Watkin Jones faces £15m cladding replacement bill

Grant Prior 4 years ago
Share

Watkin Jones is bracing itself for a bill of up to £15m to replace cladding on eight student accommodation blocks.

The towers are covered in high pressure laminate (HPL) cladding which the government has advised should be removed from high-rise buildings.

Watkin Jones said it would look to recover some of the costs from consultants and subcontractors involved in the original construction.

It said: “In response to the revised Government guidance, issued in January 2020, on the suitability of certain cladding solutions used on high-rise residential buildings, the Group is working with the owners of eight of its previously developed purpose-built student accommodation schemes to remediate/replace cladding. 

“The majority of the cladding is high pressure laminate (HPL), which has been under more recent scrutiny and is covered by the revised guidance.  

“The group is taking proactive and responsible steps to ensure the safety of tenants, working with building owners, even though the buildings concerned were developed in accordance with all building regulations at the time of construction and no liability is accepted for the works.

Discussions with the property owners remain ongoing, but the board currently expects that this may result in a sharing of the costs of certain remedial works with them. 

“The gross cost to the group could be in the range of £12 million to £15 million, over the next two years. 

“A one-off non-underlying provision for this cost is likely to be made at the year end, once the outcome of those discussions has been established.  

“The group will look to recover some of this cost from the subcontractors and consultants engaged on implementing the particular cladding systems at the time. 

“This is likely to take an extended period of time to achieve and the extent of any recovery is currently uncertain.”

The announcement came at Watkin Jones announced strong first half results for the six months to March 31 2020.

Pre-tax profit was up to £26.6m from £22.4m last year as revenue rose to £185.7m from £159.1m.

Most sites have now been remobilised following lockdown with jobs operating at around 75% capacity.

Watkin Jones said: “We anticipate a modest increase in costs to complete our committed development programme during Covid-19 disruption.”

Latest news

Geoffrey Osborne files administration notice

Contractor in talks to save parts of the business
2 days ago

RG Group signs £121m Newcastle rental homes job

Developer Olympian Homes advances 519 flats plan at Pottery Lane site
1 day ago

Winners named for £260m Manchester Uni framework

B&K, Henry Bros, Graham, Robertson and Vinci among new line-up
2 days ago

Shed specialist Benniman rides out market lull

Worcestershire warehouse builder says industrial and logistics work is picking up again
1 day ago

Another contractor cleared after high profile immigration raid

Adana Construction employees were working legally on site swooped on by Home Office
1 day ago

McAleer & Rushe wants to meet new London suppliers

Contractor holding Meet the Buyer event in London: Register now
2 days ago

McAlpine signs £500m Broadgate dual towers deal

Work to start on iconic 36-storey and 21-storey towers
2 days ago

Worker rescued from collapsed four metre deep trench

Fire crews take six hours to save trapped builder near Blackwall Tunnel
3 days ago

Gove puts another major building scheme on hold

Secretary of State starts another planning fight after M&S defeat
3 days ago

Greenwich University tenders £300m framework

Up to five firms will carry out upgrade and newbuild work at three campuses
3 days ago

Work starts on Manchester 26-storey Obsidian tower

Contractor Domis starts Salboy's 10th Manchester scheme in seven years
2 days ago

Race for £1.3bn West Midlands social homes framework

The Community Housing Group reboots tender race for new build housing
2 days ago

Delancey submits £400m King’s Cross lab plans

200,000 sq ft lab/office project will be built above railway and tube tunnels just 4.5m below
3 days ago

Winners revealed for £150m fire safety framework

New deal will help organisations comply with the Building Safety Act
3 days ago

Sellar plans £500m City tower next to Walkie-Talkie

Consultation starts on London 60 Gracechurch Street tower
3 days ago

Severfield ends year on high with record order book

Orders top £500m with strong future pipeline of opportunities ahead
4 days ago

Second senior director exits National Highways

Commercial director Malcolm Dare set to move on to new role
4 days ago

New scheme fuels London lab building boom

Plans in for 160,000 sq ft Whitechapel scheme near Royal London hospital
4 days ago

Contract race starts for next £155m section of A9 dualling

Prior Information Notice published for Tay Crossing to Ballinluig stretch
4 days ago

£55m Sheffield build-to-rent scheme approved

Demolition to start later this year for 158-flat Sheffield Garden project
4 days ago

London back as most expensive place to build in world

Capital leapfrogs Geneva to top costliest construction rankings
4 days ago

Gas supplier Regent to buy TClarke for £90m

£491m turnover listed building services specialist to be sold
5 days ago

Steel contractor Billington launches into bridge market

Steelwork firm hires staff from failed architectural and bridge specialist SH Structures
4 days ago

McGee employees benefit from rise in profits

Pre-tax profit doubles boosting payouts for Employee Ownership Trust
4 days ago

Lendlease veteran is latest new McAlpine director

Paul Sims joins as Operations Director after 40 years at rival contractor
5 days ago

Costain signs site labour supply deal with four firms

Contractor to use only a quartet of providers for temporary labour supply
5 days ago

BAM go-ahead for Leeds 200,000 sq ft office

Latitude Yellow will complete final plot at Doncaster Monk Bridge site
5 days ago

VolkerFitzpatrick wins £30m logistics job

Latest deal to build five distribution units for Prologis UK
5 days ago

Trio win new Scape utilities consultancy framework

Perfect Circle, AtkinsRéalis and Arcadis win places on
5 days ago

Precast firm FP McCann cleared after immigration raid

Home Office takes no action after public raid on construction site
6 days ago

Contractor services