NAO raises alarm over cost of finishing Carillion hospitals

Aaron Morby 3 years ago
Share

Spending watchdog the National Audit Office has sounded the alarm about the risk of further significant cost increases finishing Carillion’s two major hospital projects.

Contract to replace cladding at the Royal Liverpool is now out to bid
Contract to replace cladding at the Royal Liverpool is now out to bid

Investigators are particularly concerned about the risks of rectifying the badly-built Royal Liverpool hospital.

An in-depth report into both the Midlands Metropolitan and Royal Liverpool projects blames the disastrous outcomes on Carillion pricing the jobs too low to meet specifications.

On present estimates, both hospitals will cost double the original budgets to build and will complete between three and five years late.

Going forward the report raises concerns about Laing O’Rourke’s remediation and finishing agreement with the local Liverpool NHS Trust because of an absence of contractual incentives to control costs.

At the Midland Metropolitan, the Sandwell Trust has negotiated a ‘target price’ for Balfour Beatty.

The report hopes that prices should not rise on this hospital unless the Trust changes the scope of the project or there are unforeseen problems with Carillion’s work.

Construction of the Royal Liverpool is now expected to cost at least £724m compared with the original £350m budget. This includes the current estimate of £293m for remedial work to the structure and to complete the construction.

The construction of the Midland Metropolitan is now expected to cost at least £663m compared with £350m in the original business case. This includes £315m still to be spent to complete.

The report reveals the background behind the discovery of cracked concrete beams, first highlighted by the Enquirer in a story on the 13 January 2017.

Carillion investigated while work continued during 2017 and found cracks in three beams.

By December 2017, just before Carillion went into liquidation, the hospital was at a late stage of construction, with interior fit-out almost complete.

Carillion told the Trust that the issues with the beams would be fixed by February 2018 and estimated that the build should be complete by mid-April 2018, 13 months late.

The full extent of the building’s problems then started to be unearthed as Arup surveyed the building.

By October 2018, the number of parts of the structure that required significant rectification had increased to about 100.

This required some interior walls, wiring, piping, and heavy machinery and equipment to be stripped out, mainly across three floors of the hospital.

Costs kept soaring as Arup also discovered large parts of the building’s cladding did not conform to the relevant fire regulations.

The cost of fixing the cladding was first put at £5m.

Further work has since revealed that the cost of fixing the cladding will be about 10 times this initial estimate and that there may also be deficiencies in the internal fire protection and the mechanical, electrical and plumbing systems.

Remedial costs soar as extent of building faults uncovered


The cost of maintaining both hospitals has also risen due to changes in the market since the PFI contracts were signed, and the delays have also led to cost increases on other projects.

The use of PFI means that the private sector will end up paying most of the cost increase, and the public sector is only expected to pay 1% more in real terms across both projects than was originally expected.

Latest news

Domis set for £195m Boddingtons Brewery scheme

Developer Salboy buys Manchester site to kickstart long-awiated 556 homes project
21 mins ago

John Lewis £500m funding deal to build 1,000 rental homes

Deal to advance BTR flats at store sites in Bromley, West Ealing and Reading
13 hours ago

Esh launches new housing retrofit division

Esh Retrofit Solutions will target market to improve the energy performance of social rented homes
1 min ago

Eric Wright wins tricky £52m Liverpool transformation

Contractor working with engineers at Ridge and Partners on "challenging" Stanley Lock Flight site
3 days ago

Investment giant buys Bristol M&E contractor

RDCP Infrastructure acquires Avon Combined Electrical Services
3 days ago

Demolition start for £50m Farnworth town centre rebuild

Caddick Construction is tipped for main works due to start in the spring
3 days ago

L&G Modular strikes deal to build 1,000 affordable homes

Modular homes business teams up with Hampshire's Vivid housing association
3 days ago

Former Erith operations director joins John F Hunt

Scott Exell named new operations director at demolition specialist John F Hunt
3 days ago

Green light for £135m Leeds twin tower resi scheme

Construction to start in New Year on 500 build-to-rent apartments
4 days ago

Mace hits 1m tonnes carbon saving target for clients

Present work pipeline betters 2026 carbon emission saving target
3 days ago

Plans in for £40m surf park at former Kent colliery

Seahive surf lagoon and health resort will be built near Deal
4 days ago

Crushed demolition worker vows to return to industry

Shannon Brasier hoping to return to construction following horror accident
4 days ago

Mount Anvil to start 900-home North London estate rebuild

Planning approval paves way for Barnsbury Estate rebuild in Islington
4 days ago

Green light for major laboratory campus in Cambridge

Developer BioMed to tender first building on 600,000 sq ft lab complex in the New Year
4 days ago

Belfast firm signs the biggest work deal yet under Project Gigabit

Fibrus to hook-up rural Cumbria to lightning-fast broadband under £108m deal
4 days ago

McLaren wins Leeds logistics park contract

Work to start imminently on warehouse complex for Firethorn Trust
5 days ago

Work restarts on £683m waste power plant after site death

Construction suspended for a week of investigations following fatality
5 days ago

Demolition starts on £135m Wigan Galleries scheme

Contractor BCEGI starts work on project to redevelop Wigan town centre
5 days ago

Amey CEO to step down following private equity buyout

Amanda Fisher to leave once business is transferred to new owners
5 days ago

New body set up to vet plant operator card schemes

Contractor trades bodies unite to tackle competency concerns over plant operator skills cards
5 days ago

Kier leads switch to hybrid battery generators

Battery units work alongside smaller generators cutting run times by nearly 60%
5 days ago

Plans in for first Leeds co-living scheme

Watkin Jones submits plan to convert old Direct Line HQ into 230 studio flats
5 days ago

Demolition worker crushed by excavator

Court hears 20-year-old woman was left with "life changing injuries"
6 days ago

Government pays £700m for 50% stake in Sizewell C

New body, Great British Nuclear, will be set up to develop pipeline of nuclear projects
6 days ago

Costain wins Heathrow Airport asset renewal deal

Firm takes early contractor involvement role in Terminal 2 baggage handling upgrade
6 days ago

Worker killed on £683m waste power plant site

Fatal collision involving heavy goods vehicle on giant north London site
6 days ago

HS2 JV shifts four Wembley Stadiums of earth in record time

EKFB team digs and hauls 15 million cu m of muck in 20 months
6 days ago

Milestone wins £300m Wiltshire highways upkeep

Ringway will hand over to Milestone in March next year
6 days ago

Low-risk business model helps Renew post record results

Renew reveals latest acquisition with £15.6m purchase of water specialist Enisca
6 days ago

London Albert Embankment hotel towers approved

Two separate hotels rising to 26 and 29 storeys approved
6 days ago

Contractor services