Main contractor Weiser Construction Ltd and Complete Cladding Systems Ltd have been fined a total of £310,000 after a worker suffered life changing injuries.

An HSE picture of the accident scene
An HSE picture of the accident scene

Leeds Magistrates’ Court heard how, on 4 January 2016, Brian Robinson was working as a sheeter cladder at the Weiser Construction site at the John Cotton factory in Mirfield, West Yorkshire.

He was on a factory roof fixing sheet metal cladding and capping to the gable end of an adjoining building.

While tying the cappings to the roof, Robinson fell through a roof light 9.7m into the active factory area below. He suffered an open fracture to his femur and multiple fractures to his pelvis.

Robinson underwent operations to insert six pins into his pelvis, two pins to the top and two pins to the bottom of his femur.

An HSE investigation found the original scaffold that had been constructed upon the roof had been removed prior to cladding works being completed.

Spandeck boards with guardrails were the preferred control measure but use of these boards meant that workers could not affix the handrails in situ.

No nets had been scheduled to be used in the area of the factory and as Robinson fell, the top half of his legs struck the top of a storage cage, approximately 2.4m high, before continuing his fall to the floor behind the storage cage.

Weiser Construction Ltd (now in liquidation) of Clark Business Recovery Ltd, Leeds pleaded guilty to safety breaches and  was fined £145,000 with £5,046.30 costs.

Complete Cladding Systems Ltd of Bishop Auckland also pleaded guilty and was fined £165,000 with £5,114.49 costs

After the hearing, HSE inspector Paul Thompson said: “Work at height, such as roof work, is a high-risk activity that accounts for a high proportion of workplace serious injuries and fatalities each year.

“This was a wholly avoidable incident, caused by the failure of the principal contractor to manage and monitor the works to ensure the correct work equipment was being used.

“This risk was further amplified by the cladding company’s failure to ensure suitable measures were in place to prevent persons falling a distance liable to cause personal injury.”

Latest news

Taylor Wimpey to loan subbies £600 a month

£5m Pay It Forward Scheme to support 2,750 self employed workers
1 hour ago

Latest government advice on safe site working

Workers to be kept two metres apart "as much as possible"
4 hours ago

Balfour Beatty under fire for 30 Crossrail redundancies

Union slams redundancies as cruel during pandemic and calls for furloughing
6 hours ago

Gleeson gears-up for post pandemic work push

Share placing to raise £16m with £4m set aside for subcontractors in supply chain
6 hours ago

Coronavirus update for construction: Wednesday April 8

The latest advice and information from industry trade bodies
6 hours ago

Winvic tops March contracts league

Coronavirus outbreak afflicts March orders
13 hours ago

Mace starts re-opening sites

"Construction must find a way to work safely to support the UK’s economic recovery"
1 day ago

Kier to convert Swansea film studio into hospital

Andrew Scott also advances Neath sports academy conversion
18 hours ago

BAM Construct to furlough 440 staff on full pay

Board and senior managers take 20% salary cut
21 hours ago

Plant theft soars as construction sites close

Thieves taking advantage of coronavirus impact to steal site equipment
15 hours ago

Keep the industry updated by joining the Enquirer Directory

Membership lets construction know you are open for business now or in the future
2 years ago

Scottish sites ordered to close unless on essential list

Scottish government publishes list of what construction work can carry on: Full details
2 days ago

Private clients urged not to come after contractors

Industry urged to work together through pandemic or risk legal war
2 days ago

Vistry Partnerships bags £213m haul of affordable homes jobs

Clearance given to start pre-commencement works during covid-19 crisis
1 day ago

Competition concerns intensify over Kingspan panels deal

Acquisition of SIG's Building Solutions could leave contractors with few alternative suppliers to choose from
1 day ago

Coronavirus update for construction: Tuesday April 7

The latest advice and information from industry trade bodies
1 day ago

Model contracts to fast-track Covid-19 extra contractor payments

Cabinet office publishes contract variations for contractor payments on stalled sites
1 day ago

Builders call on CITB to cancel levy this year

Pressure mounts on skills body to do more to help industry which funds it
1 day ago

Galliard Homes suspends recladding job in London

160 workers stood down as major reclad of New Capital Quay site closed over social distancing
1 day ago

Murphy MD joins Byrne Group to head concrete frame arm

New MDs appointed at Byrne Bros and Ellmer
2 days ago

BAM to build 500-bed Harrrogate Nightingale covid-19 hospital

Harrogate Convention Centre will be transformed within 14 days
2 days ago

Construction buyers report steepest work drop in a decade

Coronavirus crisis sparks major slump in March
2 days ago

Supply chain “disconnect” threatens to halt site work

Contractors lack vital materials while suppliers sat on stocks as sites shut
2 days ago

Highways England to speed up payments and procurement

Market engagement starts for £3.6bn Operations Scheme Delivery Framework
2 days ago

Skanska seals £193m Welsh Water deal

AMP7 deal covers water treatment works, dams and pipe installation
2 days ago

Gleeson to prioritise house sales to key workers after crisis

House builder furloughs three-quarters of staff as focus turns to preparing to restart work quickly
2 days ago

Coronavirus update for construction: Monday April 6

The latest advice and information from industry trade bodies
2 days ago

Four contractors mobilised for Glasgow temporary hospital

Glasgow’s Scottish Events Campus to be transformed in two weeks
5 days ago

Ministers talking directly to construction chiefs over Covid-19

Bosses talking direct to government as trade bodies set-up Covid-19 task force
5 days ago

London most costly city in the world for construction

Cost survey on eve of pandemic ranked Bristol as more expensive than Manchester
3 days ago

Contractor services