London super sewer passes halfway point

Aaron Morby 4 years ago
Share

Tunnellers boring the London super sewer have just passed the halfway mark on the vast £3.8bn project.

The main tunnel at Battersea
The main tunnel at Battersea

The giant machines digging the main Thames Tideway tunnel have now bored over 13km of the 25km total length.

The tunnel now stretches as far west as Fulham and, eastwards, it has reached Blackfriars in the City of London – passing under 13 bridges including Albert Bridge, Westminster Bridge and Waterloo Bridge.

TBM Rachel digging the west section has passed the 3km mark on her 7km journey from Fulham to Acton.

So far, the tunnels have been constructed using four tunnel boring machines.

Two more tunnelling machines are due to start working in east London this year, creating the eastern section of the main tunnel from Bermondsey to Newham, as well as a slightly smaller 4km connection tunnel in Greenwich.

The project is looking to develop innovative ways of works and has introduced pre-shift work-outs to help prevent musculoskeletal disorders at Thames Tideway.

Tunnel team’s ‘stretch and flex’ sessions at the beginning of shifts, enabling engineers, site managers and drivers alike to prepare for the day’s tasks while getting a little bit of exercise in the process.

Andy Mitchell, Tideway CEO, said: “After more than three years of exceptional work by our teams across London, we’ve reached the halfway mark on the super sewer.

“There’s still a way to go but reaching this point on schedule is testament to the success of the team, who have achieved a huge number of engineering feats – including tunnelling under the river through a variety of ground conditions, building new pieces of land in the Thames to work in and digging giant shafts up to 50m deep below London.

Secondary lining for a 60m-deep shaft built in Bermondsey is now complete using 4,000 cu m of slip-formed concrete

“Once complete, not only will we have a cleaner river but there will be seven new areas of public space created along the Thames, transforming the embankment and creating new areas for Londoners and visitors to reconnect with the river.”

As well as the main tunnel, a 1km connection tunnel is also currently under construction in Wandsworth.

Three million tonnes of excavated material have been transported by river, avoiding 340,000 HGV journeys

Tunnelling is due to complete in 2022, allowing up to two years of commissioning for a March 2024 opening.

Latest news

Morgan Sindall to build former Willmott Dixon leisure job

New contractor appointed on
15 hours ago

Graham consortium wins £400m Manchester job

Equitix consortium to now work up DBFO plans for University of Manchester’s Fallowfield Campus
11 hours ago

Keltbray looking to sell infrastructure business

£378m turnover rail, energy and highways business up for sale
22 hours ago

Innovative viaduct building method used for first time in UK

HS2 contractors will build nine viaducts in Delta Junction using special cantilevered process
22 hours ago

Unite buys London site to fast-track 444-bed student scheme

£800m to be spent on London development pipeline in next five years
22 hours ago

CITB awards £2.5m of contracts to management consultant

Three outsourced deals in the last year for "project leadership and management consultancy"
22 hours ago

Village centre approved for 6,000-home new town plan

Hampshire's Welborne Garden Village plan has been in the pipeline for two decades.
21 hours ago

£3m fine after cherry picker demolition death

Court rules after tragedy during decommissioning of gas rig
22 hours ago

BAM plans wave of job cuts at UK Construction arm

Co-op Live arena plunges Bam Construction to £19.5m first-half loss
2 days ago

Robot tunnel builder goes into administration

Hypertunnel was hoping to revolutionise how underground structures are built
2 days ago

Wates to build £86m Guildford Council housing scheme

40% of the 248 homes will become council homes under partnership deal
2 days ago

“Scrap CITB” say three quarters of construction firms

Payroll giant Hudson Contract calls for CITB to be absorbed into new Skills England training body
2 days ago

£100m Prestwich Village revival approved

Vinci and Willmott Dixon in chase for Muse-led regeneration scheme
2 days ago

Carbon negative asphalt aggregate trialled on M11

Skanska and Tarmac test CO2 absorbing aggregate material on stretch of Essex motorway
2 days ago

Father and son sentenced over covid construction loan fraud

Bristol builders given suspended jail sentences over bogus Bounce Back Loans
2 days ago

Beck Interiors files administration notice

Supply chain has suffered delayed payments from £139m-turnover luxury fit out specialist
3 days ago

Green light for York Central civil service office hub

£60m office project accelerates York Central goods yard redevelopment
3 days ago

Blenheim House Construction enters administration

Administrators looking at options on present projects
3 days ago

Profits rise at Esh Group with more to come

Contractor confident about year ahead as market conditions move in right direction
3 days ago

Piling specialist Van Elle sees housing orders rise 30%

Mark Cutler says firm on course to deliver 10% annual sales growth
3 days ago

HS2 to spend £100m shutting sites where work never started

Remediation of sites no longer needed for cancelled Phase 2 will take three years
4 days ago

Willmott Dixon wins £61m deal for new Army dog unit

Contractor to revamp Kendrew Barracks in Rutland
3 days ago

Stockport advances 4,000-home Town Centre East plan

Council seeks consultants to steer plan for 280-acre area in the city
3 days ago

ISG sale imminent as buyers set-up UK holding company

South African nutrition entrepreneur and Australian partner primed to take over
4 days ago

CR Construction wins £210m Manchester towers

Construction to start next year on four blocks ranging from nine to 34-storeys
4 days ago

Southern Housing to rationalise supply chain following merger

Firms put on alert for £1.7bn construction framework renewal
4 days ago

Decision delayed on 52-storey Isle of Dogs tower

Hong Kong developer plans 460 flats block next to Millwall Inner Dock
4 days ago

Go-ahead for £850m North London estate rebuild

Flagship Edmonton housing estate redevelopment will deliver 2,000 new homes
4 days ago

Mace lands £184m Oxford Science Park contract

Contractor to build trio of laboratory and office buildings
5 days ago

Worker paralysed in 30ft fall during electricity pylon demolition

Specialist firm fined £240,000 after court hears linesman attached lanyard to a loosened steel section
4 days ago

Contractor services