Relations are souring between subcontractors and smaller housing developers as the fall-out from the coronavirus crisis continues to create tension across construction.

The Enquirer has been contacted by a string of specialists caught up in rows with clients on residential jobs.

The major house builders are gradually returning to work.

But many of the problems are centred-on sites run by small and medium sized developers.

One groundworks specialist said: “We are caught up in a dispute with a housing developer in Buckinghamshire.

“They closed their sites at the end of March along with many companies. We were due to have our February Valuation paid on April 1 when we they asked us along with all the other subcontractors on site to agree to accept just 50% of the valuation.

“We declined as we felt this was unfair as all the works were carried out prior to Covid-19 and we had in turn paid all our suppliers.

“To top it all they then asked the trades to return to site last week without receiving any payment.

“We cannot get them to even give us common courtesy and reply to our emails or telephone calls. We are trying to do the best for our suppliers, but companies like this put all the trades in untenable situations.”

Another decorating specialist said: “We have been hit with a seven-day notice by a housing developer.

“Our staff and our self employed workers are on furlough yet the developer is demanding us back on site by the end of this week to work on their flats.”

Emails from the developer seen by the Enquirer state: “We are not being aggressive just acting on our own predicament in line with government guidance .

“We are contractually bound, despite the pandemic. Therefore we need our contractors to perform.

“It is clear that although the country is on lockdown the construction industry is not .

“You clearly do not have the appetite to complete the works in the timeframe which you have agreed to and we have no option but to issue you this notice.

“We have at no point closed the site and we have had other trades working safely.”

Another M&E specialist said: “We have submitted our February valuations and the developer has refused point blank to pay them.

“They sent us an email saying their board has decided not to pay to protect their business.

“What about our business?”

Latest news

Go-ahead for City of London’s tallest tower

1 Undershaft building will equal the Shard in height
3 hours ago

Construction T Level scrapped due to lack of demand

Courses canned after less than 100 sign-up for latest round
1 day ago

Five firms clinch £300m Greenwich Uni framework deal

McLaren, Wates, Morgan Sindall, Vinci and Willmott Dixon secure places
9 hours ago

Hill Group strikes first Build to Rent deal

House builder agrees finance with Lloyds Living to start Stevenage scheme
9 hours ago

Construction output hit by fall in repair and maintenance

Industrial and commercial new work grows despite wider fall in activity
9 hours ago

Wates transfers pension scheme to “superfund”

Pension management specialist Clara to take charge of £210m fund
9 hours ago

Muse hires new development director for North West

Tom Darby joins from developer Bruntwood
9 hours ago

Bid rigging probe launched into school repair work

Firms raided this week with focus on roofing contracts
2 days ago

McLaren hires ex-ISG regional boss for north east expansion

Andrew Beaumont becomes MD of new Yorkshire and North East business
1 day ago

Government commits to four new prisons in seven years

£2.3bn pledged for new prison build programme
2 days ago

Road and rail delays hit revenue at Van Elle

Turnover drops 5% as markets remain challenging for piling specialist
1 day ago

Boot reports ‘noticeable improvement’ in planning system

Government planning reforms already unblocking council planning
1 day ago

Go-ahead to revamp former London city hall

Project will straighten the building's leaning profile with terraces to every level
2 days ago

United Living to divert Midlands gas pipeline

600m pipeline diversion clears way for M54 to M6 link road construction
1 day ago

Credit insurance saves Billington from ISG hit

Steel specialist puts on extra shifts at its plants to cope with demand
2 days ago

M&E specialist Dodd doubles profit on retrofit surge

Family-owned Telford specialist delivers record revenue of nearly £250m
2 days ago

Go-ahead for 800-home Croydon dual towers

One Lansdowne Road build to rent scheme to cost £260m to build
2 days ago

Construction inflation set to return raising tender prices

End of 2024 to mark the bottom of present inflationary trough
2 days ago

Start date for vast Balfour and Costain carbon capture power job

£4bn Teesside project to start construction next year creating 3,000 jobs
3 days ago

Plans go in to start revamp of North Finchley town centre

Developer Regal unveils first details of Barnet masterplan
2 days ago

Glencar bags £18m Big Yellow London store

Six-storey stoarage centre to be built at Staples Corner
2 days ago

Plan unveiled for 31-storey London Fenchurch Street tower

Demolition work to start in 2026 for new office tower
3 days ago

Vinci Building buys tower cranes for first time

Contractor invests in two WOLFFKRAN all-electric cranes at £138m Sheffield site
3 days ago

30 local firms land United Utilities £500m framework

Minor works deal win for North West civils and M&E specialists
3 days ago

Restructure pays off as Higgins returns to profit

Housing contractor recovers from £25.9m loss last year
3 days ago

Former Heathrow boss joins Mace in board rejig

Firm completes string NED appointments to expanded group board
4 days ago

Planning officers to get powers to bypass committee stage for housing

Rayner reform plan to cut out local council planning committees
4 days ago

National Insurance hike to delay construction recovery

Arcadis paints varied picture with full recovery delayed until 2026
4 days ago

Gratte Bros rides out cost rises with profit increase

M&E specialist warns of further upward pressure on wage costs
4 days ago

Sellar’s 36-storey London City office tower approved

Demolition work to start in 2026 at 60 Gracechurch Street site
6 days ago

Contractor services