Willmott Dixon masters social distancing site challenge

Aaron Morby 5 years ago
Share

Willmott Dixon is using a mix of technology and novel working practices to keep its £48m Birmingham University school of engineering project on track during the coronavirus epidemic.

The project is about six months away from completing
The project is about six months away from completing

The private building contractor was one of the first firms to adopt new site working practices in the early stages of coronavirus lockdown.

Nick Proverbs, senior operations manager, said the big project had now successfully adapted to ensure workers could observe social distancing measures.

The change has involved clearer planning of activity and in some instances moving work off-site to give workers more space.

Now Willmott Dixon also holds virtual site tours for its client.

“When guidance by Construction Leadership Council was released, our first action was to review what roles could be performed from home, which led to our design and commercial teams relocating to their homes,” said Proverbs.

“This helped free up space in our site cabins to implement social distancing measures, placing each desk station more than 2m apart at any one point.

“Our supply chain partners also implemented the same process in their site cabins to reduce the number of people to just key roles.”

UoB office distancing.jpg

Site team re-configured operations to ensure social distancing site lay-out.

Willmott Dixon looked at where bottlenecks were likely to be, such as staircases and routes in and out of the site.

To combat this, it created a series of one-way systems, allowing site operatives to keep their distance and avoid oncoming people.

UoB one way.jpg

To give site operatives greater space to take their breaks in, Willmott Dixon hired a 190 sq m marquee, erected on one of the University car parks.

Marquee as a canteen.JPG

Temporary canteen allows social distancing at breaks

In other areas, Willmott Dixon created rotas and removed seats to prevent overcrowding.

The firm has also appointed a site attendant to monitor the drying room to ensure no more than two people use it at any one time.

Canteens, meeting rooms, desks, and all site entrances and exits were equipped with hand sanitisers.

UoB hand sanitiser.jpg

Each morning, Willmott Dixon holds toolbox talks with staff and supply chain partners to communicate the latest guidance and working practices.

Meetings are held in open areas, allowing for the maintenance of the 2m rule.

Where roles can abide by social distancing work has continued.  For roles such as installing plasterboard, where it is near-impossible to work safely while abiding by social distancing, work has stopped.

Proverbs said that if anyone shows symptoms of the coronavirus or needs to self-isolate, they are empowered to do so and it is critical they abide by this directive.

UoB5.jpg

Willmott Dixon has finished constructing the concrete frame and is currently building the atrium roof, external windows and cladding, as well as internal stud partitioning and mechanical and electrical installations.

“Most of the work has been able to continue and abide by social distancing,” said proverbs.

“In some instances, such as some of the joinery in the atrium, work has been moved to take place offsite to enable more space for site operatives to work.”

He added that the supply of materials had become more challenging after some builders’ merchants closed, although many are now reopening.

He said: “We have also experienced materials we have ordered being diverted to the NHS; this is completely understandable at a time of crisis.”

To plan works, Willmott Dixon is using Spannureva, an application based sticky note planning system.

This allows it to collaboratively plan anywhere, maintaining social distancing on-site while allowing those working from home to participate.

All supply chain and design partners have access to the plan, which allows for discussions around planned activity.

“Through implementing this process, we are seeing an increase of 25% in our planned activity complete measures,” said Proverbs.

UoB2.jpg

Keeping the customer abreast of progress and challenges remains critical.

At the start of each week, there is an internal operations COVID-19 virtual meeting to review overall progress, current works, any challenges the team are facing and what it means to the project.

Each Wednesday Willmott Dixon holds a virtual guided site tour for the client using a GoPro.

The video is then uploaded to Microsoft Teams, allowing the customer to see the latest developments, pause and ask questions.

UoB3.jpg

Site tours are now done online

Latest news

Former Hewlett civils firm fails amid director blame game

£17m turnover CORE Special Projects ceases trading after 10 years
2 days ago

Problem job sinks Mace construction profits

Consultancy arm now making more money than larger construction division
3 days ago

Acciona heads May contracts league with water job

Mace displaces Sir Robert McAlpine at the top of the annualised rankings
2 days ago

Cardo swoops for wall insulation specialist SERS

Building maintenance group continues rapid growth spree with takeover of retrofit expert
2 days ago

New finance chief at Laing O’Rourke

Accountant Ilze Williamson joins from architecture practice
2 days ago

United Living acquires civils specialist Glenelly

Latest move in the power infrastructure sector
2 days ago

Gloom slowly lifting from construction buyers

"Worst phase of spending cutbacks may have passed"
3 days ago

Over 1,300 finished flats lying empty in Gateway 3 logjam

Final safety sign-off stalls occupation and pushes developers to the brink
3 days ago

Modular specialist Elements Europe falls into administration

Move into main contracting sinks pod specialist
3 days ago

Magrock lands first job with Big Yellow Self Storage

Construction to start this summer on Kentish Town site
3 days ago

Van Elle hit by BSR delays as £134m revenue falls short

Building Safety Regulator logjam delays major resi piling jobs
3 days ago

ECF seals £1bn deal for Northampton town revamp

Development agreement for 25-acre town centre reboot
3 days ago

Demolition starts revamp of 16 acre Luton site

Construction to start by end of year on major industrial and logistics scheme
3 days ago

Anglian Water ramps up pipeline rollout with fresh 260km deal

More drought-busting pipeline work flows to Strategic Pipeline Alliance firms
3 days ago

Framework winners named on Peel Ports £750m deal

Graham and Mclaughlin & Harvey share major works lot
3 days ago

Reeves pledges £15.6bn for regional transport

Chancellor to unveil big spending package today for Metro mayors
4 days ago

Kier ditches diesel for hydrogen in green major site power trial

Trial shows over 20,000 litres of diesel already saved at Bridgwater Tidal Barrier
4 days ago

Plans unveiled for 1million sq ft commercial scheme

Design & build opportunities available at Scunthorpe site
4 days ago

Bouygues seals £119m deal for twin college builds in Wales

Work starts this month on Barry Waterfront and Cardiff Airport tech hubs
4 days ago

MPs back Sellafield delivery shake-up but costs spiralling to £136bn

Four out of five recent projects now on track, but wider site faces growing risks
4 days ago

Fraudster ordered to pay back £80k to contractors

Office worker embezzled £516,000 from two construction companies
4 days ago

Wates gets start date for Victoria Tower restoration

Work to begin this summer and last to 2031
4 days ago

Kier upgrades margin target as order book holds firm

Contractor eyes 4.5% margin as bid discipline pays off
5 days ago

Willmott Dixon bags hat-trick of leisure centre energy retrofits

£15.8m North Herts Council deal includes replacing boilers for air source heat pumps
5 days ago

Drylining giant takes bold step on accepting design risk

Siniat liability pledge designed to stop risk being pushed down supply chain
5 days ago

Section 106 agreements now taking an average of 16 months

Planning departments cannot cope with workloads leading to more house building delays
5 days ago

Winvic starts £200m Towcester Park logistics scheme

IM Properties presses ahead with 1.1m sq ft Midlands logistics park
5 days ago

Safety regulatory drag takes toll on Getjar turnover

Revenue slumps 42% as firm adapts to slower resi job starts
6 days ago

Erith seals early works for £300m London City Road tower

Demolition to start this summer for landmark Old Street roundabout job
6 days ago

Galliford gets sign-off to start Wigan Galleries job

Fettlers scheme starts with £44m market hall and basement build
6 days ago

Contractor services