Crossrail parts company with Costain Skanska at Bond Street

Grant Prior 4 years ago
Share

Costain/Skanska joint venture’s troubled Crossrail contract at Bond Street Station has been ended early.

Crossrail said the mutual decision was made “due to the volume of work remaining and the number of people required on site to complete the station” in a post-Covid world.

One site source told the Enquirer: “Word went around the job on Tuesday that this was happening and that Wednesday would be their last day.”

The Enquirer understands that Crossrail and the contractors were in discussions until midnight to agree terms of the split.

The problem job is the only one of ten central London Crossrail stations that is not yet ready for the trial running of trains.

Continued productivity issues on the site have seen it lag behind other stations.

Crossrail bosses hope to have the central section between Paddington and Abbey Wood finally up and running from summer 2021.

The £18bn project was originally due to open in December 2018.

The latest project update earlier this month said: “All central section stations, except Bond Street, have now been certified as ready to support Trial Running – Bond Street will be ready to support Trial Running by the end of July.”

The Costain/Skanska joint venture started work at Bond Street in February 2013 on a contract originally valued at £200m which was expected to be completed by February 2017.

A Crossrail Ltd spokesperson said: “In the light of Covid-19, we have been reviewing and re-structuring any works that are essential to opening the railway and to ensure we complete the Elizabeth line in the most effective and efficient way.

“This includes at Bond Street which is uniquely affected by the post-Covid world due to the volume of work remaining and the number of people required on site to complete the station.

“Over the last few weeks Crossrail Ltd has been in discussions with Costain Skanska Joint Venture (CSJV) to agree a way forward for Bond Street.

“As a result, Crossrail Ltd and CSJV have mutually agreed to conclude the existing contract as of midnight on 24 June and will work together to ensure a safe and effective transition. Crossrail Ltd will be putting in place new arrangements to complete the works which largely relate to fit-out and testing and commissioning activity.”

“Despite the significant challenges COVID-19 brings our focus remains on doing everything we can to open the central section between Paddington and Abbey Wood as soon as possible and the earliest possible opening for Bond Street.”

A CSJV spokesperson said: “In the light of COVID-19, Crossrail has been reviewing and re-structuring any works that are essential to opening the railway and to ensure it completes the Elizabeth line successfully.

“This includes at Bond Street which is uniquely affected by the COVID-19 crisis, due to the number of operatives required on site to complete the station.

“Crossrail will now consider plans for any future works in a post COVID-19 environment.

“As a result, Crossrail and CSJV have mutually agreed to conclude the joint venture’s works under the existing contract as of midnight on 24 June and will work together to mitigate costs and to ensure a safe and effective transition.”

Crossrail will complete the works in-house which largely relate to fit-out and testing and commissioning activity.

The Enquirer understands Engie are also now on site to carry-out “care and custody and security arrangements” at Bond Street.

CSJV continues to work with Crossrail as main contractor at Paddington where arrangements are unchanged.

 

 

Latest news

Go-ahead for City of London’s tallest tower

1 Undershaft building will equal the Shard in height
2 days ago

Construction T Level scrapped due to lack of demand

Courses canned after less than 100 sign-up for latest round
3 days ago

Five firms clinch £300m Greenwich Uni framework deal

McLaren, Wates, Morgan Sindall, Vinci and Willmott Dixon secure places
2 days ago

Hill Group strikes first Build to Rent deal

House builder agrees finance with Lloyds Living to start Stevenage scheme
2 days ago

Construction output hit by fall in repair and maintenance

Industrial and commercial new work grows despite wider fall in activity
2 days ago

Wates transfers pension scheme to “superfund”

Pension management specialist Clara to take charge of £210m fund
2 days ago

Muse hires new development director for North West

Tom Darby joins from developer Bruntwood
2 days ago

Bid rigging probe launched into school repair work

Firms raided this week with focus on roofing contracts
4 days ago

McLaren hires ex-ISG regional boss for north east expansion

Andrew Beaumont becomes MD of new Yorkshire and North East business
3 days ago

Government commits to four new prisons in seven years

£2.3bn pledged for new prison build programme
4 days ago

Road and rail delays hit revenue at Van Elle

Turnover drops 5% as markets remain challenging for piling specialist
3 days ago

Boot reports ‘noticeable improvement’ in planning system

Government planning reforms already unblocking council planning
3 days ago

Go-ahead to revamp former London city hall

Project will straighten the building's leaning profile with terraces to every level
3 days ago

United Living to divert Midlands gas pipeline

600m pipeline diversion clears way for M54 to M6 link road construction
3 days ago

Credit insurance saves Billington from ISG hit

Steel specialist puts on extra shifts at its plants to cope with demand
4 days ago

M&E specialist Dodd doubles profit on retrofit surge

Family-owned Telford specialist delivers record revenue of nearly £250m
4 days ago

Go-ahead for 800-home Croydon dual towers

One Lansdowne Road build to rent scheme to cost £260m to build
4 days ago

Construction inflation set to return raising tender prices

End of 2024 to mark the bottom of present inflationary trough
4 days ago

Start date for vast Balfour and Costain carbon capture power job

£4bn Teesside project to start construction next year creating 3,000 jobs
5 days ago

Plans go in to start revamp of North Finchley town centre

Developer Regal unveils first details of Barnet masterplan
4 days ago

Glencar bags £18m Big Yellow London store

Six-storey stoarage centre to be built at Staples Corner
4 days ago

Plan unveiled for 31-storey London Fenchurch Street tower

Demolition work to start in 2026 for new office tower
5 days ago

Vinci Building buys tower cranes for first time

Contractor invests in two WOLFFKRAN all-electric cranes at £138m Sheffield site
5 days ago

30 local firms land United Utilities £500m framework

Minor works deal win for North West civils and M&E specialists
5 days ago

Restructure pays off as Higgins returns to profit

Housing contractor recovers from £25.9m loss last year
5 days ago

Former Heathrow boss joins Mace in board rejig

Firm completes string NED appointments to expanded group board
6 days ago

Planning officers to get powers to bypass committee stage for housing

Rayner reform plan to cut out local council planning committees
6 days ago

National Insurance hike to delay construction recovery

Arcadis paints varied picture with full recovery delayed until 2026
6 days ago

Gratte Bros rides out cost rises with profit increase

M&E specialist warns of further upward pressure on wage costs
6 days ago

Sellar’s 36-storey London City office tower approved

Demolition work to start in 2026 at 60 Gracechurch Street site
1 week ago

Contractor services