Parliament restoration plan under review

Aaron Morby 5 years ago
Share

The independent body set up to manage the £4bn-plus restoration of the Houses of Parliament has put the project on pause to re-examine fully the current plan.

An expert team set up by the new Sponsor Body in charge of the work will review all options for how the restoration programme should proceed, including new ways of working during the coronavirus outbreak.

They will also reassess the central decision taken five years ago to relocate all MPs and Lords to allow work to proceed. This was seen as the “best and most cost-effective” option.

The upgrade to the Northern Estate to create the temporary home for MPs will itself cost up to £1.6bn.

Sarah Johnson, the Sponsor Body CEO, said given the completely altered political and economic landscape, the review will need to be both deeper and more wide-ranging than initially anticipated.

She said: “The restoration and renewal of the Houses of Parliament will be the biggest and most complex heritage project ever undertaken in the UK.

“The Sponsor Body has been set up to ensure that the project is delivered in the most efficient way that delivers value for money.

“It is entirely appropriate that we should pause at this time to consider the validity of recommendations made over five years ago before either the Sponsor Body or Delivery Authority was formed.

“The impact of the current health crisis on public finances and Parliament’s ways of working has made it even more essential that we review both the strategy for relocating the two Houses and the scope of the restoration of the Palace.”

The Sponsor Body was formally established last month. It is the single client accountable to Parliament and oversees the Delivery Authority, which will carry out the work.

Johnson said she would involve infrastructure and programme management experts drawn from the Sponsor Body and Delivery Authority to carry out the assessment.

She added that The House of Commons now contains many new Members elected for the first time who may well take a different view of Restoration and Renewal from Members in 2016.

It is also a very different Government which, even before the current crisis, had a clear set of priorities. In the light of Covid-19, there are likely to be other key drivers, arising mainly as a result of the impact on the economy, on public finances and on the population at large.

The Sponsor Body review is launched today and is expected to report in the autumn.

Latest news

Network Rail fined £3.75m after double track worker death

Michael Lewis and Gareth Delbridge were killed while working on rail line in Wales
8 hours ago

Local contractor Castle lands £60m South Shields campus

Work to start this summer on new home for South Tyneside College and South Shields Marine School
13 hours ago

GRAHAM wins £100m deal after safety regulator approval

Dyecoats scheme in Leeds becomes one of first to receive Building Safety Act Gateway 2 green light
2 days ago

London Super Sewer now fully connected

10-year construction programme draws to a close
21 hours ago

McLaren signs off £125m London Bank over-station job

Developer Helical secures funding deal for 8-storey office job
20 hours ago

Work on Labour’s new towns to start by 2029

More than 100 sites put forward for a dozen new town locations
1 day ago

Unite hails 12 years without a site accident at Battersea

More than 4,000 union members have worked on the redevelopment without a single serious accident
20 hours ago

Housing orders surge offers hope after 5.2% new work fall last year

Housing orders surged 24% in final quarter of 2024 as developers release schemes
2 days ago

McLaren Property gets new Construction Director

Jon Mangham joins from Equans
1 day ago

BAM Construction suffers £40m loss after Co-op Live setback

Civils business profit surges 24% to £80m
2 days ago

Over 150 jobs axed as J S Wright goes under

Insolvency specialist FRP Advisory goes in at Birmingham M&E specialist
2 days ago

Extra cash found to speed-up safety regulator

Government to spend extra £2m to clear backlog of high rise approvals
2 days ago

Galliford Try lands £63m RAF accommodation deal

Work to start within months at RAF Digby in Lincolnshire
2 days ago

Balfour Beatty wins Trent arched bridge job

Briton Fabricators will build the £13m bridge from prefabricated sections
2 days ago

Goldbeck to build new £50m Cardiff County Hall

German-owned contractor vowing to be a "disrupter in the UK market"
2 days ago

Laing O’Rourke chairman to step down

Ray O'Rourke to take over chair from Sir John Parker
3 days ago

Farrans lands Leeds Bradford Airport phase 2 upgrade

Contractor takes follow-on refurb job after terminal extension
3 days ago

ISG built Bristol housing block to be torn down

Contractor's collapse sinks Bristol flats remediation claim
3 days ago

RSK revenue nears £2bn as losses soar to £132m

Refinancing last summer puts group on course for more growth this year
3 days ago

Bridge design wind error adds £20m to construction costs

Completion of £148m Grantham Southern Relief Road delayed by a year
3 days ago

Rayner pledges extra £350m for social house building

More than 3,000 homes could be built with cash injection
3 days ago

City’s biggest retrofit tower scheme approved

Triple-fronted 70 Gracechurch Street building will rise to 33 storeys
4 days ago

Defibrillator saves worker’s life on Wates site

Machine operator saved after "dying" for 16 minutes on prison job
4 days ago

Funding deal for £125m Camden Roundhouse scheme

Developer Regal set to start 264-bed student scheme
4 days ago

Balfour leadership rejig to focus on three key growth sectors

Divisional CEO trio take lead roles for energy, defence and transport expansion
4 days ago

ABP bidders day for £150m Humber ports pipeline

Nine projects in the pipeline to support automotive and energy transition schemes
4 days ago

Hinkley Point C to create 3,000 jobs as work ramps up

Fitout surge to swell workforce to 15,000 in next 18 months
4 days ago

Hercules sells suction excavator division for £2.4m

Loss making arm sold by labour hire specialist
4 days ago

Foundations complete at HS2 Old Oak Common station

Station base completed using 76,000 cubic metres of concrete and 17,000 tonnes of reinforced steel
4 days ago

Bids invited for £175m consultancy framework

Fusion21 inviting consultants to join latest four-year deal
4 days ago

Contractor services