Watkin Jones faces £15m cladding replacement bill

Grant Prior 5 years ago
Share

Watkin Jones is bracing itself for a bill of up to £15m to replace cladding on eight student accommodation blocks.

The towers are covered in high pressure laminate (HPL) cladding which the government has advised should be removed from high-rise buildings.

Watkin Jones said it would look to recover some of the costs from consultants and subcontractors involved in the original construction.

It said: “In response to the revised Government guidance, issued in January 2020, on the suitability of certain cladding solutions used on high-rise residential buildings, the Group is working with the owners of eight of its previously developed purpose-built student accommodation schemes to remediate/replace cladding. 

“The majority of the cladding is high pressure laminate (HPL), which has been under more recent scrutiny and is covered by the revised guidance.  

“The group is taking proactive and responsible steps to ensure the safety of tenants, working with building owners, even though the buildings concerned were developed in accordance with all building regulations at the time of construction and no liability is accepted for the works.

Discussions with the property owners remain ongoing, but the board currently expects that this may result in a sharing of the costs of certain remedial works with them. 

“The gross cost to the group could be in the range of £12 million to £15 million, over the next two years. 

“A one-off non-underlying provision for this cost is likely to be made at the year end, once the outcome of those discussions has been established.  

“The group will look to recover some of this cost from the subcontractors and consultants engaged on implementing the particular cladding systems at the time. 

“This is likely to take an extended period of time to achieve and the extent of any recovery is currently uncertain.”

The announcement came at Watkin Jones announced strong first half results for the six months to March 31 2020.

Pre-tax profit was up to £26.6m from £22.4m last year as revenue rose to £185.7m from £159.1m.

Most sites have now been remobilised following lockdown with jobs operating at around 75% capacity.

Watkin Jones said: “We anticipate a modest increase in costs to complete our committed development programme during Covid-19 disruption.”

Latest news

ECF clinches deal for Hull 850-home urban village

East Bank waterside village plan advances
8 hours ago

Passenger train derailed after hitting track left by Colas workers

Contractor and Network Rail asked to make improvements after accident
7 hours ago

Bryson signs £6m safety products deal with Skanska

Safety specialist becomes sole supplier to contracting giant
6 hours ago

Murphy wins £120m St Fergus gas compressor project

Three low emission compressor units to be installed for National Gas
3 hours ago

Blenheim House payout hopes fade as claims hit £33m

Suggested 10p in the £1 payout for subcontractors now unlikely
18 hours ago

£1.3bn decarbonising and fire safety deals out for bid

South East Consortium starts hunt for firms for housing upgrade work prize
18 hours ago

£30m turnover M&E contractor files administration notice

TNA Electrical makes administration application
19 hours ago

Plan for first big offices at £1.7bn Manchester innovation hub

500,000 sq ft of offices planned at renamed Sister development
18 hours ago

Murphy starts work on £2.5bn Eastern Green Link 1

Giant subsea electricity cable project will take three years to build
18 hours ago

Subcontractors wanted for work across Birmingham

Latest Constructionline event: Register now
19 hours ago

Acheson Construction files administration notice

£53m turnover South West contractor lodges court notice
2 days ago

Hunt for 10 firms to deliver £37bn new hospital plan

Race starts for mega-framework with pledge to spread work among all firms
2 days ago

Springfield to build homes for army of green energy workers

Scottish house builder sells 2,480 plots to Barratt Redrow in strategy switch
2 days ago

Preferred bidder for Stoke city centre scheme

Genr8 Kajima to build Etruscan Square scheme in Hanley
2 days ago

BAM go-ahead for £56m Glasgow leisure centre

Work to start on East Renfrewshire complex later this year
2 days ago

Network Rail fined £3.75m after double track worker death

Michael Lewis and Gareth Delbridge were killed while working on rail line in Wales
4 days ago

Local contractor Castle lands £60m South Shields campus

Work to start this summer on new home for South Tyneside College and South Shields Marine School
4 days ago

GRAHAM wins £100m deal after safety regulator approval

Dyecoats scheme in Leeds becomes one of first to receive Building Safety Act Gateway 2 green light
5 days ago

London Super Sewer now fully connected

10-year construction programme draws to a close
5 days ago

McLaren signs off £125m London Bank over-station job

Developer Helical secures funding deal for 8-storey office job
5 days ago

Work on Labour’s new towns to start by 2029

More than 100 sites put forward for a dozen new town locations
5 days ago

Unite hails 12 years without a site accident at Battersea

More than 4,000 union members have worked on the redevelopment without a single serious accident
5 days ago

Housing orders surge offers hope after 5.2% new work fall last year

Housing orders surged 24% in final quarter of 2024 as developers release schemes
6 days ago

McLaren Property gets new Construction Director

Jon Mangham joins from Equans
5 days ago

BAM Construction suffers £40m loss after Co-op Live setback

Civils business profit surges 24% to £80m
6 days ago

Over 150 jobs axed as J S Wright goes under

Insolvency specialist FRP Advisory goes in at Birmingham M&E specialist
6 days ago

Extra cash found to speed-up safety regulator

Government to spend extra £2m to clear backlog of high rise approvals
6 days ago

Galliford Try lands £63m RAF accommodation deal

Work to start within months at RAF Digby in Lincolnshire
6 days ago

Balfour Beatty wins Trent arched bridge job

Briton Fabricators will build the £13m bridge from prefabricated sections
6 days ago

Goldbeck to build new £50m Cardiff County Hall

German-owned contractor vowing to be a "disrupter in the UK market"
6 days ago

Contractor services