HS2 must start by March to avoid serious cost rises

Aaron Morby 3 years ago
Share

The Government’s spending watchdog has warned that any further delays in taking a decision on HS2 will dramatically impact on forecast construction costs.

Contractrors must start main works before the end of March to avoid further significant delays and cost rises
Contractrors must start main works before the end of March to avoid further significant delays and cost rises

An investigation into the HS2 project by the National Audit Office said the £30bn cost envelope for phase one is now more bolted down, but raised concern that costs for phase two were more uncertain.

Since April 2017, the forecast cost of phase one main civils has jumped 85% to £10.7bn.

Auditors have warned that any delays beyond March will dramatically increase costs on the project’s second phase.

If work does not begin by this date, the schedule may be delayed or compressed further because some of the construction work can only be done at certain times of the year.

Delays would also compress later parts of the programme, such as integrating the signalling and control systems, which are complex and risky parts of delivering the project on time and budget.

Auditors revealed that shifting the risks on targeted construction costs has saved £1bn through contractors reducing prices in response to the reduced risks.

The report says that HS2 revisions to its commercial approach were sensible but carried risks that it must manage.

Under new arrangements, contractors will no longer be liable for cost increases above a fixed target price.

Instead, HS2 has developed an estimated cost for the works with its contractors that will leave HS2  responsible for funding increases above the estimated cost, while contractors would lose a proportion of their fee for building the railway if they fail to meet cost and schedule milestones.

The NAO said that HS2 must now develop its capability to manage the programme to avoid further cost rises.

The report said: “We welcome the increased realism on the estimated cost and schedule for the programme. However, significant risks remain.

“While the estimated cost and schedule for Phase One are now on a stronger footing, the challenge of getting Phase One into construction, and of monitoring and managing the programme as it progresses, is considerable.”

Phase Two is at a far earlier stage of development with many important decisions to be made before HS2 Ltd and the Department can improve cost and schedule estimates.

HS2 has purchased 66% of the land required to build Phase One and has spent £7.4bn in preparations to start.

The full project cost now sits between £65bn and £88bn (2015 prices), between 17% and 58% more than the available funding of £56bn agreed.

Welcoming the report, HS2 said: “As the NAO recognises, our work – along with a greater understanding of the ground conditions and build requirements – means Ministers have robust cost estimates for Phase One of the HS2 project.”

The High Speed Rail Group made up of contractors and suppliers, said:  “If the Government want to fulfil their promise of an infrastructure revolution, HS2 must be completed in full, without further dither and delay.

“The alternatives spoken of are many years behind HS2 in terms of readiness to begin work and some, like Northern Powerhouse Rail, require HS2 to be delivered to realise their full benefits.”

Robert Nisbet, director of nations and regions at the Rail Delivery Group, which represents train operators and Network Rail said: “It’s time to inject some realism into the debate about HS2.

“There are no shovel ready alternatives. To cancel it would be to worsen punctuality and overcrowding on the railway for years to come, throttling future economic growth and damaging the environment by encouraging car travel.”

Latest news

Investment giant buys Bristol M&E contractor

RDCP Infrastructure acquires Avon Combined Electrical Services
3 hours ago

Demolition start for £50m Farnworth town centre rebuild

Caddick Construction is tipped for main works due to start in the spring
4 hours ago

L&G Modular strikes deal to build 1,000 affordable homes

Modular homes business teams up with Hampshire's Vivid housing association
4 hours ago

Former Erith operations director joins John F Hunt

Scott Exell named new operations director at demolition specialist John F Hunt
11 hours ago

Green light for £135m Leeds twin tower resi scheme

Construction to start in New Year on 500 build-to-rent apartments
19 hours ago

Mace hits 1m tonnes carbon saving target for clients

Present work pipeline betters 2026 carbon emission saving target
15 hours ago

Plans in for £40m surf park at former Kent colliery

Seahive surf lagoon and health resort will be built near Deal
1 day ago

Crushed demolition worker vows to return to industry

Shannon Brasier hoping to return to construction following horror accident
1 day ago

Mount Anvil to start 900-home North London estate rebuild

Planning approval paves way for Barnsbury Estate rebuild in Islington
1 day ago

Green light for major laboratory campus in Cambridge

Developer BioMed to tender first building on 600,000 sq ft lab complex in the New Year
1 day ago

Belfast firm signs the biggest work deal yet under Project Gigabit

Fibrus to hook-up rural Cumbria to lightning-fast broadband under £108m deal
1 day ago

McLaren wins Leeds logistics park contract

Work to start imminently on warehouse complex for Firethorn Trust
2 days ago

Work restarts on £683m waste power plant after site death

Construction suspended for a week of investigations following fatality
2 days ago

Demolition starts on £135m Wigan Galleries scheme

Contractor BCEGI starts work on project to redevelop Wigan town centre
2 days ago

Amey CEO to step down following private equity buyout

Amanda Fisher to leave once business is transferred to new owners
2 days ago

New body set up to vet plant operator card schemes

Contractor trades bodies unite to tackle competency concerns over plant operator skills cards
2 days ago

Kier leads switch to hybrid battery generators

Battery units work alongside smaller generators cutting run times by nearly 60%
2 days ago

Plans in for first Leeds co-living scheme

Watkin Jones submits plan to convert old Direct Line HQ into 230 studio flats
2 days ago

Demolition worker crushed by excavator

Court hears 20-year-old woman was left with "life changing injuries"
3 days ago

Government pays £700m for 50% stake in Sizewell C

New body, Great British Nuclear, will be set up to develop pipeline of nuclear projects
3 days ago

Costain wins Heathrow Airport asset renewal deal

Firm takes early contractor involvement role in Terminal 2 baggage handling upgrade
3 days ago

Worker killed on £683m waste power plant site

Fatal collision involving heavy goods vehicle on giant north London site
4 days ago

HS2 JV shifts four Wembley Stadiums of earth in record time

EKFB team digs and hauls 15 million cu m of muck in 20 months
3 days ago

Milestone wins £300m Wiltshire highways upkeep

Ringway will hand over to Milestone in March next year
3 days ago

Low-risk business model helps Renew post record results

Renew reveals latest acquisition with £15.6m purchase of water specialist Enisca
3 days ago

London Albert Embankment hotel towers approved

Two separate hotels rising to 26 and 29 storeys approved
3 days ago

Keltbray names new director of strategic engineering

Tim Lohmann takes up newly-formed role to drive innovative engineering solutions
3 days ago

Go-ahead for £200m lithium refinery on Teesside

Work to start next year on Europe's first lithium hydroxide processing plant
4 days ago

HS2 agency workers paid the wrong wages

Payroll software problems leave workers out of pocket
4 days ago

Electric car whizz joins O’Rourke

Contractor looking to learn tech lessons from other sectors
4 days ago

Contractor services