Crossrail can’t find enough managers to complete project

Grant Prior 1 year ago
Share

Crossrail bosses are struggling to find project managers to complete the delayed scheme.

A damning report from the National Audit Office has revealed that Crossrail currently has 143 unfilled vacancies at its central delivery team “including project delivery teams to work with main contractors to deliver the programme.”

There are also 33 further vacancies across the orgnaisation as it battles to hit a revised opening deadline of between October 2020 and March 2021.

Crossrail scaled down its central management team as the job approached its original December 2018 opening date.

The NAO report said: “In order to be able to manage programme risks and the complex contractual arrangements effectively, Crossrail Ltd needs to rebuild its capability and capacity in a number of disciplines.

“During 2018, Crossrail Ltd reduced the number of staff in its central functions, such as risk management, planning and contract and commercial management, as it pursued its demobilisation plans in accordance with its aim to meet the December 2018 deadline.

“All of these functions are critical to completing the programme efficiently and effectively.

“The company now recognises that it still needs skills and has started to recruit.

“It has hired a head of risk and plans to increase the team from one person to five, and has reinstated its audit and assurance committee, which it disbanded in 2018.

“It has increased the size of the planning team by 15 to 34. It is also re-establishing its external affairs team.

“Crossrail Ltd has, however, struggled to recruit the skills it needs. Its capacity to manage the programme effectively remains a key risk.”

The revelation is among a catalogue of management blunders highlighted in the NAO report which have resulted in the project running two years late and £2.8bn over budget.

It details how Crossrail chiefs lost control of contractors and made a series of operational mistakes in a desperate attempt to hit the doomed original deadline.

The report blames cost increases on:

  • Crossrail Ltd’s delivery and commercial strategy
  • the build-up of delays, dependencies and interfaces between contracts and projects
  • not changing course when there were clear signs that the programme was not on track

The NAO believes major problems were evident on the project as early as 2015 and resulted in changes required to the design and to contractors’ delivery schedules which increased costs on most of the 36 main contracts.

It said: “Between February 2017 and December 2018, for example, the forecast final cost of the contract to install track and key systems in the tunnels increased by 80% from £532 million to £956 million.

“Crossrail Ltd also made decisions that drove unnecessary cost.

“In early 2018, Crossrail Ltd began carrying out train testing and construction activity in alternating time periods, to allow for early sight of potential train and signalling system issues.

“However, this testing was of limited use and took any spare time and space from construction workers on site.

“Crossrail Ltd also reduced the size of its central programme and risk management teams during 2018, in anticipation of the programme reaching completion in December 2018.

“It is currently attempting to rehire these personnel. ”

NAO head Amyas Morse said: “There have been a number of choices made in the course of this project that have clearly damaged public value.”

The extent of cost increases on major contracts laid bare in the report:

Latest news

Stepnell lifts Covid pay cuts two weeks early

Family owned contractor returns to pre-pandemic salaries
1 day ago

Laing O’Rourke office staff to face temperature checks

Contractor rolls out site screening initiative ahead of white collar workers return
1 day ago

Delay confirmed for “cash flow chaos” VAT change

Domestic reverse charge plan put back to March 2021
1 day ago

BAM signs first university pain-gain share alliance deal

£220m Sheffield Hallam alliance includes designers and FM contractor
1 day ago

Willmott Dixon praises staff and supply chain for Covid response

Contractor made 2.5% profit margin in 2019 providing strong platform for pandemic challenges
1 day ago

TfL picks consultants for £500m project framework

Costain, Mace and Lendlease feature among big multi-disciplinary firms
1 day ago

SES Engineering Services MD steps down

Jason Knights to leave Wates, once successor found
2 days ago

Government protects trade credit insurance cover

£10bn guarantee to stop the market seizing up
2 days ago

Construction occupational health scheme to close

Owner B&CE pulls plug on Constructing Better Health
1 day ago

Buyers report downturn easing after April Covid carnage

Supply chain disruptions still hampering reopened sites
2 days ago

Keep the industry updated by joining the Enquirer Directory

Membership lets construction know you are open for business now or in the future
2 years ago

Leeds civil engineering contractor collapses

Athena Civil Engineering placed into administration
2 days ago

Barhale back in profit after problem contracts loss

Civils giant bounces back after tunnelling issues on aqueduct scheme contribute to £15m loss
2 days ago

Coronavirus disruption tips Van Elle into the red

Former Galliford Try finance director to become chairman of piling specialist
2 days ago

£300m to kick-start three major London schemes

Infrastructure funding for 20,0000 homes at Brent Cross, Silvertown and Barking Riverside
2 days ago

JRL Group names new civils MD

Matt Love to lead £18m specialist piling business
3 days ago

HB Reavis acquires prime Shoreditch site

Construction to start next year on latest workplace scheme
2 days ago

Premier Inn restarts construction work on 35 sites

Hotel giant committed to long term expansion plans
3 days ago

London £130m Old Kent Road scheme approved

Work to start early next year at former Carpetright warehouse
3 days ago

Plans go in for 42 acre London food market

Billingsgate, Spitalfields and Smithfield to get a new home in Dagenham
3 days ago

Kier Highways and Seddon reinstated to Prompt Payment Code

Contractors now keeping to pledge to pay 95% of suppliers within 60 days
3 days ago

Leading brick makers to axe 600 jobs

Ibstock and Forterra restructure businesses to meet forecast fall in demand
3 days ago

London fit-out firm Square Metre in administration

Fifty jobs cut as lockdown tips £32m fit-out firm over the edge
3 days ago

Last webinar for contractors interested in £600m plant

Final procurement information event before OJEU notice next month
3 days ago

Offsite system to cut staircase construction times by 80%

New integrated balustrade system added before precast stairs lifted into place on site
4 days ago

Arup bags job to re-open Cardiff city centre

Arup plans to improve public spaces, repurposed streets and digital infrastructure
4 days ago

Hard-hat mounted cough guard will help protect site workers

New product from JSP will help keep sites safe
4 days ago
JSP Ltd

Balfour Beatty to start £355m Hull A63 scheme

All systems go for delayed Castle Street upgrade to transform Hull
4 days ago

Contractors face data danger fighting covid contract disputes

Redundancies could see project knowledge lost
4 days ago

Mace bags role on £39bn Northern Powerhouse Rail plan

Firm takes lead on project controls, project, stakeholder and commercial management
5 days ago

Contractor services