Crossrail can’t find enough managers to complete project

Grant Prior 3 weeks ago
Share

Crossrail bosses are struggling to find project managers to complete the delayed scheme.

A damning report from the National Audit Office has revealed that Crossrail currently has 143 unfilled vacancies at its central delivery team “including project delivery teams to work with main contractors to deliver the programme.”

There are also 33 further vacancies across the orgnaisation as it battles to hit a revised opening deadline of between October 2020 and March 2021.

Crossrail scaled down its central management team as the job approached its original December 2018 opening date.

The NAO report said: “In order to be able to manage programme risks and the complex contractual arrangements effectively, Crossrail Ltd needs to rebuild its capability and capacity in a number of disciplines.

“During 2018, Crossrail Ltd reduced the number of staff in its central functions, such as risk management, planning and contract and commercial management, as it pursued its demobilisation plans in accordance with its aim to meet the December 2018 deadline.

“All of these functions are critical to completing the programme efficiently and effectively.

“The company now recognises that it still needs skills and has started to recruit.

“It has hired a head of risk and plans to increase the team from one person to five, and has reinstated its audit and assurance committee, which it disbanded in 2018.

“It has increased the size of the planning team by 15 to 34. It is also re-establishing its external affairs team.

“Crossrail Ltd has, however, struggled to recruit the skills it needs. Its capacity to manage the programme effectively remains a key risk.”

The revelation is among a catalogue of management blunders highlighted in the NAO report which have resulted in the project running two years late and £2.8bn over budget.

It details how Crossrail chiefs lost control of contractors and made a series of operational mistakes in a desperate attempt to hit the doomed original deadline.

The report blames cost increases on:

  • Crossrail Ltd’s delivery and commercial strategy
  • the build-up of delays, dependencies and interfaces between contracts and projects
  • not changing course when there were clear signs that the programme was not on track

The NAO believes major problems were evident on the project as early as 2015 and resulted in changes required to the design and to contractors’ delivery schedules which increased costs on most of the 36 main contracts.

It said: “Between February 2017 and December 2018, for example, the forecast final cost of the contract to install track and key systems in the tunnels increased by 80% from £532 million to £956 million.

“Crossrail Ltd also made decisions that drove unnecessary cost.

“In early 2018, Crossrail Ltd began carrying out train testing and construction activity in alternating time periods, to allow for early sight of potential train and signalling system issues.

“However, this testing was of limited use and took any spare time and space from construction workers on site.

“Crossrail Ltd also reduced the size of its central programme and risk management teams during 2018, in anticipation of the programme reaching completion in December 2018.

“It is currently attempting to rehire these personnel. ”

NAO head Amyas Morse said: “There have been a number of choices made in the course of this project that have clearly damaged public value.”

The extent of cost increases on major contracts laid bare in the report:

Latest news

Galliford Try confirms 350 construction job cuts

Slimmed-down division to focus on building,water and highways
16 hours ago

Kier wins £20m Sheffield Park Hill student scheme

Flats at iconic estate will be converted into 356 student homes
2 hours ago

Site inductions to contain modern slavery warnings

How to spot labour exploitation now explained alongside traditional health and safety briefing
6 hours ago

Dawnus went down owing supply chain more than £40m

Subcontractors left in the lurch again following latest collapse
15 hours ago

Plastic road built on new housing development

Springfield Properties recycles waste plastic to help build new road
11 hours ago

Interserve benched on £1bn Welsh framework

SEWSCAP 3 deal: Details of latest winners
1 day ago

BAM Nuttall profit hits 10-year high

Operating margin back to 3% as profit tops £26m
1 day ago

Diversification shields Keltbray from demolition slowdown

Contractor looking at new markets as core commercial workloads fall
16 hours ago

Robertson lures property boss from Henry Boot

Nick Harris joins from one of contractor's biggest clients
1 day ago

Esh gears up for £36m Sunderland road job

Esh mobilises to start phase 3 of city strategic corridor
1 day ago

London office work shifts towards major refurb projects

London crane survey shows little sign of Brexit blues
2 days ago

US consultant Tetra Tech to buy WYG for £43m

WYG board backs 55p a share offer at big premium to 16p share price
2 days ago

Boost your online presence – join the Enquirer Directory

New site for suppliers and buyers showcases products, services and latest stories
1 year ago

Prater soars past £100m revenue

Envelope specialist optimistic 2019 will see another year of growth
2 days ago

Construction to start on new Farringdon scheme this year

Helical and AshbyCapital acquire Charterhouse Place
2 days ago

VolkerFitzpatrick wins £27m rail station upgrade

Two stations to be upgraded in Cambridge and King’s Lynn enhancements
2 days ago

Joiner hit in face by falling steel beam

House builder fined £60,000 for lack of site supervision
2 days ago

Major contractors going cool on road maintenance market

Highways England taking more work in-house and looking to work direct with supply chain
5 days ago

Infrastructure project final costs average 80% above bid prices

Success measures for projects should shift from an over-focus on costs towards whole-life benefit
5 days ago

Newcastle firm targets £50bn London rooftop homes sector

High Street Group buys London rooftop penthouse firm
5 days ago

London Bridge 39-storey student tower approved

Student accommodation projects return to the Capital
5 days ago

Kier clinches £22m Paisley town hall revamp

Main construction to start early next year
5 days ago

Consultation opens on £1bn trans-Pennine A66 dualling

Plan to dual eight stretches of highway from Penrith and Scotch Corner
5 days ago

Kier project and commercial teams at loggerheads

Insiders reveal tension between teams on major projects
6 days ago

Lords call for HS2 rethink to secure northern upgrades

Warning that HS2 costs are out of control
6 days ago

Margins rising as nmcn enjoys strong start to the year

Water business surging ahead as new housing division expands
6 days ago

Durkan names new CEO as revenue rises to £165m

Ronan Murphy promoted and plans to double revenue in five years
6 days ago

Wates submits first phase of £1bn London housing plan

Havering Council and Wates Residential submit plans for Napier and New Plymouth House site
6 days ago

Affordable and build to rent homes lift Countryside

House builder's modular timber panel factory in Warrington now fully operational
6 days ago

Partner wanted for £800m Salford Crescent plan

Preferred bidder to be named before the end of this year
7 days ago

Contractor services