Costain Welsh road job £100m over budget and two years late

Aaron Morby 5 years ago
Share

Costain’s Heads of the Valleys A465 road project in Wales is now expected to come in more than £100m over budget and more than two years late.

Costain contract involves seven bridges and 12.5km of retaining walls
Costain contract involves seven bridges and 12.5km of retaining walls

Latest Welsh Government estimates suggest improving an 8km stretch of the road between Gilwern and Brynmawr will cost £321m and now not be completed until next year.

These big cost overruns have tipped Costain and the Welsh Government into a simmering dispute about who is liable to pay certain costs.

A report issued today by the Auditor General for Wales, commissioned as a result of the dispute, shines a light on problems on the project.

Some of the £100m increase relates to design changes requested by the Welsh Government and extra measures to address environmental impacts, but the engineering and contractual challenges experienced on the project account for most of it, concludes the report.

Costain argues that the latest estimates of Welsh Government liabilities are understated, while the authorities argue the figures represent a reasonable allowance for its liabilities at this stage.

It also emerged that Costain refused twice in 2017 to sort issues out using adjudication, with the Welsh Government finally commencing adjudications in 2018 against Costain on three separate issues without its agreement.

Since then, the pair have been involved in separate adjudications and arbitrations on different project issues with varying success.

The project was progressed using early contractor involvement with Costain first signed up in 2011. By December 2014, at the start of the detailed design and construction contract, target costs stood at £223m.

The project involves building on a steep-sided valley – the Clydach Gorge – and passes through the Brecon Beacons National Park. It forms part of a larger scheme to improve 40km of the A465 between Hirwaun and Abergavenny which is now expected to cost around £1bn overall.

The final cost and timescale for Costain’s project remain uncertain. Work was due to finish in September 2018, but full completion is now expected to run to Spring 2021.

Auditor General for Wales, Adrian Crompton said today: “This is not the first time that the Welsh Government has faced difficulties with significant cost increases and delays on road projects and it is vital that lessons are learnt for future infrastructure schemes.

“Despite some wider benefits being delivered and expectations about the eventual impact of the road improvement, those living and working locally are paying a higher than expected price for the ongoing delays and disruption during construction.”

Six sections of the A465 with a range of procurement models


In 2000, the Welsh Government anticipated that all six sections could potentially be completed by 2009, for £268m

In the previous Auditor General’s January 2011 report, the Welsh Government expected the entire A465 scheme to be completed by 2020 for £763m.

But the timetable has slipped and the Welsh Government estimates the scheme will complete in 2025 at a total cost now of around £1bn.

A Welsh Government spokesperson said: “This project is widely recognised as one of the most complex road engineering projects in the UK at the moment, presenting significant construction challenges.

“We recognise the frustration caused by the issues highlighted in the report, and will, of course, consider its findings. Lessons from the project so far have already been incorporated into subsequent projects.

“We remain confident that this ambitious and complex scheme will be completed as intended and will bring significant benefits to the region.”

Latest news

Construction to start in May on £1bn port expansion

Work at London Gateway site will last four years
15 hours ago

Green light for London Euston Tower rebuild

British Land says nearly a third of original tower will be retained
21 hours ago

Contractors struggling to keep-up with demand for data centres

More than half of clients fear supply chain will struggle
22 hours ago

Robert De Niro’s Nobu backs Manchester super tower

76-storey skyscraper will be tallest outside of London
22 hours ago

PAC warns post-Grenfell policies threaten new homes goal

Watchdog MPs warn new build rates are being hit by diversion of funds to safety remediation
22 hours ago

400 schools and hospitals to get rooftop solar panels

£180m investment is the first major project for Great British Energy
22 hours ago

Legendre UK to convert Diageo HQ into hotel

Work to start this year transforming former home of drinks giant
23 hours ago

Glencar wins phase 2 of Harwell tech scheme

Tech Foundry West will create 70,000 sq ft of lab and manufacturing space
22 hours ago

Beard breaks company record with latest results

Family-owned firm posts best results for 133 years
2 days ago

United Living buys street lighting contractor

North West's Jones acquisition also strengthens power distribution offer
2 days ago

Deal to start £1.1bn British Library extension

Japanese developer takes control with aim to start construction next year
3 days ago

Fraud warning over bogus site supplies orders

Site temporary protection specialist sounds alarm after foiling scammers
2 days ago

Plan for world’s tallest energy-positive tower in Birmingham

£60m solar clad 29-storey tower will produce more energy than it consumes
2 days ago

Costain to lead on nuclear fuel site upgrade

Programme delivery partner role for upgrade to infrastructure at Capenhurst site
2 days ago

Willmott Dixon wins £32m Doncaster digital tech hub

Construction to start next month on Gateway One scheme
2 days ago

Pickstock to build Stratford resi tower

Construction set to start next year by modular builder owner
2 days ago

ISG accountants face investigation over audit

Watchdog launches probe into final accounts for collapsed contractor
3 days ago

Developer given suspended jail sentence for fire safety breaches

Director wrongly allowed residents to move into block before getting fire safety sign-off
3 days ago

Muse submits 1,600-home regen plan for Solihull town centre

Work to start early next year on Mell Square shopping centre redevelopment
3 days ago

Plans to be submitted for £140m Cardiff Central revamp

Enabling works to start this year to pave the way for construction
3 days ago

Developer fined after site hit with nine safety notices

Company "showed a total disregard to keeping its workers safe"
3 days ago

Ringway retains Hertfordshire highways after 12 years

Contract worth £55m a year and could be extended to 21 years
4 days ago

Driver pulls knife on Balfour Beatty road worker

East Sussex incident highlights dangers faced by highways staff
4 days ago

Wates starts £300m Suffolk prison expansion

Firm to build three house blocks at HMP Highpoint
4 days ago

Southern Housing seeks 10 firms for £1.7bn upgrade deal

South east fire safety and housing upgrade framework out to bid
4 days ago

Pothole patch-up policy fails as roads repair backlog hits £17bn

Industry calls for urgent mindset change on funding and maintaining local roads
4 days ago

Green light for 2,100 homes at old East London gasworks

St William secures S106 deal for world’s largest Victorian gasworks regen scheme
5 days ago

Lifting regs review bagged up with ‘bat and newt’ red tape purge

Government calls in regulators and tells Ofwat to speed up 30 major water projects
5 days ago

House builders call for rethink on Building Safety Levy

Developers call for spotlight to be turned on product manufacturers
5 days ago

Costain raids Balfour Beatty for new head of rail

Alistair Geddes joins as rail director
5 days ago

Contractor services