Laing O’Rourke completes first HS2 bridge in two days

Grant Prior 4 years ago
Share

Laing O’Rourke joint venture LM has completed the installation of a 65-metre bridge over the M42, in just two days forming the first permanent structure to be delivered for HS2.

The job was carried out by engineering specialist Expanded, working on behalf of HS2 enabling works contractor, LMJV (Laing O’Rourke and J. Murphy & Sons Joint Venture).

The 2,750 tonne bridge structure was carried along the motorway on a self-propelled modular transporter.

The 448-wheel transporter took just one hour and 45 minutes to move the bridge span 150 metres into position, where it was affixed to a composite concrete deck to complete the overall bridge structure.

The successful installation marks the completion of the first of four bridges to be built close to the new Interchange Station at Solihull.

It will form part of the major remodelling of the regional road network to improve the circulation of traffic around the HS2 railway line and connect the existing road network to the new Interchange Station.

Mark Thurston, HS2 Ltd’s CEO said: “This new road bridge is the first permanent structure to be installed along the route of Britain’s new railway, so today represents an important milestone for the project and the West Midlands region.

“Constructing the bridge off site and using innovative engineering practices to install it over the motorway enabled us to carry out the work in just two days, keeping disruption to a minimum for road users”.

Simon Russell, LM project director, said: “This is British construction design and engineering innovation at its finest.

“Major components of the bridge and its supports were built offsite under safe, high quality conditions, then transported to site for assembly.

“Advanced digital capabilities allowed us to design all elements of the structure in a virtual world, before building it for real.”

The new road bridge over the M42 was built using a Design for Manufacture and Assembly (DfMA) strategy.

Expanded Structures led the construction programme on site, with 1,610 tonnes of precast and insitu concrete delivered, including 115 modular abutment shells and 298 precast deck components.

These major structural elements of the bridge supports and deck were made at Laing O’Rourke’s Centre for Modern Construction (formerly EIP) in Nottinghamshire.

Regional supplier Cleveland Bridge supplied 1,130 tonnes of steel plate girders.

Peter Lyons, Business Unit Leader, Expanded, said: “Offsite manufacturing and modular construction offer substantial benefits in terms of greater efficiency, higher quality, safety, and reduced time on site and disruption to local communities and road users.

“By delivering factory made components and assembling them on site, we have constructed abutment walls in 5 days, compared to between 8-12 weeks for traditional methods, achieved with a site team averaging just eight operatives.”

Later this year, a similar operation will take place to position a bridge over the A446, also as part of remodelling of road networks around the future Interchange Station.

The LM team will also be installing two further bridges which will span the high-speed line itself.

 

 

Latest news

Go-ahead for City of London’s tallest tower

1 Undershaft building will equal the Shard in height
23 hours ago

Construction T Level scrapped due to lack of demand

Courses canned after less than 100 sign-up for latest round
2 days ago

Five firms clinch £300m Greenwich Uni framework deal

McLaren, Wates, Morgan Sindall, Vinci and Willmott Dixon secure places
1 day ago

Hill Group strikes first Build to Rent deal

House builder agrees finance with Lloyds Living to start Stevenage scheme
1 day ago

Construction output hit by fall in repair and maintenance

Industrial and commercial new work grows despite wider fall in activity
1 day ago

Wates transfers pension scheme to “superfund”

Pension management specialist Clara to take charge of £210m fund
1 day ago

Muse hires new development director for North West

Tom Darby joins from developer Bruntwood
1 day ago

Bid rigging probe launched into school repair work

Firms raided this week with focus on roofing contracts
3 days ago

McLaren hires ex-ISG regional boss for north east expansion

Andrew Beaumont becomes MD of new Yorkshire and North East business
2 days ago

Government commits to four new prisons in seven years

£2.3bn pledged for new prison build programme
3 days ago

Road and rail delays hit revenue at Van Elle

Turnover drops 5% as markets remain challenging for piling specialist
2 days ago

Boot reports ‘noticeable improvement’ in planning system

Government planning reforms already unblocking council planning
2 days ago

Go-ahead to revamp former London city hall

Project will straighten the building's leaning profile with terraces to every level
3 days ago

United Living to divert Midlands gas pipeline

600m pipeline diversion clears way for M54 to M6 link road construction
2 days ago

Credit insurance saves Billington from ISG hit

Steel specialist puts on extra shifts at its plants to cope with demand
3 days ago

M&E specialist Dodd doubles profit on retrofit surge

Family-owned Telford specialist delivers record revenue of nearly £250m
3 days ago

Go-ahead for 800-home Croydon dual towers

One Lansdowne Road build to rent scheme to cost £260m to build
3 days ago

Construction inflation set to return raising tender prices

End of 2024 to mark the bottom of present inflationary trough
3 days ago

Start date for vast Balfour and Costain carbon capture power job

£4bn Teesside project to start construction next year creating 3,000 jobs
4 days ago

Plans go in to start revamp of North Finchley town centre

Developer Regal unveils first details of Barnet masterplan
3 days ago

Glencar bags £18m Big Yellow London store

Six-storey stoarage centre to be built at Staples Corner
3 days ago

Plan unveiled for 31-storey London Fenchurch Street tower

Demolition work to start in 2026 for new office tower
4 days ago

Vinci Building buys tower cranes for first time

Contractor invests in two WOLFFKRAN all-electric cranes at £138m Sheffield site
4 days ago

30 local firms land United Utilities £500m framework

Minor works deal win for North West civils and M&E specialists
4 days ago

Restructure pays off as Higgins returns to profit

Housing contractor recovers from £25.9m loss last year
4 days ago

Former Heathrow boss joins Mace in board rejig

Firm completes string NED appointments to expanded group board
5 days ago

Planning officers to get powers to bypass committee stage for housing

Rayner reform plan to cut out local council planning committees
5 days ago

National Insurance hike to delay construction recovery

Arcadis paints varied picture with full recovery delayed until 2026
5 days ago

Gratte Bros rides out cost rises with profit increase

M&E specialist warns of further upward pressure on wage costs
5 days ago

Sellar’s 36-storey London City office tower approved

Demolition work to start in 2026 at 60 Gracechurch Street site
1 week ago

Contractor services