HS2 must start by March to avoid serious cost rises

Aaron Morby 4 years ago
Share

The Government’s spending watchdog has warned that any further delays in taking a decision on HS2 will dramatically impact on forecast construction costs.

Contractrors must start main works before the end of March to avoid further significant delays and cost rises
Contractrors must start main works before the end of March to avoid further significant delays and cost rises

An investigation into the HS2 project by the National Audit Office said the £30bn cost envelope for phase one is now more bolted down, but raised concern that costs for phase two were more uncertain.

Since April 2017, the forecast cost of phase one main civils has jumped 85% to £10.7bn.

Auditors have warned that any delays beyond March will dramatically increase costs on the project’s second phase.

If work does not begin by this date, the schedule may be delayed or compressed further because some of the construction work can only be done at certain times of the year.

Delays would also compress later parts of the programme, such as integrating the signalling and control systems, which are complex and risky parts of delivering the project on time and budget.

Auditors revealed that shifting the risks on targeted construction costs has saved £1bn through contractors reducing prices in response to the reduced risks.

The report says that HS2 revisions to its commercial approach were sensible but carried risks that it must manage.

Under new arrangements, contractors will no longer be liable for cost increases above a fixed target price.

Instead, HS2 has developed an estimated cost for the works with its contractors that will leave HS2  responsible for funding increases above the estimated cost, while contractors would lose a proportion of their fee for building the railway if they fail to meet cost and schedule milestones.

The NAO said that HS2 must now develop its capability to manage the programme to avoid further cost rises.

The report said: “We welcome the increased realism on the estimated cost and schedule for the programme. However, significant risks remain.

“While the estimated cost and schedule for Phase One are now on a stronger footing, the challenge of getting Phase One into construction, and of monitoring and managing the programme as it progresses, is considerable.”

Phase Two is at a far earlier stage of development with many important decisions to be made before HS2 Ltd and the Department can improve cost and schedule estimates.

HS2 has purchased 66% of the land required to build Phase One and has spent £7.4bn in preparations to start.

The full project cost now sits between £65bn and £88bn (2015 prices), between 17% and 58% more than the available funding of £56bn agreed.

Welcoming the report, HS2 said: “As the NAO recognises, our work – along with a greater understanding of the ground conditions and build requirements – means Ministers have robust cost estimates for Phase One of the HS2 project.”

The High Speed Rail Group made up of contractors and suppliers, said:  “If the Government want to fulfil their promise of an infrastructure revolution, HS2 must be completed in full, without further dither and delay.

“The alternatives spoken of are many years behind HS2 in terms of readiness to begin work and some, like Northern Powerhouse Rail, require HS2 to be delivered to realise their full benefits.”

Robert Nisbet, director of nations and regions at the Rail Delivery Group, which represents train operators and Network Rail said: “It’s time to inject some realism into the debate about HS2.

“There are no shovel ready alternatives. To cancel it would be to worsen punctuality and overcrowding on the railway for years to come, throttling future economic growth and damaging the environment by encouraging car travel.”

Latest news

Plan in for £3bn Lincolnshire mega data centre

3.3m sq ft Humber Tech Park will be one of Europe's largest data centres
1 day ago

Green light for Digbeth 1,300 homes scheme

Warner’s Fields scheme to start with excavation and landscaping of the River Rea
1 day ago

Flagship biodiversity net gain scheme flawed

NAO warns Government's flagship green development scheme at risk of failure
1 day ago

£210m M3 Junction 9 upgrade gains consent

VolkerFitzpatrick to start work in early 2025 on Winnall roundabout, near Winchester
1 day ago

United Living wins 14-year L&Q homes repairs deal

Trafford housing upkeep deal worth £205m
1 day ago

£400m Lewisham resi-led scheme advances

Land deal paves way for Amro Partners' 1,000-home London scheme
1 day ago

McLaren gets go-ahead for Grade II listed Leeds student scheme

Springfield House to be revamped and two new wings added
1 day ago

Piling giant to fit people alarms on all rigs

Cementation Skanska upgrades site safety systems
1 day ago

Vistry to make £800m profit after subcontractor cost cuts

House builder bullish about shareholder returns after asking suppliers for discounts
2 days ago

Shareholders approve £2.5bn Barratt and Redrow merger

Final hurdle is for the competition regulator to approve the deal.
2 days ago

Green light for £80m Leith waterfront revamp

Build-to-rent homes and student accommodation scheme to be built
2 days ago

Tilbury Douglas clears Interserve legacy jobs to return to profit

Revenue tops £500m in first year as standalone contractor
3 days ago

Land deal paves way for Manchester civil service office hub

Government buys five acres at former Central Retail Park
2 days ago

Speller Metcalfe wins Wolverhampton library upgrade

Full works are due to start in the autumn
2 days ago

Skills shortage puts big infrastructure projects at risk

Government failing as an intelligent client and now over-reliant on consultancies
3 days ago

Contractors face further insulation board price hikes

Cost of PIR insulation boards set to rise another 10%
3 days ago

Henry Boot wins £36m Rotherham Markets job

Project involves upgrading existing market and building a new library
3 days ago

Keltbray hires new head of infrastructure procurement

Lukasz Olszewski will oversee rail, energy and highways business units
3 days ago

Tunnel fit out robot to revolutionise civils work

Costain and VVB Engineering part of innovative consortium
3 days ago

Funding deal for £86m wind turbine test centre

Latest investment at National Renewable Energy Centre in Blyth
4 days ago

Plan in for Manchester ‘upside-down’ 18-storey tower

Landmark cantilevered NXQ building plan for city Northern Quarter
4 days ago

London 25km Super Sewer hooked up for commissioning

Tideway completes connection to existing Lee Tunnel sewer system
4 days ago

£200m Lincoln ring-road approved

North Hykeham Relief Road granted planning permission
4 days ago

£1bn Manchester Airport City plan rebooted as new sci-tech hub

Plan pivots from offices to science and manufacturing campus, called MIX Manchester
5 days ago

Record results at maintenance specialist Renew

Infrastructure maintenance work continues to pay off for contractor
4 days ago

Barhale lands £21m shaft scheme for Thames Water

Civils specialist bags latest upgrade deal on Thames Water Ring Main
4 days ago

Caddick names new north east director

Former Laing O'Rourke project lead joins Yorkshire contractor
4 days ago

Mount Anvil wins London Camden estate rebuild

Deverloper wins £133m Bacton Phase 2 development in Gospel Oak
5 days ago

London Met Uni seeks firm for £280m estate upgrade

A single partner contractor will deliver 10-year building upgrade plan
5 days ago

Top 30 M&E contractors set for growth – ranking

Growth in data centres and commercial refits creates optimism for year ahead
5 days ago

Contractor services