Game-changing task ahead for HS2 phase 1

Aaron Morby 2 months ago
Share

HS2 is being hailed as a game-changer for the industry that will usher in new ways of working and innovation.

Phase 1 will require 24 miles of tunnels, almost double that of Crossrail
Phase 1 will require 24 miles of tunnels, almost double that of Crossrail

The size of the programme means that the industry has been given a once in a generation opportunity to invest long term in the development of skills, capabilities and technology.

The task ahead to deliver the 140-mile phase one route is challenging with the four main delivery consortia having to deliver 85 miles of this route in tunnels and cuttings.

Nine contractors – Balfour Beatty, Costain, Eiffage, Kier, Sir Robert McAlpine, Skanska, Strabag, Vinci and VolkerFitzpatrick – will be delivering the main civils packages.

Construction will begin with the biggest engineering challenges – such as the stations and tunnels – then the main viaducts and bridges.

As such, most activity during 2020 will be focused on the city centre station sites and the major construction compounds at Old Oak Common, M25, Calvert and Streethay.

The 25 miles of tunnels on Phase One will be mainly bored with some cut and cover work. By comparison, the Crossrail project has 13 miles of tunnels.

The portal structures will be 200m long and 0.8m thick. They will contain 1m long perforations at 2m intervals at the top of the portal side walls

Bouygues, VolkerFitzpatrick and Sir Robert McAlpine (Align JV) will bore the 10-mile long Chiltern tunnel which will be the deepest at 90m on the route, while Skanska, Costain, Strabag’s London tunnels from Euston are the longest at 13 miles, albeit with a surface break at Old Oak Common station.

In total, contractors will deliver 300 rail, road and footbridges.

Around 20km of viaducts will be built. Align JV also has the task of delivering the innovative bridge at Colne Valley, which is to become the UK’s longest viaduct.

The Colne Viaduct at 3.4km it is 1km longer that the Forth Rail Bridge

The design includes innovative ideas for transparent noise-reduction barriers with vertical lines which are visible to bats and wildfowl to reduce possible impacts, while creating a slimmer side profile of the viaduct.

Balfour Beatty/ Vinci joint venture will have its work cut out on the northern section where it must deliver the complex Delta Junction outside Birmingham.

Part of the complex Delta Junction crossing the M6 and local rail lines

At 9.5km long, this junction section consists of seven bridges and viaducts spanning three rail lines, eight roads, five rivers and canals and the M6.

The route to the north of the Delta Junction towards Lichfield consists of embankments and cuttings with several viaducts crossing natural watercourses and canals.

Construction of phase one presents a vast challenge to the earthmoving sector in scale alone.

Around 50 embankments need to be built up including the longest at Grendon Underwood, which will run to 3km in length and rise to 3.5m high.

At the same time, contractors will also have to excavate 66 cuttings. The longest is the Calvert Cutting at 4.1km cut to a depth of nearly 10m.

But the award for the deepest on the project goes to Lower Thorpe Cutting, which will be dug to a maximum depth of 30.5m along its  750m length.

The new stations are set to become significant economic hubs, capable of delivering transformative growth along the whole route.

Mace and Dragados have the most challenging station project at HS2’s London Terminus.

On current plans, the firms will build 11 new 400m long platforms, a new concourse and improved connections to Euston and Euston Square Underground stations.

Design teams are also looking at the opportunity to create a new northerly entrance facing Camden Town as well as new east-west links across the whole station site

A three-way joint venture between Balfour Beatty/VINCI/Systra will deliver the Old Oak Station in north west London, which will act as the London Terminus for several years while the longer Euston Station project is completed.

Value engineering has already cut 27% of the roof steelwork from Balfour Beatty/Vinci’s Old Oak Common Station project

There will be six high-speed platforms situated underground at Old Oak Common with an integrated connection to the adjoining conventional station with platforms for the Elizabeth Line and Great Western Mainline at ground level.

The current station design also includes the potential for provision of future services to Wales and the west of England.

Birmingham’s landmark station at Curzon Street is presently out to bid for the second time as a two-stage tender to help reduce bidders risk.

Up to nine trains per hour in each direction will use the station’s seven platforms.

Expected to cost £570m to build, Curzon Street station will be the first brand new intercity terminus station built in Britain since the 19th century.

The station boasts the latest eco-friendly design and sustainable technologies including capturing rainwater and sustainable power generation.

The designs improve access to different modes of transport, with the Midland Metro running alongside and underneath the station

The designs will also incorporate the existing Old Curzon Street building and link it to the new station’s eastern concourse at New Canal Street.

Birmingham Interchange Station in Solihull, due out to tender shortly, will connect HS2 services to the city’s airport.

It will be made up of two 415m long island platforms, offering four platforms, as well as two central high speed through lines for non-stopping services.

The station will be linked to the NEC, Birmingham International Station and Birmingham Airport via a shuttle carrying up to 2,100 passengers per hour in each direction.

The 2.3km shuttle route will also have stops at Birmingham International Station, and the National Exhibition Centre.

Aerial of Birmingham Interchange Station in Solihull

On the route between London and Birmingham HS2’s tracks will sit on concrete “slab track”.

This is a hard-wearing and low-maintenance alternative to ballast, which supports plans to run up to 18 trains per hour in each direction.

Whereas ballast track requires the rails to be replaced every 20 years, slab track is designed to last for over 100 years.

The railway’s design specification is for speeds up to 225mph although daily timetabled operation will see trains run at 205mph top speed, just over 6mph faster than TGVs in France.

Latest news

Willmott Dixon furloughs 800 staff as 90% of its sites stay open

Shortage of materials hitting projects despite drive to keep sites open
6 hours ago

Taylor Wimpey to loan subbies £600 a month

£5m Pay It Forward Scheme to support 2,750 self employed workers
8 hours ago

Latest government advice on safe site working

Workers to be kept two metres apart "as much as possible"
10 hours ago

Balfour Beatty under fire for 30 Crossrail redundancies

Union slams redundancies as cruel during pandemic and calls for furloughing
13 hours ago

Gleeson gears-up for post pandemic work push

Share placing to raise £16m with £4m set aside for subcontractors in supply chain
12 hours ago

Coronavirus update for construction: Wednesday April 8

The latest advice and information from industry trade bodies
13 hours ago

Winvic tops March contracts league

Coronavirus outbreak afflicts March orders
19 hours ago

Mace starts re-opening sites

"Construction must find a way to work safely to support the UK’s economic recovery"
1 day ago

Kier to convert Swansea film studio into hospital

Andrew Scott also advances Neath sports academy conversion
1 day ago

BAM Construct to furlough 440 staff on full pay

Board and senior managers take 20% salary cut
1 day ago

Plant theft soars as construction sites close

Thieves taking advantage of coronavirus impact to steal site equipment
21 hours ago

Keep the industry updated by joining the Enquirer Directory

Membership lets construction know you are open for business now or in the future
2 years ago

Scottish sites ordered to close unless on essential list

Scottish government publishes list of what construction work can carry on: Full details
2 days ago

Private clients urged not to come after contractors

Industry urged to work together through pandemic or risk legal war
2 days ago

Vistry Partnerships bags £213m haul of affordable homes jobs

Clearance given to start pre-commencement works during covid-19 crisis
2 days ago

Competition concerns intensify over Kingspan panels deal

Acquisition of SIG's Building Solutions could leave contractors with few alternative suppliers to choose from
2 days ago

Coronavirus update for construction: Tuesday April 7

The latest advice and information from industry trade bodies
1 day ago

Model contracts to fast-track Covid-19 extra contractor payments

Cabinet office publishes contract variations for contractor payments on stalled sites
1 day ago

Builders call on CITB to cancel levy this year

Pressure mounts on skills body to do more to help industry which funds it
2 days ago

Galliard Homes suspends recladding job in London

160 workers stood down as major reclad of New Capital Quay site closed over social distancing
2 days ago

Murphy MD joins Byrne Group to head concrete frame arm

New MDs appointed at Byrne Bros and Ellmer
2 days ago

BAM to build 500-bed Harrrogate Nightingale covid-19 hospital

Harrogate Convention Centre will be transformed within 14 days
2 days ago

Construction buyers report steepest work drop in a decade

Coronavirus crisis sparks major slump in March
2 days ago

Supply chain “disconnect” threatens to halt site work

Contractors lack vital materials while suppliers sat on stocks as sites shut
3 days ago

Highways England to speed up payments and procurement

Market engagement starts for £3.6bn Operations Scheme Delivery Framework
3 days ago

Skanska seals £193m Welsh Water deal

AMP7 deal covers water treatment works, dams and pipe installation
3 days ago

Gleeson to prioritise house sales to key workers after crisis

House builder furloughs three-quarters of staff as focus turns to preparing to restart work quickly
3 days ago

Coronavirus update for construction: Monday April 6

The latest advice and information from industry trade bodies
3 days ago

Four contractors mobilised for Glasgow temporary hospital

Glasgow’s Scottish Events Campus to be transformed in two weeks
5 days ago

Ministers talking directly to construction chiefs over Covid-19

Bosses talking direct to government as trade bodies set-up Covid-19 task force
5 days ago

Contractor services