Crossrail parts company with Costain Skanska at Bond Street

Grant Prior 5 years ago
Share

Costain/Skanska joint venture’s troubled Crossrail contract at Bond Street Station has been ended early.

Crossrail said the mutual decision was made “due to the volume of work remaining and the number of people required on site to complete the station” in a post-Covid world.

One site source told the Enquirer: “Word went around the job on Tuesday that this was happening and that Wednesday would be their last day.”

The Enquirer understands that Crossrail and the contractors were in discussions until midnight to agree terms of the split.

The problem job is the only one of ten central London Crossrail stations that is not yet ready for the trial running of trains.

Continued productivity issues on the site have seen it lag behind other stations.

Crossrail bosses hope to have the central section between Paddington and Abbey Wood finally up and running from summer 2021.

The £18bn project was originally due to open in December 2018.

The latest project update earlier this month said: “All central section stations, except Bond Street, have now been certified as ready to support Trial Running – Bond Street will be ready to support Trial Running by the end of July.”

The Costain/Skanska joint venture started work at Bond Street in February 2013 on a contract originally valued at £200m which was expected to be completed by February 2017.

A Crossrail Ltd spokesperson said: “In the light of Covid-19, we have been reviewing and re-structuring any works that are essential to opening the railway and to ensure we complete the Elizabeth line in the most effective and efficient way.

“This includes at Bond Street which is uniquely affected by the post-Covid world due to the volume of work remaining and the number of people required on site to complete the station.

“Over the last few weeks Crossrail Ltd has been in discussions with Costain Skanska Joint Venture (CSJV) to agree a way forward for Bond Street.

“As a result, Crossrail Ltd and CSJV have mutually agreed to conclude the existing contract as of midnight on 24 June and will work together to ensure a safe and effective transition. Crossrail Ltd will be putting in place new arrangements to complete the works which largely relate to fit-out and testing and commissioning activity.”

“Despite the significant challenges COVID-19 brings our focus remains on doing everything we can to open the central section between Paddington and Abbey Wood as soon as possible and the earliest possible opening for Bond Street.”

A CSJV spokesperson said: “In the light of COVID-19, Crossrail has been reviewing and re-structuring any works that are essential to opening the railway and to ensure it completes the Elizabeth line successfully.

“This includes at Bond Street which is uniquely affected by the COVID-19 crisis, due to the number of operatives required on site to complete the station.

“Crossrail will now consider plans for any future works in a post COVID-19 environment.

“As a result, Crossrail and CSJV have mutually agreed to conclude the joint venture’s works under the existing contract as of midnight on 24 June and will work together to mitigate costs and to ensure a safe and effective transition.”

Crossrail will complete the works in-house which largely relate to fit-out and testing and commissioning activity.

The Enquirer understands Engie are also now on site to carry-out “care and custody and security arrangements” at Bond Street.

CSJV continues to work with Crossrail as main contractor at Paddington where arrangements are unchanged.

 

 

Latest news

Van Elle finds buyer for loss-making Canadian arm

Two-year North America foray ends with £2.6m exit deal
4 hours ago

£100m student halls to replace derelict London Crown Court

IQ student project gets go-ahead at Blackfriars court building site
4 hours ago

Safety green light for Newcastle student scheme

Gateway 2 approval process delays construction start by a year
4 hours ago

Bachy turnover sinks by over £100m as HS2 surge fades

Piling specialist reports slow year as mega projects step down
3 hours ago

Plans go in for next phase of Manchester Waters

New neighbourhood planned for island site
3 hours ago

Cardo nails £52m Sussex council homes roofing deal

Firm beats 14 rivals to take Lewes and Eastbourne roofing programmes
4 hours ago

JRL names new fit-out lead to drive expansion

Graham Ardley steps up to drive next phase of commercial and residential growth
4 hours ago

Construction output yo-yos as growth falters again

Quarterly output down 0.3% amid cautious investor sentiment
3 days ago

Free school build plans axed to fund £3bn SEND expansion

Education secretary scraps 28 free schools to plug SEND shortfall
3 days ago

McLaren seals £160m funding for Manchester student tower

737-bed Upper Brook Street student scheme forward funded by L&G
3 days ago

Former McAlpine boss lined up for Royal BAM board role

Paul Hamer to replace Paul Sheffield on Dutch group supervisory board
4 days ago

Plans go in for £650m retail park to resi scheme

Construction could start in early 2027 on new neighbourhood for Lewisham
4 days ago

Lovell launches Midlands refurb division

Renew Central to be headed by Carl Yale
3 days ago

M Group muscles into top five contractors after growth spurt

Private-equity backed infra giant builds £8.8bn work mountain
4 days ago

Plans in for first major build phase of £2bn York Central scheme

Developers table plans for nearly 1,000 homes, parkland and York’s new western station gateway
4 days ago

Lords push for staged Gateway 2 approval to aid design and build

Inquiry warns BSR’s over-detailed Gateway 2 demands are freezing D&B process
4 days ago

CITB wage bill tops £52m as staff numbers jump 13%

Accounts show 182 people at training body earn £60,000+ a year
4 days ago

Peterborough electrical specialist files administration notice

EML Electrical Contractors lodges court notice
4 days ago

Ant Yapi UK lands latest Chelsea Barracks deal

Fit-out work on Building 7 will last until summer 2027
4 days ago

Go-ahead for plan to level Cambridge retail park for life-science hub

Minister overturns council refusal as Railpen’s scheme promises £600m economic uplift
5 days ago

Subcontractor competition keeps build costs flat at Berkeley

"Highly competitive tendering" expected to continue next year
5 days ago

Industry calls grow to scrap the CITB

Latest training cuts final straw for a lot of contractors
6 days ago

Green light for major Oxford Circus mixed use scheme

Construction to start in 2029 on revamp of BHS and London College of Fashion site
5 days ago

Coventry to back build of Very Light Rail street pilot

Council set to approve 800m twin-track route in push for rapid-build transport revolution
5 days ago

Willmott Dixon on blocks for £35m Surrey leisure centre

Cranleigh leisure centre will be the third in the UK built to Passivhaus-standard
6 days ago

Benniman bags latest DIRFT next-gen logistics job

DC11 shed to raise sustainability bar at rail-linked logistics park
6 days ago

Vinci wins funding sign-off to begin main £70m St Helens rebuild

Early 2026 start confirmed as council signs off biggest investment in decades
6 days ago

£175m Trafford Stretford Mall resi job out to bid

Trafford Council starts hunt for contractor for 249-home first phase
6 days ago

CITB cuts more training funds despite £79m cash pile

Training body imposes another round of sudden cuts on contractors
7 days ago

Mace design director joins McLaren

Lucy Craig appointed design director at Construction Management and Specialist Projects division
6 days ago