Willmott Dixon masters social distancing site challenge

Aaron Morby 5 years ago
Share

Willmott Dixon is using a mix of technology and novel working practices to keep its £48m Birmingham University school of engineering project on track during the coronavirus epidemic.

The project is about six months away from completing
The project is about six months away from completing

The private building contractor was one of the first firms to adopt new site working practices in the early stages of coronavirus lockdown.

Nick Proverbs, senior operations manager, said the big project had now successfully adapted to ensure workers could observe social distancing measures.

The change has involved clearer planning of activity and in some instances moving work off-site to give workers more space.

Now Willmott Dixon also holds virtual site tours for its client.

“When guidance by Construction Leadership Council was released, our first action was to review what roles could be performed from home, which led to our design and commercial teams relocating to their homes,” said Proverbs.

“This helped free up space in our site cabins to implement social distancing measures, placing each desk station more than 2m apart at any one point.

“Our supply chain partners also implemented the same process in their site cabins to reduce the number of people to just key roles.”

UoB office distancing.jpg

Site team re-configured operations to ensure social distancing site lay-out.

Willmott Dixon looked at where bottlenecks were likely to be, such as staircases and routes in and out of the site.

To combat this, it created a series of one-way systems, allowing site operatives to keep their distance and avoid oncoming people.

UoB one way.jpg

To give site operatives greater space to take their breaks in, Willmott Dixon hired a 190 sq m marquee, erected on one of the University car parks.

Marquee as a canteen.JPG

Temporary canteen allows social distancing at breaks

In other areas, Willmott Dixon created rotas and removed seats to prevent overcrowding.

The firm has also appointed a site attendant to monitor the drying room to ensure no more than two people use it at any one time.

Canteens, meeting rooms, desks, and all site entrances and exits were equipped with hand sanitisers.

UoB hand sanitiser.jpg

Each morning, Willmott Dixon holds toolbox talks with staff and supply chain partners to communicate the latest guidance and working practices.

Meetings are held in open areas, allowing for the maintenance of the 2m rule.

Where roles can abide by social distancing work has continued.  For roles such as installing plasterboard, where it is near-impossible to work safely while abiding by social distancing, work has stopped.

Proverbs said that if anyone shows symptoms of the coronavirus or needs to self-isolate, they are empowered to do so and it is critical they abide by this directive.

UoB5.jpg

Willmott Dixon has finished constructing the concrete frame and is currently building the atrium roof, external windows and cladding, as well as internal stud partitioning and mechanical and electrical installations.

“Most of the work has been able to continue and abide by social distancing,” said proverbs.

“In some instances, such as some of the joinery in the atrium, work has been moved to take place offsite to enable more space for site operatives to work.”

He added that the supply of materials had become more challenging after some builders’ merchants closed, although many are now reopening.

He said: “We have also experienced materials we have ordered being diverted to the NHS; this is completely understandable at a time of crisis.”

To plan works, Willmott Dixon is using Spannureva, an application based sticky note planning system.

This allows it to collaboratively plan anywhere, maintaining social distancing on-site while allowing those working from home to participate.

All supply chain and design partners have access to the plan, which allows for discussions around planned activity.

“Through implementing this process, we are seeing an increase of 25% in our planned activity complete measures,” said Proverbs.

UoB2.jpg

Keeping the customer abreast of progress and challenges remains critical.

At the start of each week, there is an internal operations COVID-19 virtual meeting to review overall progress, current works, any challenges the team are facing and what it means to the project.

Each Wednesday Willmott Dixon holds a virtual guided site tour for the client using a GoPro.

The video is then uploaded to Microsoft Teams, allowing the customer to see the latest developments, pause and ask questions.

UoB3.jpg

Site tours are now done online

Latest news

Go-ahead for City of London’s tallest tower

1 Undershaft building will equal the Shard in height
1 day ago

Construction T Level scrapped due to lack of demand

Courses canned after less than 100 sign-up for latest round
2 days ago

Five firms clinch £300m Greenwich Uni framework deal

McLaren, Wates, Morgan Sindall, Vinci and Willmott Dixon secure places
2 days ago

Hill Group strikes first Build to Rent deal

House builder agrees finance with Lloyds Living to start Stevenage scheme
2 days ago

Construction output hit by fall in repair and maintenance

Industrial and commercial new work grows despite wider fall in activity
2 days ago

Wates transfers pension scheme to “superfund”

Pension management specialist Clara to take charge of £210m fund
2 days ago

Muse hires new development director for North West

Tom Darby joins from developer Bruntwood
2 days ago

Bid rigging probe launched into school repair work

Firms raided this week with focus on roofing contracts
3 days ago

McLaren hires ex-ISG regional boss for north east expansion

Andrew Beaumont becomes MD of new Yorkshire and North East business
3 days ago

Government commits to four new prisons in seven years

£2.3bn pledged for new prison build programme
3 days ago

Road and rail delays hit revenue at Van Elle

Turnover drops 5% as markets remain challenging for piling specialist
3 days ago

Boot reports ‘noticeable improvement’ in planning system

Government planning reforms already unblocking council planning
3 days ago

Go-ahead to revamp former London city hall

Project will straighten the building's leaning profile with terraces to every level
3 days ago

United Living to divert Midlands gas pipeline

600m pipeline diversion clears way for M54 to M6 link road construction
3 days ago

Credit insurance saves Billington from ISG hit

Steel specialist puts on extra shifts at its plants to cope with demand
4 days ago

M&E specialist Dodd doubles profit on retrofit surge

Family-owned Telford specialist delivers record revenue of nearly £250m
4 days ago

Go-ahead for 800-home Croydon dual towers

One Lansdowne Road build to rent scheme to cost £260m to build
4 days ago

Construction inflation set to return raising tender prices

End of 2024 to mark the bottom of present inflationary trough
4 days ago

Start date for vast Balfour and Costain carbon capture power job

£4bn Teesside project to start construction next year creating 3,000 jobs
4 days ago

Plans go in to start revamp of North Finchley town centre

Developer Regal unveils first details of Barnet masterplan
4 days ago

Glencar bags £18m Big Yellow London store

Six-storey stoarage centre to be built at Staples Corner
4 days ago

Plan unveiled for 31-storey London Fenchurch Street tower

Demolition work to start in 2026 for new office tower
5 days ago

Vinci Building buys tower cranes for first time

Contractor invests in two WOLFFKRAN all-electric cranes at £138m Sheffield site
5 days ago

30 local firms land United Utilities £500m framework

Minor works deal win for North West civils and M&E specialists
5 days ago

Restructure pays off as Higgins returns to profit

Housing contractor recovers from £25.9m loss last year
5 days ago

Former Heathrow boss joins Mace in board rejig

Firm completes string NED appointments to expanded group board
5 days ago

Planning officers to get powers to bypass committee stage for housing

Rayner reform plan to cut out local council planning committees
5 days ago

National Insurance hike to delay construction recovery

Arcadis paints varied picture with full recovery delayed until 2026
6 days ago

Gratte Bros rides out cost rises with profit increase

M&E specialist warns of further upward pressure on wage costs
6 days ago

Sellar’s 36-storey London City office tower approved

Demolition work to start in 2026 at 60 Gracechurch Street site
1 week ago

Contractor services