Costain Welsh road job £100m over budget and two years late

Aaron Morby 5 years ago
Share

Costain’s Heads of the Valleys A465 road project in Wales is now expected to come in more than £100m over budget and more than two years late.

Costain contract involves seven bridges and 12.5km of retaining walls
Costain contract involves seven bridges and 12.5km of retaining walls

Latest Welsh Government estimates suggest improving an 8km stretch of the road between Gilwern and Brynmawr will cost £321m and now not be completed until next year.

These big cost overruns have tipped Costain and the Welsh Government into a simmering dispute about who is liable to pay certain costs.

A report issued today by the Auditor General for Wales, commissioned as a result of the dispute, shines a light on problems on the project.

Some of the £100m increase relates to design changes requested by the Welsh Government and extra measures to address environmental impacts, but the engineering and contractual challenges experienced on the project account for most of it, concludes the report.

Costain argues that the latest estimates of Welsh Government liabilities are understated, while the authorities argue the figures represent a reasonable allowance for its liabilities at this stage.

It also emerged that Costain refused twice in 2017 to sort issues out using adjudication, with the Welsh Government finally commencing adjudications in 2018 against Costain on three separate issues without its agreement.

Since then, the pair have been involved in separate adjudications and arbitrations on different project issues with varying success.

The project was progressed using early contractor involvement with Costain first signed up in 2011. By December 2014, at the start of the detailed design and construction contract, target costs stood at £223m.

The project involves building on a steep-sided valley – the Clydach Gorge – and passes through the Brecon Beacons National Park. It forms part of a larger scheme to improve 40km of the A465 between Hirwaun and Abergavenny which is now expected to cost around £1bn overall.

The final cost and timescale for Costain’s project remain uncertain. Work was due to finish in September 2018, but full completion is now expected to run to Spring 2021.

Auditor General for Wales, Adrian Crompton said today: “This is not the first time that the Welsh Government has faced difficulties with significant cost increases and delays on road projects and it is vital that lessons are learnt for future infrastructure schemes.

“Despite some wider benefits being delivered and expectations about the eventual impact of the road improvement, those living and working locally are paying a higher than expected price for the ongoing delays and disruption during construction.”

Six sections of the A465 with a range of procurement models


In 2000, the Welsh Government anticipated that all six sections could potentially be completed by 2009, for £268m

In the previous Auditor General’s January 2011 report, the Welsh Government expected the entire A465 scheme to be completed by 2020 for £763m.

But the timetable has slipped and the Welsh Government estimates the scheme will complete in 2025 at a total cost now of around £1bn.

A Welsh Government spokesperson said: “This project is widely recognised as one of the most complex road engineering projects in the UK at the moment, presenting significant construction challenges.

“We recognise the frustration caused by the issues highlighted in the report, and will, of course, consider its findings. Lessons from the project so far have already been incorporated into subsequent projects.

“We remain confident that this ambitious and complex scheme will be completed as intended and will bring significant benefits to the region.”

Latest news

Six guilty of £2m bribery over Devon housing site deals

Corrupt building bosses and E.ON project chief and QS sentenced
3 days ago

1,650 former ISG staff launch legal claims

Redundancy Payment Service facing payout of more than £9m
4 days ago

Plans lodged for £1bn cancer research centre in Sutton

London Cancer Hub will deliver around 1m sq ft of lab and research space
3 days ago

London Met Uni seeks firm for £284m estate revamp

Contractor wanted to deliver capital works and FM
3 days ago

Delayed £2bn estate rebuild back on as Berkeley signs deal

Birmingham council development agreement paves way for 2028 Ladywood start
4 days ago

Tilbury Douglas boosts margin to 2.1% as profits double

Firm targets 3.5% margin by 2029 under new business plan
4 days ago

Subbies battle for fastest bricklayer title

Winchmore management team go back on the tools
4 days ago

Green light for revised McLaren Reading revamp

Mixed-use plans to transform Broad Street Mall site
3 days ago

Three arrested in Blu-3 and Mace bribery probe

Serious fraud office swoops over alleged £3m bribes to former Mace associates
4 days ago

Scotland’s most complex A9 dualling job heads to market

Market testing starts for £205m Pitlochry to Killiecrankie 6.4km upgrade
4 days ago

Unite signs £390m student beds JV with Manchester Met

Construction at Cambridge Halls site to start next year
4 days ago

Turkish contractor Limak to build new Luton Town stadium

Construction to start this summer on 25,000-seater venue
5 days ago

Kitchen fitter crushed to death by concrete blocks

House builder goes into liquidation before court case
4 days ago

Mears clinches £230m renewal for key Milton Keynes housing deal

Housing upkeep contractor achieves 100% renewal rate in bust rebid period
4 days ago

Murphy on board at new £32m rail station

Construction to start next year at Golborne station
5 days ago

HS2 engineers finish UK’s heaviest bridge slide early

A46 Kenilworth Bypass reopens 30 hours earlier than planned
5 days ago

Bowmer + Kirkland to build £190m Oxford science scheme

Work to start at end of next month on 180,000 sq ft Fabrica scheme
5 days ago

New BAM leisure centre pool springs a leak

Contractor investigating "technical issues" delaying new £36m green leisure centre
6 days ago

United Living lands £250m HyNet pipeline deal

Firm wins deal to design and build over 34km of pipework to collect CO2
5 days ago

Hydrogen diggers get green light to use roads

JCB hails historic decision for advance of hydrogen-fuelled plant on sites
5 days ago

Go-ahead for McAleer & Rushe Glasgow student job

£100m funding deal paves way for 591-bed student tower
5 days ago

Fly-tippers to get their vehicles crushed

Drones will be used to identify cowboy construction waste operators
5 days ago

Green light for £150m West End office revamp

Shaftesbury Avenue office retrofit retains 75% of original building
6 days ago

Morgan Sindall lands £30m Brunswick Wharf scheme in Bideford

North Devon waterside project will provide 100 flats
5 days ago

Former Keltbray managers jailed after corruption trial

Jail sentences following bribery probe on jobs including Battersea Power Station
6 days ago

Lidl pumps £500m into store and logistics expansion

Discounter plans 40 new stores this year as expansion ramps up
6 days ago

JJ Rhatigan UK profit jumps as turnover tops £150m

Irish contractor's expansion in England gathers pace
6 days ago

Driverless digger to be used on Taylor Woodrow site

Autonomous excavator to work at Manchester Airport after successful trial
6 days ago

MCS Build lands Basingstoke warehouse scheme

Construction starts this month after £26m funding deal
6 days ago

Leeds United unveil stadium revamp design

Club has still to set a timeframe for staged Elland Road upgrade
6 days ago

Contractor services