Costain Welsh road job £100m over budget and two years late

Aaron Morby 4 years ago
Share

Costain’s Heads of the Valleys A465 road project in Wales is now expected to come in more than £100m over budget and more than two years late.

Costain contract involves seven bridges and 12.5km of retaining walls
Costain contract involves seven bridges and 12.5km of retaining walls

Latest Welsh Government estimates suggest improving an 8km stretch of the road between Gilwern and Brynmawr will cost £321m and now not be completed until next year.

These big cost overruns have tipped Costain and the Welsh Government into a simmering dispute about who is liable to pay certain costs.

A report issued today by the Auditor General for Wales, commissioned as a result of the dispute, shines a light on problems on the project.

Some of the £100m increase relates to design changes requested by the Welsh Government and extra measures to address environmental impacts, but the engineering and contractual challenges experienced on the project account for most of it, concludes the report.

Costain argues that the latest estimates of Welsh Government liabilities are understated, while the authorities argue the figures represent a reasonable allowance for its liabilities at this stage.

It also emerged that Costain refused twice in 2017 to sort issues out using adjudication, with the Welsh Government finally commencing adjudications in 2018 against Costain on three separate issues without its agreement.

Since then, the pair have been involved in separate adjudications and arbitrations on different project issues with varying success.

The project was progressed using early contractor involvement with Costain first signed up in 2011. By December 2014, at the start of the detailed design and construction contract, target costs stood at £223m.

The project involves building on a steep-sided valley – the Clydach Gorge – and passes through the Brecon Beacons National Park. It forms part of a larger scheme to improve 40km of the A465 between Hirwaun and Abergavenny which is now expected to cost around £1bn overall.

The final cost and timescale for Costain’s project remain uncertain. Work was due to finish in September 2018, but full completion is now expected to run to Spring 2021.

Auditor General for Wales, Adrian Crompton said today: “This is not the first time that the Welsh Government has faced difficulties with significant cost increases and delays on road projects and it is vital that lessons are learnt for future infrastructure schemes.

“Despite some wider benefits being delivered and expectations about the eventual impact of the road improvement, those living and working locally are paying a higher than expected price for the ongoing delays and disruption during construction.”

Six sections of the A465 with a range of procurement models


In 2000, the Welsh Government anticipated that all six sections could potentially be completed by 2009, for £268m

In the previous Auditor General’s January 2011 report, the Welsh Government expected the entire A465 scheme to be completed by 2020 for £763m.

But the timetable has slipped and the Welsh Government estimates the scheme will complete in 2025 at a total cost now of around £1bn.

A Welsh Government spokesperson said: “This project is widely recognised as one of the most complex road engineering projects in the UK at the moment, presenting significant construction challenges.

“We recognise the frustration caused by the issues highlighted in the report, and will, of course, consider its findings. Lessons from the project so far have already been incorporated into subsequent projects.

“We remain confident that this ambitious and complex scheme will be completed as intended and will bring significant benefits to the region.”

Latest news

Police ban mobile cranes from roads over Easter

Plant hire bosses livid as forces across the country extend abnormal load embargoes
21 hours ago

Director jailed for exposing workers to asbestos

Ten tonnes of asbestos insulating board stripped out by unqualified workers
1 day ago

Site labour rates start rising again

Industry's biggest payroll firm says "it feels like things could be turning round"
1 day ago

Council finds extra £33m for Buckinghamshire link road

South East Aylesbury Link Road costs soar by nearly 30% to £147m
1 day ago

Quartet win £490m North West & Central railway works deal

Skanska, Kier, Octavius Infrastructure and Story Contracting bag major projects deal
1 day ago

Unite Students plans first major mixed-use scheme

Developer's first mixed BTR and PBSA project to be built in Edinburgh
2 days ago

Galliford Try names new finance director

Rentokil's Kris Hampson joins contractor to replace Andrew Duxbury
1 day ago

Council boss hits out at bat threat to £274m road job

Natural England could scupper scheme due to be built by Ferrovial
1 day ago

Hydrogen-fuelled diggers to be allowed onto highways

Government to raise barrier to widespread use of hydrogen fuelled plant in construction
2 days ago

Plans in for £118m Government hub in Darlington

Work pencilled to start later this year on new home for 1,450 civil servants
2 days ago

New contractor highlights Henry Construction jobs on website

New firm lists jobs by failed contractor to show its experience
2 days ago

Contractors line up for £2.6bn Anglian Water AMP8 deal

Eight big names land places on pioneering @one Alliance
3 days ago

McAleer & Rushe bags first major later living project

Work to start this month on 167-flat Royal Tunbridge Wells project
2 days ago

Kier starts first all-electric prison houseblock job in Kent

Next-generation fully electric T60 prison houseblock to be built at HMP Elmley
2 days ago

Keepmoat sees better times ahead in housing market

Profits dip in 2023 despite construction of record number of new homes
2 days ago

Vistry signs partnership deals for 1,900 mixed tenure homes

West Sussex former airfield and Newmarket sites to break ground
3 days ago

Turnover at Wates tops £2bn for first time

Construction division exceeds £1bn turnover as average contract value hits record high of £48.3m
3 days ago

L&G looks to sell Cala Homes in exit from house building

Insurance giant reported to be preparing to offload 3,000 homes-a-year developer
4 days ago

Multiplex profit almost trebles as margin hits 5.5%

Revenue jumps 20% to £675m as big London scheme complete
3 days ago

TopHat puts plans to open huge Corby factory on hold

Advanced manufacturing facility was due to employ 1,000 people
3 days ago

Laing O’Rourke lands Calderdale hospital job

Enabling works to start by the end of this year at West Yorkshire site
3 days ago

Go-ahead for £475m Sunderland film and TV studios

Work to start this year on first phase Corwn Work studios
3 days ago

Willmott Dixon set for £20m Stockport Community Hub

Planning decision expected in June on Marple leisure and health clinic project
3 days ago

Police hunt for blundering dumper truck thief

Raider drove into a fence before getting stuck on a bank
3 days ago

Beattie Passive files administration notice

Passivhaus pioneer has been in business for more than ten years
4 days ago

McAlpine set for £50m space and tech centre

Northumbria Uni sign pre-con deal for new satellite research hub
4 days ago

VolkerFitzpatrick seals £34m Kent road viaduct

Work to start next year on Sturry Link Road near Canterbury
4 days ago

Eight win £600m Scottish civil engineering framework

Balfour, Farrans, Graham and Morgan Sindall win major works lot
4 days ago

Site engineer crushed to death by excavator

22-year-old victim died just months after graduating from university
6 days ago

NG Bailey fined £135,000 after hospital site death

Worker died after striking overhead beam while navigating a mobile elevating work platform
7 days ago

Contractor services