Infrastructure project final costs average 80% above bid prices

Aaron Morby 5 years ago
Share

Infrastructure project outturn costs are running nearly 80% higher than winning tender prices, according to new project data.

 London 2012 games is considered a crowning success, yet the games cost over three times the original budget.  The evolution of the budget and the political and public acceptance of this overspend, compares starkly with attitudes to Crossrail at 26% over budget
London 2012 games is considered a crowning success, yet the games cost over three times the original budget. The evolution of the budget and the political and public acceptance of this overspend, compares starkly with attitudes to Crossrail at 26% over budget

An influential report from Institution of Civil Engineers, which publishes the fresh figures from 25 projects, warns that the sector is facing a twin market failure.

A combination of unforeseeable cost increases driven by both external and project risks and low contractor margins, depressed by fears of not winning major project work, has stifled innovation, skills and sustainability, warn senior engineers.

The regular failure to deliver to budget has prompted calls for mindset changes among clients about cost envelopes during early project planning, more detailed scoping and much fairer allocation of risk with contractors.

The report is published as contractors planning to deliver HS2 main civils packages are locked in talks to agree on final bid prices near original cost estimates.

A leading infrastructure contractor supplied figures for projects awarded between 2009 and 2018 on the proviso it remained anonymous.

Only one project was delivered within the original tender price, with project costs swelling by 80% on average above the original contract value on the rest

The ICE emphatically rules out excessive profit taking, pointing out pre-tax margins in construction fell from just under 3% in 2013 to an average of –0.9% in 2018.

Miles Ashley, Chair of the report’s Steering Group, said: “Industry and government need to work smarter, find ways to reduce the disparity between forecasts and outturns, but also to change the narrative and ensure the wider public, the end users, are also aware of the whole-life benefits these incredible infrastructure projects are bringing to them.”

Recommendations


  • Infrastructure owners should complete scope, design and exploration before work starts to avoid scope creep or retroactive changes, taking steps to include contractors in design at an early stage.
  • The Government and infrastructure owners must move away from capital cost as the most important metric when assessing project benefits, and recognise the importance of whole-life economic, social and environmental value.
  • All public infrastructure owners undertaking procurement must award contracts based on a cost estimate range, using a should-cost estimate as a reference point, with an amount of contingency allocated appropriate to the level of project maturity.
  • Principles set out in the Government Outsourcing Playbook should be mandatory for infrastructure owners, this includes infrastructure owners undertaking should-cost modelling to help inform their expectations and knowledge of appropriate tender prices during the procurement process.

Report: Reducing the gap between cost estimates and outturns for major infrastructure projects and programmes

Latest news

Plans go in for huge Olympic Park construction hub

Bow Goods Yard could deliver 3.5m tonnes of materials a year to sites across London
3 hours ago

Surgo Construction went down owing £4.5m

Biggest creditor is Bellway Homes after dispute on housing job
5 hours ago

Plan for £100m Liverpool Baltic station

Construction work could begin next year
6 hours ago

Vistry seals £157m West London housing deal

Around 575 homes to be built at Merrick Place scheme in Ealing
5 hours ago

Streamlined Watkin Jones returns to profit in first half

Multi-room specialist sees secured work pipeline hit £1.4bn
5 hours ago

Bellway hires ex-brickie as group construction chief

James Griffin to oversee move to the Future Homes Standard and timber frame.
5 hours ago

Persimmon under fire for delays to £10m relief road

West Suffolk Council serves Breach of Condition Notices after timetable slips again
6 hours ago

BAM wins £33m Kent secondary school job

Replacement Swanley academy to be built at live school site
5 hours ago

Aluminium cladding specialist collapses

Melton Mowbray-based firm worked for several main contractors
1 day ago

Brickwork contractor Lee Marley returns to profit

Affordable and rental homes demand lifts brickwork contractor
1 day ago

Housing contractor Durkan suffers second year of losses

More fire safety provisions tip firm into £3.9m loss
1 day ago

Farrans makes breakthrough on tricky tunnel job

Tunnel under Tees latest part of new £155m water pipeline job
1 day ago

Heidelberg buys aggregates and earthworks specialist B&A

Latest deal follows acquisition of Mick George
1 day ago

Flagship biodiversity net gain scheme flawed

NAO warns Government's flagship green development scheme at risk of failure
4 days ago

Plan in for £3bn Lincolnshire mega data centre

3.3m sq ft Humber Tech Park will be one of Europe's largest data centres
4 days ago

Green light for Digbeth 1,300 homes scheme

Warner’s Fields scheme to start with excavation and landscaping of the River Rea
4 days ago

£210m M3 Junction 9 upgrade gains consent

VolkerFitzpatrick to start work in early 2025 on Winnall roundabout, near Winchester
4 days ago

United Living wins 14-year L&Q homes repairs deal

Trafford housing upkeep deal worth £205m
4 days ago

£400m Lewisham resi-led scheme advances

Land deal paves way for Amro Partners' 1,000-home London scheme
4 days ago

McLaren gets go-ahead for Grade II listed Leeds student scheme

Springfield House to be revamped and two new wings added
4 days ago

Piling giant to fit people alarms on all rigs

Cementation Skanska upgrades site safety systems
4 days ago

Vistry to make £800m profit after subcontractor cost cuts

House builder bullish about shareholder returns after asking suppliers for discounts
5 days ago

Shareholders approve £2.5bn Barratt and Redrow merger

Final hurdle is for the competition regulator to approve the deal.
5 days ago

Green light for £80m Leith waterfront revamp

Build-to-rent homes and student accommodation scheme to be built
5 days ago

Tilbury Douglas clears Interserve legacy jobs to return to profit

Revenue tops £500m in first year as standalone contractor
6 days ago

Land deal paves way for Manchester civil service office hub

Government buys five acres at former Central Retail Park
5 days ago

Speller Metcalfe wins Wolverhampton library upgrade

Full works are due to start in the autumn
5 days ago

Skills shortage puts big infrastructure projects at risk

Government failing as an intelligent client and now over-reliant on consultancies
6 days ago

Contractors face further insulation board price hikes

Cost of PIR insulation boards set to rise another 10%
6 days ago

Henry Boot wins £36m Rotherham Markets job

Project involves upgrading existing market and building a new library
6 days ago

Contractor services