Costain Welsh road job £100m over budget and two years late

Aaron Morby 4 years ago
Share

Costain’s Heads of the Valleys A465 road project in Wales is now expected to come in more than £100m over budget and more than two years late.

Costain contract involves seven bridges and 12.5km of retaining walls
Costain contract involves seven bridges and 12.5km of retaining walls

Latest Welsh Government estimates suggest improving an 8km stretch of the road between Gilwern and Brynmawr will cost £321m and now not be completed until next year.

These big cost overruns have tipped Costain and the Welsh Government into a simmering dispute about who is liable to pay certain costs.

A report issued today by the Auditor General for Wales, commissioned as a result of the dispute, shines a light on problems on the project.

Some of the £100m increase relates to design changes requested by the Welsh Government and extra measures to address environmental impacts, but the engineering and contractual challenges experienced on the project account for most of it, concludes the report.

Costain argues that the latest estimates of Welsh Government liabilities are understated, while the authorities argue the figures represent a reasonable allowance for its liabilities at this stage.

It also emerged that Costain refused twice in 2017 to sort issues out using adjudication, with the Welsh Government finally commencing adjudications in 2018 against Costain on three separate issues without its agreement.

Since then, the pair have been involved in separate adjudications and arbitrations on different project issues with varying success.

The project was progressed using early contractor involvement with Costain first signed up in 2011. By December 2014, at the start of the detailed design and construction contract, target costs stood at £223m.

The project involves building on a steep-sided valley – the Clydach Gorge – and passes through the Brecon Beacons National Park. It forms part of a larger scheme to improve 40km of the A465 between Hirwaun and Abergavenny which is now expected to cost around £1bn overall.

The final cost and timescale for Costain’s project remain uncertain. Work was due to finish in September 2018, but full completion is now expected to run to Spring 2021.

Auditor General for Wales, Adrian Crompton said today: “This is not the first time that the Welsh Government has faced difficulties with significant cost increases and delays on road projects and it is vital that lessons are learnt for future infrastructure schemes.

“Despite some wider benefits being delivered and expectations about the eventual impact of the road improvement, those living and working locally are paying a higher than expected price for the ongoing delays and disruption during construction.”

Six sections of the A465 with a range of procurement models


In 2000, the Welsh Government anticipated that all six sections could potentially be completed by 2009, for £268m

In the previous Auditor General’s January 2011 report, the Welsh Government expected the entire A465 scheme to be completed by 2020 for £763m.

But the timetable has slipped and the Welsh Government estimates the scheme will complete in 2025 at a total cost now of around £1bn.

A Welsh Government spokesperson said: “This project is widely recognised as one of the most complex road engineering projects in the UK at the moment, presenting significant construction challenges.

“We recognise the frustration caused by the issues highlighted in the report, and will, of course, consider its findings. Lessons from the project so far have already been incorporated into subsequent projects.

“We remain confident that this ambitious and complex scheme will be completed as intended and will bring significant benefits to the region.”

Latest news

Mace confirmed on £100m London office retrofit

Work underway on Helical's 100 New Bridge Street job near Ludgate Circus
3 hours ago

Wylfa chosen for next big nuclear power station build

Government names Anglesey site for a large-scale gigawatt nuclear power plant.
6 hours ago

Bowmer & Kirkland trading profit halves

Contractor buys HVAC specialist Adcock despite challenging market
6 hours ago

Piling specialist Van Elle plans further job cuts

Piling specialist plans further cost savings in face of lower demand
7 hours ago

Civils contractor A Catlow files administration notice

High voltage cable specialist lodges court notice
6 hours ago

Green light for ARC Oxford lab campus

Work to start later this year on £40m Ascent building job
7 hours ago

Stonehenge tunnel hit by another legal delay

Court upholds latest appeal against £1.7bn scheme by campaigners
24 hours ago

Plans go in for huge Olympic Park construction hub

Bow Goods Yard could deliver 3.5m tonnes of materials a year to sites across London
1 day ago

40% affordable homes target for Labour’s new towns

Labour pledges to select new town sites by end of first year
1 day ago

Plan for £100m Liverpool Baltic station

Construction work could begin next year
1 day ago

Surgo Construction went down owing £4.5m

Biggest creditor is Bellway Homes after dispute on housing job
1 day ago

Vistry seals £157m West London housing deal

Around 575 homes to be built at Merrick Place scheme in Ealing
1 day ago

Streamlined Watkin Jones returns to profit in first half

Multi-room specialist sees secured work pipeline hit £1.4bn
1 day ago

Bellway hires ex-brickie as group construction chief

James Griffin to oversee move to the Future Homes Standard and timber frame.
1 day ago

Persimmon under fire for delays to £10m relief road

West Suffolk Council serves Breach of Condition Notices after timetable slips again
1 day ago

BAM wins £33m Kent secondary school job

Replacement Swanley academy to be built at live school site
1 day ago

Aluminium cladding specialist collapses

Melton Mowbray-based firm worked for several main contractors
2 days ago

Brickwork contractor Lee Marley returns to profit

Affordable and rental homes demand lifts brickwork contractor
2 days ago

Housing contractor Durkan suffers second year of losses

More fire safety provisions tip firm into £3.9m loss
2 days ago

Farrans makes breakthrough on tricky tunnel job

Tunnel under Tees latest part of new £155m water pipeline job
2 days ago

Heidelberg buys aggregates and earthworks specialist B&A

Latest deal follows acquisition of Mick George
2 days ago

Flagship biodiversity net gain scheme flawed

NAO warns Government's flagship green development scheme at risk of failure
5 days ago

Plan in for £3bn Lincolnshire mega data centre

3.3m sq ft Humber Tech Park will be one of Europe's largest data centres
5 days ago

Green light for Digbeth 1,300 homes scheme

Warner’s Fields scheme to start with excavation and landscaping of the River Rea
5 days ago

£210m M3 Junction 9 upgrade gains consent

VolkerFitzpatrick to start work in early 2025 on Winnall roundabout, near Winchester
5 days ago

United Living wins 14-year L&Q homes repairs deal

Trafford housing upkeep deal worth £205m
5 days ago

£400m Lewisham resi-led scheme advances

Land deal paves way for Amro Partners' 1,000-home London scheme
5 days ago

McLaren gets go-ahead for Grade II listed Leeds student scheme

Springfield House to be revamped and two new wings added
5 days ago

Piling giant to fit people alarms on all rigs

Cementation Skanska upgrades site safety systems
5 days ago

Vistry to make £800m profit after subcontractor cost cuts

House builder bullish about shareholder returns after asking suppliers for discounts
6 days ago

Contractor services