Infrastructure project final costs average 80% above bid prices

Aaron Morby 5 years ago
Share

Infrastructure project outturn costs are running nearly 80% higher than winning tender prices, according to new project data.

 London 2012 games is considered a crowning success, yet the games cost over three times the original budget.  The evolution of the budget and the political and public acceptance of this overspend, compares starkly with attitudes to Crossrail at 26% over budget
London 2012 games is considered a crowning success, yet the games cost over three times the original budget. The evolution of the budget and the political and public acceptance of this overspend, compares starkly with attitudes to Crossrail at 26% over budget

An influential report from Institution of Civil Engineers, which publishes the fresh figures from 25 projects, warns that the sector is facing a twin market failure.

A combination of unforeseeable cost increases driven by both external and project risks and low contractor margins, depressed by fears of not winning major project work, has stifled innovation, skills and sustainability, warn senior engineers.

The regular failure to deliver to budget has prompted calls for mindset changes among clients about cost envelopes during early project planning, more detailed scoping and much fairer allocation of risk with contractors.

The report is published as contractors planning to deliver HS2 main civils packages are locked in talks to agree on final bid prices near original cost estimates.

A leading infrastructure contractor supplied figures for projects awarded between 2009 and 2018 on the proviso it remained anonymous.

Only one project was delivered within the original tender price, with project costs swelling by 80% on average above the original contract value on the rest

The ICE emphatically rules out excessive profit taking, pointing out pre-tax margins in construction fell from just under 3% in 2013 to an average of –0.9% in 2018.

Miles Ashley, Chair of the report’s Steering Group, said: “Industry and government need to work smarter, find ways to reduce the disparity between forecasts and outturns, but also to change the narrative and ensure the wider public, the end users, are also aware of the whole-life benefits these incredible infrastructure projects are bringing to them.”

Recommendations


  • Infrastructure owners should complete scope, design and exploration before work starts to avoid scope creep or retroactive changes, taking steps to include contractors in design at an early stage.
  • The Government and infrastructure owners must move away from capital cost as the most important metric when assessing project benefits, and recognise the importance of whole-life economic, social and environmental value.
  • All public infrastructure owners undertaking procurement must award contracts based on a cost estimate range, using a should-cost estimate as a reference point, with an amount of contingency allocated appropriate to the level of project maturity.
  • Principles set out in the Government Outsourcing Playbook should be mandatory for infrastructure owners, this includes infrastructure owners undertaking should-cost modelling to help inform their expectations and knowledge of appropriate tender prices during the procurement process.

Report: Reducing the gap between cost estimates and outturns for major infrastructure projects and programmes

Latest news

Beard expands reach as revenue hits record £179m

Builder start 2024 with healthy head of work
3 hours ago

Race to start for £25m Cardiff twin tower reclad jon

Cardiff council to use SEWCAP to bid Butetown high rise flats revamp
7 hours ago

Gove calls up ‘super-squad’ to clear London planning log-jam

Specialist planning team first to unlock 7,000 homes in Newham and Greenwich
11 hours ago

Permasteelisa in £35m cladding win at St John’s Wood Square

Italian specialist to start work on luxury resi site by the end of this year
13 hours ago

Investor pumps another £30m into low carbon builder

House builder Greencore gets more funding as latest results reveal £4m loss
15 hours ago

800-bed Leeds student and shops scheme approved

Major three-block scheme will replace The Core shopping centre in the city
19 hours ago

Modular homes specialist files administration notice

Lighthouse bosses battle to save the business
20 hours ago

Go-ahead for £175m Birmingham Broad Street tower

Work to start on 47 storey build to rent tower in September
20 hours ago

Erith trading rebounds after lengthy bid-rigging probe

Staff paid £1.5m bonus after year of growth and return to profit
20 hours ago

Balfour and Costain win vast power and carbon capture job

Nine firms to share £4bn Teesside net zero work bonanza
4 days ago

First ‘Great Grid Upgrade’ job goes to MGroup and Murphy

Works to start this summer on £400m Yorkshire GREEN electricity pylon upgrade
4 days ago

London council can no longer police planning applications

Planing row reveals Greenwich officials no longer follow-up to check on developments
4 days ago

Surgo Construction falls into administration

46 jobs lost as historic contractor ceases trading
5 days ago

Mace fresh start date for £90m Natural History Museum hub

Reading project to build store for 28m specimens to start early next year
4 days ago

Competition watchdog probes Barratt Redrow merger

CMA opens investigation into creation of mega house builder
4 days ago

Safety chiefs act to avoid building control crisis

Three-month extension to deadline for professionals to prove their competence
4 days ago

TClarke hits £500m turnover target but profitability slips

Big work-winning year sees order book swell 70% to £943m
4 days ago

Just 10% of £10bn Levelling Up funding spent by councils

Speed of delivering 'shovel-ready' projects fails to meet expectations
4 days ago

Six win £1bn North West & Central railway works deal

Story, Murphy and Amey feature in five-year CP7 framework
4 days ago

Willmott Dixon names new finance chief

James Mackenzie joins from Willmott Dixon's Eco World development JV
4 days ago

Ilke Homes name reappears after £320m collapse

New brand Homespace now owns modular designs after Ilke failure
5 days ago

Second staircase rule costs Vistry £19m

Firm reopens East Midlands timber frame manufacturing plant
5 days ago

Clients urged to get ahead of contractor recovery cycle

T&T says investment decisions must be ‘made not delayed’ for best value
5 days ago

Fife groundworks and plant hirer goes under axing 35 jobs

James Penman (Plant Hire) falls into administration in 50th anniversary year
5 days ago

Smart Motorway Programme Alliance chief to step down

Tony Slater is moving on to take up fresh career challenge
5 days ago

Balfour M25 workers vote for strike in pay row

Maintenance crews to down tools over "meagre" pay offer
6 days ago

Andrew English returns to Skanska as infrastructure boss

Returning director replaces Jonathan Willcock who is off to Costain
6 days ago

Construction back in growth as output rises 1.1% in January

Green shoots of recovery as private housing returns to growth
6 days ago

UK Construction shines in solid year for Balfour Beatty

Operating margin improves to 2.3% at UK construction arm
6 days ago

JJ Rhatigan wins £49m London co-living homes job

Wood Lane project will deliver over 200 flats
6 days ago

Contractor services