HS2 must start by March to avoid serious cost rises

Aaron Morby 5 years ago
Share

The Government’s spending watchdog has warned that any further delays in taking a decision on HS2 will dramatically impact on forecast construction costs.

Contractrors must start main works before the end of March to avoid further significant delays and cost rises
Contractrors must start main works before the end of March to avoid further significant delays and cost rises

An investigation into the HS2 project by the National Audit Office said the £30bn cost envelope for phase one is now more bolted down, but raised concern that costs for phase two were more uncertain.

Since April 2017, the forecast cost of phase one main civils has jumped 85% to £10.7bn.

Auditors have warned that any delays beyond March will dramatically increase costs on the project’s second phase.

If work does not begin by this date, the schedule may be delayed or compressed further because some of the construction work can only be done at certain times of the year.

Delays would also compress later parts of the programme, such as integrating the signalling and control systems, which are complex and risky parts of delivering the project on time and budget.

Auditors revealed that shifting the risks on targeted construction costs has saved £1bn through contractors reducing prices in response to the reduced risks.

The report says that HS2 revisions to its commercial approach were sensible but carried risks that it must manage.

Under new arrangements, contractors will no longer be liable for cost increases above a fixed target price.

Instead, HS2 has developed an estimated cost for the works with its contractors that will leave HS2  responsible for funding increases above the estimated cost, while contractors would lose a proportion of their fee for building the railway if they fail to meet cost and schedule milestones.

The NAO said that HS2 must now develop its capability to manage the programme to avoid further cost rises.

The report said: “We welcome the increased realism on the estimated cost and schedule for the programme. However, significant risks remain.

“While the estimated cost and schedule for Phase One are now on a stronger footing, the challenge of getting Phase One into construction, and of monitoring and managing the programme as it progresses, is considerable.”

Phase Two is at a far earlier stage of development with many important decisions to be made before HS2 Ltd and the Department can improve cost and schedule estimates.

HS2 has purchased 66% of the land required to build Phase One and has spent £7.4bn in preparations to start.

The full project cost now sits between £65bn and £88bn (2015 prices), between 17% and 58% more than the available funding of £56bn agreed.

Welcoming the report, HS2 said: “As the NAO recognises, our work – along with a greater understanding of the ground conditions and build requirements – means Ministers have robust cost estimates for Phase One of the HS2 project.”

The High Speed Rail Group made up of contractors and suppliers, said:  “If the Government want to fulfil their promise of an infrastructure revolution, HS2 must be completed in full, without further dither and delay.

“The alternatives spoken of are many years behind HS2 in terms of readiness to begin work and some, like Northern Powerhouse Rail, require HS2 to be delivered to realise their full benefits.”

Robert Nisbet, director of nations and regions at the Rail Delivery Group, which represents train operators and Network Rail said: “It’s time to inject some realism into the debate about HS2.

“There are no shovel ready alternatives. To cancel it would be to worsen punctuality and overcrowding on the railway for years to come, throttling future economic growth and damaging the environment by encouraging car travel.”

Latest news

BSR backlog swells as new build approvals run to 36 weeks

First official Government figures expose full extent of Gateway project logjam
19 hours ago

Repair slowdown drags down construction output

New work activity rises in May despite overall 0.6% output fall
19 hours ago

Equans suffers £29m loss as new build exit drags on

Refocused retrofit contractor still dogged by legacy losses despite profitable core work
19 hours ago

Scaffolding trade body NASC facing discrimination claim

Former training manager to take trade body to Employment Tribunal
20 hours ago

ACS lands lead role on Stafford transformers lab

Contractor to start main £20m expansion in live site environment
19 hours ago

GRAHAM sees profits rise despite dip in turnover

Record order book as contractor confident about future prospects
20 hours ago

Nixon Hire sells 200-strong welfare van fleet to Sunbelt

Sunbelt more than doubles mobile site welfare capability
2 days ago

Henry family and directors face claims topping £31m

Administrators chasing dividend payout, unpaid loans and family benefits
2 days ago

Vistry eyes second-half affordable homes work surge

Government rent reforms and funding pledges power-up work pipeline
2 days ago

JV picked to progress Severn-Thames water transfer plan

AtkinsRéalis and Stantec to map pipeline or canal link
2 days ago

Police catch on the run construction boss

Director missing for months after failing to appear in court after site death
2 days ago

Green light for £800m Poplar estate revamp

Construction to start next year at Teviot Estate
3 days ago

Civil engineering trade body boss leaves to join Mace

CECA Chief Executive Alasdair Reisner joins consulting arm
3 days ago

House builders offer £100m to drop competition probe

CMA set to strike deal with cash going to affordable housing programmes
3 days ago

Transport Secretary axes £1.4bn road jobs in south east

Alexander pulls plug on A12 and A47 upgrades in budget crackdown
3 days ago

Fusion taps HG for first Birmingham student job

622-bed Bristol Road scheme kicks off contractor’s Midlands push
3 days ago

VolkerWessels UK parent group to sell core Dutch business

UK, German and North American operations remain with Dutch owner Reggeborgh
3 days ago

Union claims sex pests are rife in construction

Shock assault figures following Unite survey of 100 workers
3 days ago

Green light for two more City of London towers

Combined 77 more storeys of office schemes approved
4 days ago

John F Hunt starts enabling works on £200m Strand Premier Inn

Main contractor due to be appointed this summer
4 days ago

£200m deal unlocks full 1,000-home Digbeth scheme

Caddick has started early works on the Moda-led Stone Yard project
4 days ago

10 big road and rail upgrades get funding green light

£1.3bn A66 dualling, Simister Island junction upgrade and Midlands Rail Hub get funding
4 days ago

Design, build and finance plan for £1bn Cheddar 2 reservoir

South West Water starts pre-bid market engagement on 75km pipeline and reservoir
4 days ago

Illegal working blitz catches Indian builders

Home Office raids target migrants working cash-in-hand on sites
5 days ago

Major Sizewell concrete win for local supplier

Eastern Concrete Ltd wins its biggest ever contract
4 days ago

SIG chief put on gardening leave

New CEO appointed as Gavin Slark steps down immediately
4 days ago

Adjustable hard hat launched for different hair types

AtkinsRéalis initiative will also make PPE more comfortable for bald builders
4 days ago

Lynch appeal sees £800,000 abnormal load fine reduced to £10k

Judge rules original fine was was 'manifestly excessive'
5 days ago

Government calls up firms to explore PPP healthcare projects plan

New public-private partnership idea to be scoped out with contractors
5 days ago

Balfour Beatty terminates Danny Sullivan labour deals

Around 500 workers on HS2 will be moved to alternative agencies or be taken on direct
1 week ago