Cladder falls ten metres onto factory floor

Grant Prior 9 months ago
Share

Main contractor Weiser Construction Ltd and Complete Cladding Systems Ltd have been fined a total of £310,000 after a worker suffered life changing injuries.

An HSE picture of the accident scene
An HSE picture of the accident scene

Leeds Magistrates’ Court heard how, on 4 January 2016, Brian Robinson was working as a sheeter cladder at the Weiser Construction site at the John Cotton factory in Mirfield, West Yorkshire.

He was on a factory roof fixing sheet metal cladding and capping to the gable end of an adjoining building.

While tying the cappings to the roof, Robinson fell through a roof light 9.7m into the active factory area below. He suffered an open fracture to his femur and multiple fractures to his pelvis.

Robinson underwent operations to insert six pins into his pelvis, two pins to the top and two pins to the bottom of his femur.

An HSE investigation found the original scaffold that had been constructed upon the roof had been removed prior to cladding works being completed.

Spandeck boards with guardrails were the preferred control measure but use of these boards meant that workers could not affix the handrails in situ.

No nets had been scheduled to be used in the area of the factory and as Robinson fell, the top half of his legs struck the top of a storage cage, approximately 2.4m high, before continuing his fall to the floor behind the storage cage.

Weiser Construction Ltd (now in liquidation) of Clark Business Recovery Ltd, Leeds pleaded guilty to safety breaches and  was fined £145,000 with £5,046.30 costs.

Complete Cladding Systems Ltd of Bishop Auckland also pleaded guilty and was fined £165,000 with £5,114.49 costs

After the hearing, HSE inspector Paul Thompson said: “Work at height, such as roof work, is a high-risk activity that accounts for a high proportion of workplace serious injuries and fatalities each year.

“This was a wholly avoidable incident, caused by the failure of the principal contractor to manage and monitor the works to ensure the correct work equipment was being used.

“This risk was further amplified by the cladding company’s failure to ensure suitable measures were in place to prevent persons falling a distance liable to cause personal injury.”

Latest news

Summer start for 350-flat Nottingham scheme

9-storey block to be built next to Nottingham station
3 hours ago

Fusion21 names decarbonising framework winners

Sixty eight firms secure places on £250m energy efficiency franework
5 hours ago

Bardsley crashed owing £45m to trade creditors

Manchester builder hit by toxic mix of contractual disputes and project delays
13 hours ago

Bardsley hit sends Anders Glass under

Manchester glass merchant and glazing contractor crashes
14 hours ago

Speller Metcalfe wins £14m Devon leisure centre deal

New Tarka Leisure Centre to offer ‘endless ski slope’
9 hours ago

Green light for UK’s first ‘super slender’ resi tower

Broad Street tower in Birmingham will be less than 10m wide but rise to 37 storeys
1 day ago

Higgins bags £44m job at Shredded Wheat Factory site

Over 200 homes planned for Welwyn Garden City site
1 day ago

Jackson gets go-ahead to start £22m road upgrade

Construction to start this spring after funding agreed for A2300 improvemnets
14 hours ago

Berkeley buys former Civil Service College site

New homes and a retirement village to be built after £50m sale
1 day ago

Bilfinger wins £58m pipework deal at Hinkley Point C

Latest award from EDF at giant nuclear site
1 day ago

£1bn South West Wales framework winners

Andrew Scott and Interserve secure major projects lot for first time
2 days ago

Japanese to build UK’s biggest offsite village

Sekisui House and Urban Splash get green light to build 400-home scheme
2 days ago

Part of Clacton Pier collapses during concrete pour

Part of existing deck falls into sea during structural refurbishment work
2 days ago

Race to start for Government’s first £500m hospital

Bidders Day next month for Leeds General Infirmary expansion
2 days ago

Morrison set for £50m Stirling women’s prison

Galliford Try arm in line for redevelopment of Cornton Vale women’s prison
2 days ago

Pipe fitter hit by 700kg water pump

Worker suffers multiple fractures during accident at east London site
2 days ago

Costain cuts in to take £290m A30 upgrade

Contractor set to build bypass after Taylor Woodrow fails to agree price with Highways England
5 days ago

Aerial platforms collide on rail maintenance site

Investigation launched after accident on tracks in Essex
4 days ago

JCB cuts UK production as coronavirus hits supply chain

A quarter of JCB's component suppliers in China are on shutdown
5 days ago

Manchester Mayfield phase 1 gets green light

Work to start this autumn on new park, two office buildings and major car park
5 days ago

Boost your online presence – join the Enquirer Directory

Site for suppliers and buyers showcases products, services and latest stories
2 years ago

Sisk appoints new northern MD

Alan Rodger replaces Guy Fowler as head of the northern operation
5 days ago

Plan for £100m revamp of Manchester CIS tower

Landmark 31-storey tower refit plan as facade reaches end of design life
5 days ago

Willmott Dixon tipped for £120m Stockport Interchange

Work to start this spring on bus station scheme
5 days ago

Mace to build laser centre

Latest contract win on £81m research complex
5 days ago

Skanska scoops £240m London office job

Work set to start on 420,000 sq ft City office scheme at 20 Ropemaker Street
6 days ago

Chancellor resigns just weeks before the Budget

Sajid Javid quits with Budget due on March 11
5 days ago

Cheaper adjudication to resolve smaller dispute claims

Claims of £50,000 or less will now be worth pursuing
6 days ago

GPE revs up for £600m trio of office projects

Developer preparing to deliver 820,000 sq ft of London projects
6 days ago

Plans unveiled for £260m Digbeth cultural quarter

Over 1,000 flats and a 120-bed hotel planned at Upper Trinity Street scheme
6 days ago

Contractor services