Costain Welsh road job £100m over budget and two years late

Aaron Morby 4 years ago
Share

Costain’s Heads of the Valleys A465 road project in Wales is now expected to come in more than £100m over budget and more than two years late.

Costain contract involves seven bridges and 12.5km of retaining walls
Costain contract involves seven bridges and 12.5km of retaining walls

Latest Welsh Government estimates suggest improving an 8km stretch of the road between Gilwern and Brynmawr will cost £321m and now not be completed until next year.

These big cost overruns have tipped Costain and the Welsh Government into a simmering dispute about who is liable to pay certain costs.

A report issued today by the Auditor General for Wales, commissioned as a result of the dispute, shines a light on problems on the project.

Some of the £100m increase relates to design changes requested by the Welsh Government and extra measures to address environmental impacts, but the engineering and contractual challenges experienced on the project account for most of it, concludes the report.

Costain argues that the latest estimates of Welsh Government liabilities are understated, while the authorities argue the figures represent a reasonable allowance for its liabilities at this stage.

It also emerged that Costain refused twice in 2017 to sort issues out using adjudication, with the Welsh Government finally commencing adjudications in 2018 against Costain on three separate issues without its agreement.

Since then, the pair have been involved in separate adjudications and arbitrations on different project issues with varying success.

The project was progressed using early contractor involvement with Costain first signed up in 2011. By December 2014, at the start of the detailed design and construction contract, target costs stood at £223m.

The project involves building on a steep-sided valley – the Clydach Gorge – and passes through the Brecon Beacons National Park. It forms part of a larger scheme to improve 40km of the A465 between Hirwaun and Abergavenny which is now expected to cost around £1bn overall.

The final cost and timescale for Costain’s project remain uncertain. Work was due to finish in September 2018, but full completion is now expected to run to Spring 2021.

Auditor General for Wales, Adrian Crompton said today: “This is not the first time that the Welsh Government has faced difficulties with significant cost increases and delays on road projects and it is vital that lessons are learnt for future infrastructure schemes.

“Despite some wider benefits being delivered and expectations about the eventual impact of the road improvement, those living and working locally are paying a higher than expected price for the ongoing delays and disruption during construction.”

Six sections of the A465 with a range of procurement models


In 2000, the Welsh Government anticipated that all six sections could potentially be completed by 2009, for £268m

In the previous Auditor General’s January 2011 report, the Welsh Government expected the entire A465 scheme to be completed by 2020 for £763m.

But the timetable has slipped and the Welsh Government estimates the scheme will complete in 2025 at a total cost now of around £1bn.

A Welsh Government spokesperson said: “This project is widely recognised as one of the most complex road engineering projects in the UK at the moment, presenting significant construction challenges.

“We recognise the frustration caused by the issues highlighted in the report, and will, of course, consider its findings. Lessons from the project so far have already been incorporated into subsequent projects.

“We remain confident that this ambitious and complex scheme will be completed as intended and will bring significant benefits to the region.”

Latest news

First sign of price falls for construction products

Supply returns to pre-covid levels as demand drops
22 hours ago

Three giant lab buildings approved at £700m Oxford R&D district

Phase 2 Oxford North office and lab buildings to deliver 460,000 sq ft of space
2 days ago

PM fails to quash speculation about plan to axe HS2 phase 2

Sunak ducks future of HS2 question at big net zero Government briefing
22 hours ago

Green light for giant North Wales offshore wind farm

Awel y Môr wind farm is the biggest renewable investment in Wales for a decade
22 hours ago

T&T breaks £1bn revenue mark for first time

Global consultant enjoys strong growth across all seven geographical regions
22 hours ago

Subcontractors and suppliers wanted across Scotland

Constructionline Meet the Buyer event next week at Hampden Park: Register now
22 hours ago

Springfield switches strategy as private housing slumps

Scottish house builder turns back to affordable homes market
2 days ago

Sunak details zero carbon targets climbdown

Ban on gas boilers delayed five years; 50% rise in scrappage scheme
2 days ago

RG Group to build tallest student block in the world

Contractor confirmed on 45-storey tower in Leeds
2 days ago

Galliford Try forecasts profit to double next year

Contractor delivers strong results this year and raises expectation for 2024
2 days ago

Strabag hires 15 senior Buckingham Group staff

Austrian civils giant to set up UK building business with pool of staff
3 days ago

Contractors raise pay offer to avert engineering construction strike

Blue book agreement employers up final offer to 10%
2 days ago

Former Mid Group chief joins Tilbury Douglas

Steven Hearn gets new role as regional director of the South East division
2 days ago

Crumbly concrete found at extra 27 schools

A total of 174 schools now found to contain RAAC concrete
3 days ago

Henry Boot Construction struggling to find work

Contracting arm looking to fill order book
3 days ago

More schools found to have crumbly concrete

Surveyors find another 27 schools containing Raac
3 days ago

Buckingham Plant Hire still trading as normal

Separate plant business "not affected" by collapse of contractor
3 days ago

NG Bailey makes £25m loss after Britishvolt shock

Gigafactory loss and problem contracts blow hole in books
4 days ago

Steelwork specialist Billington delivers record first-half

Overseas recruitment push boosts headcount by 10% to drive growth
3 days ago

Vinci wins major St Helens town centre revamp

£90m first phase includes new market hall, 120-bed hotel and over 60 flats
3 days ago

Mace deputy chairman to step down from board

Mace veteran Mark Holmes will leave at the end of the year
3 days ago

CHIC extends bid deadline on £3.2bn new build framework

Closing date for 8-year framework set for 20 October
4 days ago

Work to start this year on Manchester £250m spa resort

Developer Therme gets green light for re-engineered 28-acre Trafford complex
4 days ago

Costain bags £80m water order for upgrades at 16 sites

Severn Trent contracts include work to improve wastewater quality and protect wildlife
4 days ago

Barhale JV sign-off for £18m Dewsbury sewage works upgrade

Project forms part of Yorkshire Water’s £500m investment in Phosphorous removal
4 days ago

Murphy seals main build on £124m Essex station

Contractor lands main contract after successful start on enabling works package
7 days ago

GMI lands latest £42m phase of lab cluster

Citylabs life sciences complex in Manchester continues to grow
4 days ago

Director ban for asbestos dumper

Twenty tonnes of construction waste illegally dumped on farmland
4 days ago

HS2 leg to Manchester could be axed

Rishi Sunak and Jeremy Hunt are reportedly in talks to axe Northern leg
7 days ago

FM Conway revenue tops £500m

Highways contractor reduces net debt by £10m amid strong operating cash flow
7 days ago

Contractor services