Crossrail parts company with Costain Skanska at Bond Street

Grant Prior 4 years ago
Share

Costain/Skanska joint venture’s troubled Crossrail contract at Bond Street Station has been ended early.

Crossrail said the mutual decision was made “due to the volume of work remaining and the number of people required on site to complete the station” in a post-Covid world.

One site source told the Enquirer: “Word went around the job on Tuesday that this was happening and that Wednesday would be their last day.”

The Enquirer understands that Crossrail and the contractors were in discussions until midnight to agree terms of the split.

The problem job is the only one of ten central London Crossrail stations that is not yet ready for the trial running of trains.

Continued productivity issues on the site have seen it lag behind other stations.

Crossrail bosses hope to have the central section between Paddington and Abbey Wood finally up and running from summer 2021.

The £18bn project was originally due to open in December 2018.

The latest project update earlier this month said: “All central section stations, except Bond Street, have now been certified as ready to support Trial Running – Bond Street will be ready to support Trial Running by the end of July.”

The Costain/Skanska joint venture started work at Bond Street in February 2013 on a contract originally valued at £200m which was expected to be completed by February 2017.

A Crossrail Ltd spokesperson said: “In the light of Covid-19, we have been reviewing and re-structuring any works that are essential to opening the railway and to ensure we complete the Elizabeth line in the most effective and efficient way.

“This includes at Bond Street which is uniquely affected by the post-Covid world due to the volume of work remaining and the number of people required on site to complete the station.

“Over the last few weeks Crossrail Ltd has been in discussions with Costain Skanska Joint Venture (CSJV) to agree a way forward for Bond Street.

“As a result, Crossrail Ltd and CSJV have mutually agreed to conclude the existing contract as of midnight on 24 June and will work together to ensure a safe and effective transition. Crossrail Ltd will be putting in place new arrangements to complete the works which largely relate to fit-out and testing and commissioning activity.”

“Despite the significant challenges COVID-19 brings our focus remains on doing everything we can to open the central section between Paddington and Abbey Wood as soon as possible and the earliest possible opening for Bond Street.”

A CSJV spokesperson said: “In the light of COVID-19, Crossrail has been reviewing and re-structuring any works that are essential to opening the railway and to ensure it completes the Elizabeth line successfully.

“This includes at Bond Street which is uniquely affected by the COVID-19 crisis, due to the number of operatives required on site to complete the station.

“Crossrail will now consider plans for any future works in a post COVID-19 environment.

“As a result, Crossrail and CSJV have mutually agreed to conclude the joint venture’s works under the existing contract as of midnight on 24 June and will work together to mitigate costs and to ensure a safe and effective transition.”

Crossrail will complete the works in-house which largely relate to fit-out and testing and commissioning activity.

The Enquirer understands Engie are also now on site to carry-out “care and custody and security arrangements” at Bond Street.

CSJV continues to work with Crossrail as main contractor at Paddington where arrangements are unchanged.

 

 

Latest news

Vistry to make £800m profit after subcontractor cost cuts

House builder bullish about shareholder returns after asking suppliers for discounts
18 hours ago

Shareholders approve £2.5bn Barratt and Redrow merger

Final hurdle is for the competition regulator to approve the deal.
18 hours ago

Green light for £80m Leith waterfront revamp

Build-to-rent homes and student accommodation scheme to be built
18 hours ago

Tilbury Douglas clears Interserve legacy jobs to return to profit

Revenue tops £500m in first year as standalone contractor
2 days ago

Land deal paves way for Manchester civil service office hub

Government buys five acres at former Central Retail Park
17 hours ago

Speller Metcalfe wins Wolverhampton library upgrade

Full works are due to start in the autumn
17 hours ago

Skills shortage puts big infrastructure projects at risk

Government failing as an intelligent client and now over-reliant on consultancies
2 days ago

Contractors face further insulation board price hikes

Cost of PIR insulation boards set to rise another 10%
2 days ago

Henry Boot wins £36m Rotherham Markets job

Project involves upgrading existing market and building a new library
2 days ago

Keltbray hires new head of infrastructure procurement

Lukasz Olszewski will oversee rail, energy and highways business units
2 days ago

Tunnel fit out robot to revolutionise civils work

Costain and VVB Engineering part of innovative consortium
2 days ago

Funding deal for £86m wind turbine test centre

Latest investment at National Renewable Energy Centre in Blyth
2 days ago

Plan in for Manchester ‘upside-down’ 18-storey tower

Landmark cantilevered NXQ building plan for city Northern Quarter
3 days ago

London 25km Super Sewer hooked up for commissioning

Tideway completes connection to existing Lee Tunnel sewer system
3 days ago

£200m Lincoln ring-road approved

North Hykeham Relief Road granted planning permission
3 days ago

£1bn Manchester Airport City plan rebooted as new sci-tech hub

Plan pivots from offices to science and manufacturing campus, called MIX Manchester
4 days ago

Record results at maintenance specialist Renew

Infrastructure maintenance work continues to pay off for contractor
3 days ago

Barhale lands £21m shaft scheme for Thames Water

Civils specialist bags latest upgrade deal on Thames Water Ring Main
3 days ago

Caddick names new north east director

Former Laing O'Rourke project lead joins Yorkshire contractor
3 days ago

Mount Anvil wins London Camden estate rebuild

Deverloper wins £133m Bacton Phase 2 development in Gospel Oak
4 days ago

London Met Uni seeks firm for £280m estate upgrade

A single partner contractor will deliver 10-year building upgrade plan
4 days ago

Top 30 M&E contractors set for growth – ranking

Growth in data centres and commercial refits creates optimism for year ahead
4 days ago

Race starts for £17m Leicester station redevelopment

City Council aims to restore historic Victoria building
4 days ago

Plant bosses blast “inflexible” police over road bans

Officers spotted outside sites and depots monitoring movements of large kit
7 days ago

Waterproofing firm Pudlo rescued from administration

New owners take on business while sister firm Cemfree sold to SigmaRoc
4 days ago

Construction recovery rained-off in first quarter

Sharp rise in commercial orders offers hope for Summer recovery
7 days ago

Skanska tops April contract wins ranking

London office and data centre projects lift Skanska
7 days ago

Modular builder TopHat managing director departs

Andrew Shepherd leaves Goldman-Sachs backed volumetric business
1 week ago

Balfour wins major Rolls-Royce Derby campus expansion

Masterplan involving 14 building projects will take eight years to complete
7 days ago

Graham nets £60m stands revamp at Lord’s

Construction to start this summer at the home of cricket
1 week ago

Contractor services