike on continuing high product costs
1 day ago

Green light for Birmingham Paradise landmark hotel

17-storey hotel will be the 'cornerstone' of Phase 2
1 day ago

Enabling works start at £400m Manchester First Street

Downing to start main construction in March of three resi buildings rising up to 45 storeys
1 day ago

Former BAM Nuttall chief to join Murphy

Adrian Savory to start new role as director of Major Projects division next month
1 day ago

Bouygues set for London Tustin Estate 700-home rebuild

Phased building programme to start towards the end of the year
1 day ago

Safety horror show on housing site leads to director ban

Court hears contractor ignored multiple prohibition and improvement notices
1 day ago

JV North calls up local firms for £250m new home works

Framework for home building projects worth up to £2m
1 day ago

Kier more than halves debts to below £200m

Kier chief reports steady progress in first six months of trading
2 days ago

Barhale boosts funds as it looks to rebuild turnover

Contractor confident as water companies ramp-up spending plans
2 days ago

HS2 labour agency looks to float on AIM

£23m turnover labour supply business looks to raise funds for expansion
2 days ago

Kane scores £29m M&E deal with Willmott Dixon

Off site works to play crucial role in major London estate contract
2 days ago

Graham secures third Audley retirement village

Work starts on Audley Villages site at Scarcroft, West Yorkshire.
2 days ago

Keltbray wins first deal for former nmcn infrastructure arm

Hull waste processing contract for rescued division
3 days ago

50 firms win £750m decarbonisation framework

Fusion21 framework to target 'whole building' works on homes and schools
3 days ago

Balfour Beatty UK construction MD to step down

Tom Edgcumbe to depart after just over a year as MD construction services in England and Wales
3 days ago

Crest Nicholson trebles cladding retrofit provisions to £43m

House builder revises building safety retrofit costs in face of new Government guidance
3 days ago

BAM bags £110m refurb of iconic Covent Garden tower

Landmark Seifert-designed 15-storey Space House to get two extra floors
4 days ago

Winvic to start UK’s largest speculative shed

Ellesmere Port warehouse understood to be worth around £80m
3 days ago

Kier signs deal for £169m Luton hospital revamp

Main construction work to start this month and last until 2024
3 days ago

Willmott Dixon nabs £30m Kirklees police HQ

Work to start within next few weeks on regional police HQ
4 days ago

Kier reported to be in talks to buy Tilbury Douglas

Talks reported to be at an advanced stage between both boards
4 days ago

Finance sealed for next-generation London office job

Goldman Sachs takes stake in London Bridge office project
4 days ago

John F Hunt starts giant clean-up on £110m Walsall site

Land remediation work at contaminated site will take two years
4 days ago

Build to rent boom lifts Watkin Jones profit to £52m

Surging build to rent market lifts development pipeline to £1.8 billion
4 days ago

HS2 awards £310m station lifts and escalators deal

TK Elevator signs 160 lifts and 130 escalators deal for four stations
5 days ago

Robot cutter set to revolutionise paving jobs for Eurovia

Automated system will spell end for noisy slab cutting on busy sites
5 days ago

First mass built carbon negative homes get underway

St Modwen first volume developer to build affordable carbon-negative homes
5 days ago

GMI Construction names new CEO

Lee Powell takes helm as CEO at GMI Construction in growth push
5 days ago

514-home London scheme clears final hurdle

Inland Homes declares victory after three-year planning battle over Hillingdon Master Brewer site
5 days ago

Henry Construction wins £30m Clarion housing scheme

Ravensbury estate regeneration in Mitcham is Henry's first project for Clarion
5 days ago

Contractor services