HS2 must start by March to avoid serious cost rises

Aaron Morby 6 months ago
Share

The Government’s spending watchdog has warned that any further delays in taking a decision on HS2 will dramatically impact on forecast construction costs.

Contractrors must start main works before the end of March to avoid further significant delays and cost rises
Contractrors must start main works before the end of March to avoid further significant delays and cost rises

An investigation into the HS2 project by the National Audit Office said the £30bn cost envelope for phase one is now more bolted down, but raised concern that costs for phase two were more uncertain.

Since April 2017, the forecast cost of phase one main civils has jumped 85% to £10.7bn.

Auditors have warned that any delays beyond March will dramatically increase costs on the project’s second phase.

If work does not begin by this date, the schedule may be delayed or compressed further because some of the construction work can only be done at certain times of the year.

Delays would also compress later parts of the programme, such as integrating the signalling and control systems, which are complex and risky parts of delivering the project on time and budget.

Auditors revealed that shifting the risks on targeted construction costs has saved £1bn through contractors reducing prices in response to the reduced risks.

The report says that HS2 revisions to its commercial approach were sensible but carried risks that it must manage.

Under new arrangements, contractors will no longer be liable for cost increases above a fixed target price.

Instead, HS2 has developed an estimated cost for the works with its contractors that will leave HS2  responsible for funding increases above the estimated cost, while contractors would lose a proportion of their fee for building the railway if they fail to meet cost and schedule milestones.

The NAO said that HS2 must now develop its capability to manage the programme to avoid further cost rises.

The report said: “We welcome the increased realism on the estimated cost and schedule for the programme. However, significant risks remain.

“While the estimated cost and schedule for Phase One are now on a stronger footing, the challenge of getting Phase One into construction, and of monitoring and managing the programme as it progresses, is considerable.”

Phase Two is at a far earlier stage of development with many important decisions to be made before HS2 Ltd and the Department can improve cost and schedule estimates.

HS2 has purchased 66% of the land required to build Phase One and has spent £7.4bn in preparations to start.

The full project cost now sits between £65bn and £88bn (2015 prices), between 17% and 58% more than the available funding of £56bn agreed.

Welcoming the report, HS2 said: “As the NAO recognises, our work – along with a greater understanding of the ground conditions and build requirements – means Ministers have robust cost estimates for Phase One of the HS2 project.”

The High Speed Rail Group made up of contractors and suppliers, said:  “If the Government want to fulfil their promise of an infrastructure revolution, HS2 must be completed in full, without further dither and delay.

“The alternatives spoken of are many years behind HS2 in terms of readiness to begin work and some, like Northern Powerhouse Rail, require HS2 to be delivered to realise their full benefits.”

Robert Nisbet, director of nations and regions at the Rail Delivery Group, which represents train operators and Network Rail said: “It’s time to inject some realism into the debate about HS2.

“There are no shovel ready alternatives. To cancel it would be to worsen punctuality and overcrowding on the railway for years to come, throttling future economic growth and damaging the environment by encouraging car travel.”

Latest news

Construction starts climb-back after cliff-edge output fall

Monthly output still 39% or £5.2bn down on pre-Covid level
22 mins ago

B&K in ‘strong position’ after revenue tops £1bn

Bowmer & Kirkland boasts year-end net cash of £447m after profits hit £73m
51 mins ago

Contractors press Government for Sizewell C green light

£300m of early works could begin this year if Government seizes £18bn nuclear build opportunity
1 hour ago

Mace Dragados kicks-off £1.3bn HS2 Euston station build

£400m worth of subcontract packages to be let over two years
18 hours ago

Firms wanted to clear social housing repairs backlog

PfH seeks firms for £490m repairs and voids DPS deal
2 hours ago

Construction work accelerated on £170m of flood defence schemes

Work to start on 22 sites in the next two years
2 hours ago

Final London Super Sewer TBM arrives by barge

Final stretch in sight as TBM Selina prepared for deepest Thames Tideway drive
20 hours ago

Multiplex lands £140m Glasgow office job

Main construction work to start on 13-storey scheme
21 hours ago

DfE readies firms for ‘new deal’ schools building push

Over 30 firms in fight for places as existing £8bn framework comes up for renewal
1 day ago

Student rooms developer gears up to build again

Unite buys Edinburgh site for 300-bed scheme after Covid-work pause
1 day ago

Farringdon office scheme to restart after £140m funding deal

Confidence boost for London market as main contractor due to be appointed shortly
1 day ago

HS2 team unearths Iron Age murder victim

Large wood-henge structure uncovered during Buckinghamshire tunnel site excavations
1 day ago

Hotel and office block plan for Manchester Mayfield scheme

Work to start early next summer on 385,000 sq ft project
1 day ago

South London’s Purley tower approved

Developer Thornsett Group get thumbs up for 17-storey tower mixed-use scheme
1 day ago

Collapsed crane was erected day before tragedy

Wolffkran worker still seriously injured in hospital after 85-year-old woman killed
5 days ago

London council calls up firms for £6.8bn works deal

Tower Hamlets 10-year dynamic purchasing deal will cover new housing, schools and regeneration schemes
4 days ago

Arup to cut 350 UK jobs

Job cuts among 6,000 strong UK workforce to hit next month
5 days ago

Green light for £230m Sky Studios Elstree

BAM, Lendlease and VolkerFitzpatrick understood to be in running for main contract
5 days ago

M&E contractor Ilec goes into administration

Specialist goes down after sharp drop in turnover
4 days ago

Morgan Sindall starts up Salford resi tower project

Work on 23-storey apartment block reignites New Bailey scheme
4 days ago

Amey appoints former Murphy boss as transport chief

Peter Anderson to head-up Transport Infrastructure business
5 days ago

Woman killed in London crane collapse

Four others injured as jib crashes through roof of houses next to modular building site
6 days ago

Bellway asks subcontractors for 5% rate cut

House builder wants suppliers to drop prices from next month
5 days ago

Esh Group unveils 8% staff cut

Nearly 70 jobs to be cut from 840-strong workforce
5 days ago

Bouygues wins £250m London hospital expansion

Evelina London children’s hospital embarks on next phase of development plans
6 days ago

House builders returning to full productivity on site

Vistry reports falling supply chain prices while Persimmon says forward sales up 15%
5 days ago

Firms to get £1,000 for every worker brought off furlough

Plan for jobs promises £6,500 for work placement kickstarters and £2,000 for apprentices
6 days ago

£3bn green boost as construction leads Covid recovery

Investment for energy efficient retrofitting and stamp duty holiday to boost housing market
6 days ago

Law firm caps fees for smaller construction disputes

Fixed-fee adjudication service will not see legal bills for contractors rise above £5,000
6 days ago

Top contractors orders down 44% over three months

Wates tops June contracts league with major high-rise flats order
6 days ago

Contractor services