Grenfell: 75% of unsafe blocks still to be reclad

Aaron Morby 5 years ago
Share

Two years after the Grenfell disaster three-quarters of high rise buildings identified with unsafe cladding still need to be retrofitted.

Grenfell Campaigners project fire safety warning onto a Manchester block (Credit: Grenfell United)
Grenfell Campaigners project fire safety warning onto a Manchester block (Credit: Grenfell United)

Just 105 private and public buildings over 18m have completed remediation works from the 433 identified to have been fitted by unsafe aluminium cladding.

Slow progress and lack of ambition to make buildings more resistant to fire has been thrown into the spotlight by Grenfell campaigners who have projected warnings on tower blocks in London, Manchester and Newcastle.

Also industry fire protection chiefs have warned that even the Government’s fresh planned changes to building regulations don’t go far enough.

Jonathan O’Neill, managing director, Fire Protection Association, said he wanted to see a total ban on combustible building materials on all high-risk buildings, such as schools, hospitals, nursing homes, blocks of flats – not just those buildings over 18m.

“We also want a ban on single staircases in all tall buildings, because in the event of a fire you need at least one staircase for people to be able to evacuate the building, and a second staircase for the fire and rescue services for entry,” he said.

There is also growing concern about the performance of other cladding materials like high-pressure laminates.

It is estimated that a further 340 high rises are clad with these sort of materials. Last month the Government commissioned the FPA to carry out tests on HPLs.

328 buildings to be remediated (progress)


  • 102 are social sector residential buildings; (81 started)
  • 163 are private sector residential buildings; (17 started)
  • 27 are student accommodation buildings; (4 started)
  • 29 are hotels: (3 started)
  • 7 are publicly owned buildings, all health buildings (2 started)

Also in May, the government committed to fund the remediation of high-rise private sector residential buildings with ACM but funding guidance criteria will not be published until July.

So far the government has placed a ban on combustible materials on new high-rise homes, which came into force on 21 December with a two-month transitional period.

Last week the government published consultation on recommendations set out in the Hackitt Review for a new safety regime for designing and building high-rise homes.

Latest news

Morgan Sindall to build former Willmott Dixon leisure job

New contractor appointed on
11 hours ago

Graham consortium wins £400m Manchester job

Equitix consortium to now work up DBFO plans for University of Manchester’s Fallowfield Campus
7 hours ago

Keltbray looking to sell infrastructure business

£378m turnover rail, energy and highways business up for sale
18 hours ago

Innovative viaduct building method used for first time in UK

HS2 contractors will build nine viaducts in Delta Junction using special cantilevered process
18 hours ago

Unite buys London site to fast-track 444-bed student scheme

£800m to be spent on London development pipeline in next five years
18 hours ago

CITB awards £2.5m of contracts to management consultant

Three outsourced deals in the last year for "project leadership and management consultancy"
18 hours ago

Village centre approved for 6,000-home new town plan

Hampshire's Welborne Garden Village plan has been in the pipeline for two decades.
17 hours ago

£3m fine after cherry picker demolition death

Court rules after tragedy during decommissioning of gas rig
18 hours ago

BAM plans wave of job cuts at UK Construction arm

Co-op Live arena plunges Bam Construction to £19.5m first-half loss
2 days ago

Robot tunnel builder goes into administration

Hypertunnel was hoping to revolutionise how underground structures are built
2 days ago

Wates to build £86m Guildford Council housing scheme

40% of the 248 homes will become council homes under partnership deal
2 days ago

“Scrap CITB” say three quarters of construction firms

Payroll giant Hudson Contract calls for CITB to be absorbed into new Skills England training body
2 days ago

£100m Prestwich Village revival approved

Vinci and Willmott Dixon in chase for Muse-led regeneration scheme
2 days ago

Carbon negative asphalt aggregate trialled on M11

Skanska and Tarmac test CO2 absorbing aggregate material on stretch of Essex motorway
2 days ago

Father and son sentenced over covid construction loan fraud

Bristol builders given suspended jail sentences over bogus Bounce Back Loans
2 days ago

Beck Interiors files administration notice

Supply chain has suffered delayed payments from £139m-turnover luxury fit out specialist
3 days ago

Green light for York Central civil service office hub

£60m office project accelerates York Central goods yard redevelopment
3 days ago

Blenheim House Construction enters administration

Administrators looking at options on present projects
3 days ago

Profits rise at Esh Group with more to come

Contractor confident about year ahead as market conditions move in right direction
3 days ago

Piling specialist Van Elle sees housing orders rise 30%

Mark Cutler says firm on course to deliver 10% annual sales growth
3 days ago

HS2 to spend £100m shutting sites where work never started

Remediation of sites no longer needed for cancelled Phase 2 will take three years
3 days ago

Willmott Dixon wins £61m deal for new Army dog unit

Contractor to revamp Kendrew Barracks in Rutland
3 days ago

Stockport advances 4,000-home Town Centre East plan

Council seeks consultants to steer plan for 280-acre area in the city
3 days ago

ISG sale imminent as buyers set-up UK holding company

South African nutrition entrepreneur and Australian partner primed to take over
4 days ago

CR Construction wins £210m Manchester towers

Construction to start next year on four blocks ranging from nine to 34-storeys
4 days ago

Southern Housing to rationalise supply chain following merger

Firms put on alert for £1.7bn construction framework renewal
4 days ago

Decision delayed on 52-storey Isle of Dogs tower

Hong Kong developer plans 460 flats block next to Millwall Inner Dock
4 days ago

Go-ahead for £850m North London estate rebuild

Flagship Edmonton housing estate redevelopment will deliver 2,000 new homes
4 days ago

Mace lands £184m Oxford Science Park contract

Contractor to build trio of laboratory and office buildings
5 days ago

Worker paralysed in 30ft fall during electricity pylon demolition

Specialist firm fined £240,000 after court hears linesman attached lanyard to a loosened steel section
4 days ago

Contractor services