London super sewer passes halfway point

Aaron Morby 6 years ago
Share

Tunnellers boring the London super sewer have just passed the halfway mark on the vast £3.8bn project.

The main tunnel at Battersea
The main tunnel at Battersea

The giant machines digging the main Thames Tideway tunnel have now bored over 13km of the 25km total length.

The tunnel now stretches as far west as Fulham and, eastwards, it has reached Blackfriars in the City of London – passing under 13 bridges including Albert Bridge, Westminster Bridge and Waterloo Bridge.

TBM Rachel digging the west section has passed the 3km mark on her 7km journey from Fulham to Acton.

So far, the tunnels have been constructed using four tunnel boring machines.

Two more tunnelling machines are due to start working in east London this year, creating the eastern section of the main tunnel from Bermondsey to Newham, as well as a slightly smaller 4km connection tunnel in Greenwich.

The project is looking to develop innovative ways of works and has introduced pre-shift work-outs to help prevent musculoskeletal disorders at Thames Tideway.

Tunnel team’s ‘stretch and flex’ sessions at the beginning of shifts, enabling engineers, site managers and drivers alike to prepare for the day’s tasks while getting a little bit of exercise in the process.

Andy Mitchell, Tideway CEO, said: “After more than three years of exceptional work by our teams across London, we’ve reached the halfway mark on the super sewer.

“There’s still a way to go but reaching this point on schedule is testament to the success of the team, who have achieved a huge number of engineering feats – including tunnelling under the river through a variety of ground conditions, building new pieces of land in the Thames to work in and digging giant shafts up to 50m deep below London.

Secondary lining for a 60m-deep shaft built in Bermondsey is now complete using 4,000 cu m of slip-formed concrete

“Once complete, not only will we have a cleaner river but there will be seven new areas of public space created along the Thames, transforming the embankment and creating new areas for Londoners and visitors to reconnect with the river.”

As well as the main tunnel, a 1km connection tunnel is also currently under construction in Wandsworth.

Three million tonnes of excavated material have been transported by river, avoiding 340,000 HGV journeys

Tunnelling is due to complete in 2022, allowing up to two years of commissioning for a March 2024 opening.

Latest news

Chief executive Mark Lawrence leaves TClarke

CEO leaves with immediate effect after 40 years at the busines
11 minutes ago

Turnover dips as Laing O’Rourke focuses on bottom line

Pre-tax profits nearly double as Europe Hub surges ahead while Australia stalls
5 hours ago

Cladding retrofit drive faces red alert over delivery delays

NISTA warns acceleration plan looks increasingly difficult as regulator delays, rising costs and social housing pressures mount.
8 hours ago

Galliford Try and Balfour Beatty join forces for £1.9bn A9 race

Firms form Scottish joint venture to target final five dualling packages under new framework set-up
8 hours ago

Diversification paying dividends for brick giant

Specialist contracting division performing well at BRCK Group
8 hours ago

Panattoni gets green light for Southampton logistics site

223,000 sq ft of space to be built at latest scheme
8 hours ago

Bouygues high-rise key worker housing pilot gains consent

Construction due to start next year on landmark London living rent model
8 hours ago

SCAPE starts tender race for £1.2bn regional deal

Up to 12 winners will be chosen for latest framework
1 day ago

JRL back in the black with record order book

Chairman John Reddington says £2bn record pipeline underpins recovery
1 day ago

Worker killed in fall at Birmingham hospital job

BSN Group Construction assisting police and HSE investigation into fatal accident
1 day ago

Stalled £1bn Harlow biosecurity mega project revived

Government launches market engagement after four-year hiatus
1 day ago

HG Construction lands brace of student schemes

Contract wins from Fusion Group in Cardiff and Loughborough
1 day ago

Funding deal sparks £1bn Golden Valley cyber hub build

Bowmer & Kirkland starts £95m first phase after Henry Boot secures finance
1 day ago

Linear Living gets green light for Manchester resi tower

24-storey scheme to be built by Linear Design and Construct
4 days ago

Clegg Construction lands £19m Leicester estate revamp

Work to start by end of year at Stocking Farm estate
1 day ago

Worker dies in fall on Mayfair site

Air ambulance arrives but worker pronounced dead at scene yesterday
4 days ago

Seddon defies sluggish market with profit lift

Operating margin restored to 2.2% despite public sector scheme delays
4 days ago

Green light for ‘poo powered’ eco homes scheme

Yorkshire Water seeks developer for pioneering wastewater powered community
4 days ago

Speller Metcalfe posts record £5m profit as cash pile hits £32m

Midlands contractor lifts profits despite flat turnover with nearly all next year's workload booked
4 days ago

Apprentice joiner crushed to death by falling boards

Company and director in court after renovation site tragedy
4 days ago

Four firms land £300m Scottish electricity network deal

Quartet to upgrade network across north of Scotland
5 days ago

Industry unites to warn new PM against more infrastructure cuts

Twenty eight leaders warn against damaging return to stop-start funding
5 days ago

Funding deal to kick-start Middlewood Locks tower phase

Scarborough JV targets early 2027 start on 909-home phase 4
5 days ago

Hampshire council seeks D&B firm for £100m housing job

Phase two set to start at country's largest council led housing scheme
5 days ago

Margins hit 4.8% as profits triple at Esh Group

Record year for North of England contractor
5 days ago

Labourer dies after scissor lift fall

Court hears falling wall panels knocked worker from machine during demolition work
5 days ago

MoD to split £6.6bn military homes maintenance mega deal

Procurement rethink aims to widen competition and boost SME opportunities
5 days ago

Vistry warns of first-half loss as daily net debt nears £800m

Finance chief to step down in October after new CEO completes strategic plan
6 days ago

Battersea job lifts Sisk to top of contracts league

Infrastructure work buoys top contractor order books in June
6 days ago

Council bosses blast ‘shoddy’ work by failed contractor

£3m of problems found on housing job hit by collapse of Westridge Construction
1 week ago