Opinion: Get Covid-19 site restart contract terms sorted now

Aaron Morby 5 years ago
Share

This week the bulk of contractors still on site shutdown will begin the return to work across England and Wales.

The industry is in uncharted territory complying with new safe working restrictions and the added transport and accommodation challenges.

Social distancing is not yet written into any contracts but it is something that will clearly generate extra costs and hit production.

Industry leaders fearing the worst have called for clients, main contractors and the rest of the supply chain to support each other and adopt conflict avoidance approaches.

But for subcontractors who have already been on the receiving end of 7-day notices and the threat of LADS, good practice guides are just window dressing.

There are good ways and bad ways to get through the challenges ahead.

The question of who pays for the added costs and programme slippage should not be left for courts to decide on in the future.

At this extraordinary moment in time, the industry is looking to unite in a common cause – trying to get back to work safely.

This moment must not be thrown away.  But the biggest mistake is to focus on the aspiration, blind of the likely problems.

Projects should have agreements in place that are legally solid to avoid a tsunami of litigation later down the line.

Restart terms and conditions need to be set in stone now or it will become a future contract-row bonanza for lawyers and a blight on construction.

A recognised Covid-19 claim provision that takes account of slower working conditions would also be a good idea.

Sites must be monitored to ensure safe practice is genuinely being followed.

The Health and Safety Executive with its resource shortcomings cannot be relied upon to police this across the country.

The industry must put in place its own strict plans for how it will deal with failures to observe good practice.

It also needs to find pragmatic ways to measure the relative safety in relation to viral transmission of different ways of working.

Contractors or subcontractors should not be bullied into working if they have genuine safety concerns for their employees, nor should they be allowed to hold clients to ransom.

But they must get as watertight an agreement as possible before work commences or problems will fester.

At its core, construction is a very flexible industry used to absorbing shocks, so it has the capacity to change.

Now is the time to start. 

 

Latest news

Go-ahead for City of London’s tallest tower

1 Undershaft building will equal the Shard in height
21 hours ago

Construction T Level scrapped due to lack of demand

Courses canned after less than 100 sign-up for latest round
2 days ago

Five firms clinch £300m Greenwich Uni framework deal

McLaren, Wates, Morgan Sindall, Vinci and Willmott Dixon secure places
1 day ago

Hill Group strikes first Build to Rent deal

House builder agrees finance with Lloyds Living to start Stevenage scheme
1 day ago

Construction output hit by fall in repair and maintenance

Industrial and commercial new work grows despite wider fall in activity
1 day ago

Wates transfers pension scheme to “superfund”

Pension management specialist Clara to take charge of £210m fund
1 day ago

Muse hires new development director for North West

Tom Darby joins from developer Bruntwood
1 day ago

Bid rigging probe launched into school repair work

Firms raided this week with focus on roofing contracts
3 days ago

McLaren hires ex-ISG regional boss for north east expansion

Andrew Beaumont becomes MD of new Yorkshire and North East business
2 days ago

Government commits to four new prisons in seven years

£2.3bn pledged for new prison build programme
3 days ago

Road and rail delays hit revenue at Van Elle

Turnover drops 5% as markets remain challenging for piling specialist
2 days ago

Boot reports ‘noticeable improvement’ in planning system

Government planning reforms already unblocking council planning
2 days ago

Go-ahead to revamp former London city hall

Project will straighten the building's leaning profile with terraces to every level
2 days ago

United Living to divert Midlands gas pipeline

600m pipeline diversion clears way for M54 to M6 link road construction
2 days ago

Credit insurance saves Billington from ISG hit

Steel specialist puts on extra shifts at its plants to cope with demand
3 days ago

M&E specialist Dodd doubles profit on retrofit surge

Family-owned Telford specialist delivers record revenue of nearly £250m
3 days ago

Go-ahead for 800-home Croydon dual towers

One Lansdowne Road build to rent scheme to cost £260m to build
3 days ago

Construction inflation set to return raising tender prices

End of 2024 to mark the bottom of present inflationary trough
3 days ago

Start date for vast Balfour and Costain carbon capture power job

£4bn Teesside project to start construction next year creating 3,000 jobs
4 days ago

Plans go in to start revamp of North Finchley town centre

Developer Regal unveils first details of Barnet masterplan
3 days ago

Glencar bags £18m Big Yellow London store

Six-storey stoarage centre to be built at Staples Corner
3 days ago

Plan unveiled for 31-storey London Fenchurch Street tower

Demolition work to start in 2026 for new office tower
4 days ago

Vinci Building buys tower cranes for first time

Contractor invests in two WOLFFKRAN all-electric cranes at £138m Sheffield site
4 days ago

30 local firms land United Utilities £500m framework

Minor works deal win for North West civils and M&E specialists
4 days ago

Restructure pays off as Higgins returns to profit

Housing contractor recovers from £25.9m loss last year
4 days ago

Former Heathrow boss joins Mace in board rejig

Firm completes string NED appointments to expanded group board
5 days ago

Planning officers to get powers to bypass committee stage for housing

Rayner reform plan to cut out local council planning committees
5 days ago

National Insurance hike to delay construction recovery

Arcadis paints varied picture with full recovery delayed until 2026
5 days ago

Gratte Bros rides out cost rises with profit increase

M&E specialist warns of further upward pressure on wage costs
5 days ago

Sellar’s 36-storey London City office tower approved

Demolition work to start in 2026 at 60 Gracechurch Street site
7 days ago

Contractor services