Crossrail delayed again until 2022 as costs top £19bn

Grant Prior 3 years ago
Share

Crossrail bosses have confirmed the project will not now be ready until 2022 at the earliest and total costs have broken the £19bn barrier.

The latest update comes as the Crossrail Board said: “Delivery of the Elizabeth line is now in its complex final stages and is being completed at a time of great uncertainty due to the risks and potential impacts of further Covid outbreaks.”

The board said the central section between Paddington and Abbey Wood will be ready to open in “the first half of 2022.”

The line was originally due to open in December 2018.

Latest budget estimates show that the cost to complete the project could be up to £1.1bn above the latest agreed finance package taking the total beyond £19bn.

Crossrail said it is planning to start intensive operational testing “at the earliest opportunity in 2021.”

The board blamed the latest delays on:

  • Routeway: we have had lower than planned productivity in the final completion and handover of the shafts and portals. The shafts and portals form a critical part of the routeway and contain many of the complex operating systems for the Elizabeth line. We have now completed handover of eight of the ten shafts and portals to TfL and will complete handover of the final two this autumn.
  • Stations: as more detailed plans for the completion and handover of the ten central section stations have developed, we have revised our previous schedule assumptions about the pace at which these large and complex stations can be handed over to TfL. The completion and handover of all the stations in the central section is a monumental task – in our updated plan we have phased the transfer of stations to take account the scale of this undertaking.
  • COVID-19: Covid has further exacerbated the schedule pressures due to a pause of physical activity on sites during lockdown to keep the workforce safe and significant constraints on ongoing work and productivity due to the reduced numbers that can work on site to meet strict social distancing requirements. We now have a maximum of around 2,000 people on our sites, less than 50 per cent of our pre-Covid complement.

Crossrail said it is undertaking “a period of intensive construction activity during August and September to complete the remaining construction works in the routeway for Trial Running.”

Mark Wild, Chief Executive, Crossrail Ltd, said: “Our focus remains on opening the Elizabeth line as soon as possible. Now more than ever Londoners are relying on the capacity and connectivity that the Elizabeth line will bring, and we are doing everything possible to deliver the railway as safely and quickly as we can.

“We have a comprehensive plan to complete the railway and we are striving to commence intensive operational testing for the Elizabeth line, known as Trial Running, at the earliest opportunity.

“Delivery of the Elizabeth line is now in its complex final stages and is being completed at a time of great uncertainty due to the risk and potential impacts of further Covid outbreaks.

“We are working tirelessly to complete the remaining infrastructure works so that we can fully test the railway and successfully transition the project as an operational railway to Transport for London.”

Andy Byford, London’s Transport Commissioner, said: “It is very disappointing to receive confirmation from Crossrail Ltd that their plan for opening the Elizabeth Line now has a date of the first half of 2022.

“The line will transform travel across London and is vital to supporting jobs, homes and businesses across the capital. I will now work with my team and the DfT to review Crossrail’s plans.

“I have been very clear that I am committed to getting this railway open safely and reliably as quickly as possible for the benefit of London and beyond.”

Latest news

Lonsdale went down owing £65m to supply chain

More than 600 firms owed money as reduced credit rating sinks M&E giant
2 days ago

Wates only bidder for £80m Cardiff estate rebuild

Council contacted 20 framework firms but received only one bid for 295-home Channel View estate rebuild
2 days ago

£21m legal battle over flawed concrete at Salford flats job

Developer in compensation battle with Arcadis after new concrete core demolished
2 days ago

Abu Dhabi developer Aldar Properties buys London Square

UAE giant swoops on resi specialist in vote of confidence for London market
2 days ago

Hunt for delivery partner to revive New Hospital Programme

Programme delivery partner to get £600m fee to get plans back on track
3 days ago

Green light for new £780m Essex garden village

3,700 homes and four new schools to be built at Dunton Hills
3 days ago

Laing O’Rourke makes a £288m loss

Rampant inflation on fixed-price jobs and problem contracts blow hole in accounts
3 days ago

Keltbray, OCU and Clancy clinch £1bn electricity network upgrade

Scottish and Southern Electricity Networks awards biggest ever deals for central southern England
4 days ago

G&T enlisted for commercial review of HS2 main civils contracts

Phase 1 Main Works Civils Contracts to come under cost scrutiny
3 days ago

TClarke order books doubles to top £1bn for first time

M&E specialist on track to exceed £500m turnover this year
3 days ago

Wates signs Government safety remediation pact

Private builder belatedly signs fire safety developer remediation contract
3 days ago

Liverpool all-electric industrial park approved

McLaren and Caddick in chase for Sefton 800,000 sq ft Atlantic Park scheme
3 days ago

Former Buckingham Group MD to join John F Hunt

Simon Hyams is new Managing Director for Contracting
4 days ago

Three in race for retendered £150m A9 dualling job

Bidders take another look after client takes on more risk
4 days ago

Clancy tops £300m revenue in fifth year of growth

Civils contractor delivers £13.5m pre-tax from water and energy sector work
4 days ago

Tower crane collapses on Edinburgh resi site

Jib falls onto apartment block under construction: Video
5 days ago

Salboy drops office space from Viadux Phase Two

Developer to focus on Manchester residential towers of 76 and 23 storeys
5 days ago

Warwick Uni plan for science and engineering campus

370,000 sq ft science and engineering precinct submitted for planning
4 days ago

Morgan Sindall chalks up Greater Manchester schools treble

Bury, Stockport and Wythenshawe school jobs will create 1,600 pupil places
4 days ago

Plans in for £65m Blackpool multiversity campus

Council leads plan for Talbot Gateway learning campus
4 days ago

Laing O’Rourke wins first phase of £700m Oxford R&D district

Landmark Red Hall and two labs to be built in phase 1a of Oxford North scheme
6 days ago

Ardmore wins retrofit deal on £200m Chancery Lane office

Building will be transformed to provide 105,637 sq ft of office space
6 days ago

Construction’s “Leading Lights” recognised

More than 50 winners in latest Considerate Constructors Scheme awards
5 days ago

Balfour Beatty clinches £20m Norfolk coastal defence jobs

Firm will install rock armour at Cromer and Mundesley
5 days ago

Architects join construction union Unite

Section of Architectural Workers forms official branch
6 days ago

Boot to build £20m lightweight aviation composites factory

Work starts on Sheffield University's COMPASS R&D facility
5 days ago

GMI secures £27m Leeds City College job

Site clearance underway for new Mabgate campus
6 days ago

Balfour signs deal with Koreans for UK power transmission jobs

Contractor strengthens large-scale onshore power transmission capability
6 days ago

36 storey south London build to rent flats tower approved

Construction to start next year on £220m Croydon scheme
6 days ago

Hunt for firms for £400m volumetric offsite deal

Procurement for Housing aims to expand its pool of firms on major offsite framework
6 days ago

Contractor services