Fresh site rules where 2m distancing cannot be obeyed

Aaron Morby 4 years ago
Share

Newly-updated site operating procedures for workers during the coronavirus outbreak have set out risk reduction measures where 2m distancing rules cannot be obeyed.

Third version of site operating procedures for workers spells out risk reduction measures
Third version of site operating procedures for workers spells out risk reduction measures

Version 3 of the industry’s site operating procedures allows closer than 2m working in special circumstances that are essential to project delivery.

The new Construction Leadership Council guidance recommends that where close working cannot be avoided its should be limited to less than 15 minutes and workers should be side by side rather than face to face.

The use of respiratory protective equipment should be used as a last resort in the hierarchy of mitigation measures.

More detailed guidance is now available for those who have no option but to share transport to work.

Contractors are told to put in place effective arrangements for monitoring and reviewing their compliance with the HSE now confirmed as the enforcing authority.

The latest update to SOP follows Public Health England guidance for construction sites. This states: “where it is not possible to follow the social distancing guidelines in full in relation to a particular activity, you should consider whether that activity needs to continue for the site to continue to operate, and, if so, take all the mitigating actions possible to reduce the risk of transmission”.

Hierarchy of Controls

Eliminate
• Unwell workers with symptoms should not travel to or attend the workplace
• Rearrange tasks to enable them to be done by one person, or by maintaining social distancing measures (2m)
• Avoid skin to skin and face to face contact
• Stairs to be used in preference to lifts or hoists, consider one-way systems
• Consider alternative or additional mechanical aids to reduce site meetings
• Only absolutely necessary meeting participants should attend
• Attendees should be at least two metres apart from each other
• Rooms should be well ventilated / windows opened to allow in fresh air
• Consider holding meetings in open areas where possible
Reduce
Where the social distancing measures (2 metres) cannot be applied
• Minimise frequency and time workers are within 2 metres of each other
• Minimise the number of workers involved in these tasks
• Workers should work side by side, or facing away from each other, rather than face to face
• Lower the worker capacity of lifts and hoists to reduce congestion and contact at all times
• Regularly clean common touchpoints, doors, buttons, handles, vehicle cabs, tools, equipment etc.
• Increase ventilation in enclosed spaces
• Workers should wash their hands before and after using any equipment
Isolate
Keep groups of workers that have to work within 2m
• Together in teams e.g. (do not change workers within teams)
• As small as possible
• Away from other workers where possible
Control
Where face to face working is essential to carry out a task when working within 2m
• Keep this to 15 minutes or less where possible
• Consider introducing an enhanced authorisation process for these activities
• Provide additional supervision to monitor and manage compliance
PPE
Sites should not use RPE for Coronavirus where 2m distancing guidelines are met.
• Where not possible to maintain a 2m distance, each activity must be risk assessed using the hierarchy of controls and against any sector-specific guidance, mindful that masks (RPE) are the last resort
• Re-usable PPE should be thoroughly cleaned after use and not shared
• Single-use PPE should be disposed of so that it cannot be reused
• Where personnel are required to work in specific environments (e.g. where persons are shielding, with symptoms, or confirmed Coronavirus cases may be present e.g. healthcare or in a home environment) additional PPE should be considered specific to the Coronavirus risk
Behaviours
The measures necessary to minimise the risk of spread of infection rely on everyone in the industry taking responsibility for their actions and behaviours.
Encourage an open and collaborative approach between workers and employers on site where any issues can be openly discussed and addressed.

Click for Site Operating Procedures guidance document

Latest news

Morgan Sindall to build former Willmott Dixon leisure job

New contractor appointed on
11 hours ago

Graham consortium wins £400m Manchester job

Equitix consortium to now work up DBFO plans for University of Manchester’s Fallowfield Campus
7 hours ago

Keltbray looking to sell infrastructure business

£378m turnover rail, energy and highways business up for sale
18 hours ago

Innovative viaduct building method used for first time in UK

HS2 contractors will build nine viaducts in Delta Junction using special cantilevered process
18 hours ago

Unite buys London site to fast-track 444-bed student scheme

£800m to be spent on London development pipeline in next five years
18 hours ago

CITB awards £2.5m of contracts to management consultant

Three outsourced deals in the last year for "project leadership and management consultancy"
18 hours ago

Village centre approved for 6,000-home new town plan

Hampshire's Welborne Garden Village plan has been in the pipeline for two decades.
17 hours ago

£3m fine after cherry picker demolition death

Court rules after tragedy during decommissioning of gas rig
18 hours ago

BAM plans wave of job cuts at UK Construction arm

Co-op Live arena plunges Bam Construction to £19.5m first-half loss
2 days ago

Robot tunnel builder goes into administration

Hypertunnel was hoping to revolutionise how underground structures are built
2 days ago

Wates to build £86m Guildford Council housing scheme

40% of the 248 homes will become council homes under partnership deal
2 days ago

“Scrap CITB” say three quarters of construction firms

Payroll giant Hudson Contract calls for CITB to be absorbed into new Skills England training body
2 days ago

£100m Prestwich Village revival approved

Vinci and Willmott Dixon in chase for Muse-led regeneration scheme
2 days ago

Carbon negative asphalt aggregate trialled on M11

Skanska and Tarmac test CO2 absorbing aggregate material on stretch of Essex motorway
2 days ago

Father and son sentenced over covid construction loan fraud

Bristol builders given suspended jail sentences over bogus Bounce Back Loans
2 days ago

Beck Interiors files administration notice

Supply chain has suffered delayed payments from £139m-turnover luxury fit out specialist
3 days ago

Green light for York Central civil service office hub

£60m office project accelerates York Central goods yard redevelopment
3 days ago

Blenheim House Construction enters administration

Administrators looking at options on present projects
3 days ago

Profits rise at Esh Group with more to come

Contractor confident about year ahead as market conditions move in right direction
3 days ago

Piling specialist Van Elle sees housing orders rise 30%

Mark Cutler says firm on course to deliver 10% annual sales growth
3 days ago

HS2 to spend £100m shutting sites where work never started

Remediation of sites no longer needed for cancelled Phase 2 will take three years
3 days ago

Willmott Dixon wins £61m deal for new Army dog unit

Contractor to revamp Kendrew Barracks in Rutland
3 days ago

Stockport advances 4,000-home Town Centre East plan

Council seeks consultants to steer plan for 280-acre area in the city
3 days ago

ISG sale imminent as buyers set-up UK holding company

South African nutrition entrepreneur and Australian partner primed to take over
4 days ago

CR Construction wins £210m Manchester towers

Construction to start next year on four blocks ranging from nine to 34-storeys
4 days ago

Southern Housing to rationalise supply chain following merger

Firms put on alert for £1.7bn construction framework renewal
4 days ago

Decision delayed on 52-storey Isle of Dogs tower

Hong Kong developer plans 460 flats block next to Millwall Inner Dock
4 days ago

Go-ahead for £850m North London estate rebuild

Flagship Edmonton housing estate redevelopment will deliver 2,000 new homes
4 days ago

Mace lands £184m Oxford Science Park contract

Contractor to build trio of laboratory and office buildings
5 days ago

Worker paralysed in 30ft fall during electricity pylon demolition

Specialist firm fined £240,000 after court hears linesman attached lanyard to a loosened steel section
4 days ago

Contractor services