Crossrail delayed again until 2022 as costs top £19bn

Grant Prior 4 years ago
Share

Crossrail bosses have confirmed the project will not now be ready until 2022 at the earliest and total costs have broken the £19bn barrier.

The latest update comes as the Crossrail Board said: “Delivery of the Elizabeth line is now in its complex final stages and is being completed at a time of great uncertainty due to the risks and potential impacts of further Covid outbreaks.”

The board said the central section between Paddington and Abbey Wood will be ready to open in “the first half of 2022.”

The line was originally due to open in December 2018.

Latest budget estimates show that the cost to complete the project could be up to £1.1bn above the latest agreed finance package taking the total beyond £19bn.

Crossrail said it is planning to start intensive operational testing “at the earliest opportunity in 2021.”

The board blamed the latest delays on:

  • Routeway: we have had lower than planned productivity in the final completion and handover of the shafts and portals. The shafts and portals form a critical part of the routeway and contain many of the complex operating systems for the Elizabeth line. We have now completed handover of eight of the ten shafts and portals to TfL and will complete handover of the final two this autumn.
  • Stations: as more detailed plans for the completion and handover of the ten central section stations have developed, we have revised our previous schedule assumptions about the pace at which these large and complex stations can be handed over to TfL. The completion and handover of all the stations in the central section is a monumental task – in our updated plan we have phased the transfer of stations to take account the scale of this undertaking.
  • COVID-19: Covid has further exacerbated the schedule pressures due to a pause of physical activity on sites during lockdown to keep the workforce safe and significant constraints on ongoing work and productivity due to the reduced numbers that can work on site to meet strict social distancing requirements. We now have a maximum of around 2,000 people on our sites, less than 50 per cent of our pre-Covid complement.

Crossrail said it is undertaking “a period of intensive construction activity during August and September to complete the remaining construction works in the routeway for Trial Running.”

Mark Wild, Chief Executive, Crossrail Ltd, said: “Our focus remains on opening the Elizabeth line as soon as possible. Now more than ever Londoners are relying on the capacity and connectivity that the Elizabeth line will bring, and we are doing everything possible to deliver the railway as safely and quickly as we can.

“We have a comprehensive plan to complete the railway and we are striving to commence intensive operational testing for the Elizabeth line, known as Trial Running, at the earliest opportunity.

“Delivery of the Elizabeth line is now in its complex final stages and is being completed at a time of great uncertainty due to the risk and potential impacts of further Covid outbreaks.

“We are working tirelessly to complete the remaining infrastructure works so that we can fully test the railway and successfully transition the project as an operational railway to Transport for London.”

Andy Byford, London’s Transport Commissioner, said: “It is very disappointing to receive confirmation from Crossrail Ltd that their plan for opening the Elizabeth Line now has a date of the first half of 2022.

“The line will transform travel across London and is vital to supporting jobs, homes and businesses across the capital. I will now work with my team and the DfT to review Crossrail’s plans.

“I have been very clear that I am committed to getting this railway open safely and reliably as quickly as possible for the benefit of London and beyond.”

Latest news

Go-ahead for City of London’s tallest tower

1 Undershaft building will equal the Shard in height
2 days ago

Construction T Level scrapped due to lack of demand

Courses canned after less than 100 sign-up for latest round
3 days ago

Five firms clinch £300m Greenwich Uni framework deal

McLaren, Wates, Morgan Sindall, Vinci and Willmott Dixon secure places
2 days ago

Hill Group strikes first Build to Rent deal

House builder agrees finance with Lloyds Living to start Stevenage scheme
2 days ago

Construction output hit by fall in repair and maintenance

Industrial and commercial new work grows despite wider fall in activity
2 days ago

Wates transfers pension scheme to “superfund”

Pension management specialist Clara to take charge of £210m fund
2 days ago

Muse hires new development director for North West

Tom Darby joins from developer Bruntwood
2 days ago

Bid rigging probe launched into school repair work

Firms raided this week with focus on roofing contracts
4 days ago

McLaren hires ex-ISG regional boss for north east expansion

Andrew Beaumont becomes MD of new Yorkshire and North East business
3 days ago

Government commits to four new prisons in seven years

£2.3bn pledged for new prison build programme
4 days ago

Road and rail delays hit revenue at Van Elle

Turnover drops 5% as markets remain challenging for piling specialist
3 days ago

Boot reports ‘noticeable improvement’ in planning system

Government planning reforms already unblocking council planning
3 days ago

Go-ahead to revamp former London city hall

Project will straighten the building's leaning profile with terraces to every level
3 days ago

United Living to divert Midlands gas pipeline

600m pipeline diversion clears way for M54 to M6 link road construction
3 days ago

Credit insurance saves Billington from ISG hit

Steel specialist puts on extra shifts at its plants to cope with demand
4 days ago

M&E specialist Dodd doubles profit on retrofit surge

Family-owned Telford specialist delivers record revenue of nearly £250m
4 days ago

Go-ahead for 800-home Croydon dual towers

One Lansdowne Road build to rent scheme to cost £260m to build
4 days ago

Construction inflation set to return raising tender prices

End of 2024 to mark the bottom of present inflationary trough
4 days ago

Start date for vast Balfour and Costain carbon capture power job

£4bn Teesside project to start construction next year creating 3,000 jobs
5 days ago

Plans go in to start revamp of North Finchley town centre

Developer Regal unveils first details of Barnet masterplan
4 days ago

Glencar bags £18m Big Yellow London store

Six-storey stoarage centre to be built at Staples Corner
4 days ago

Plan unveiled for 31-storey London Fenchurch Street tower

Demolition work to start in 2026 for new office tower
5 days ago

Vinci Building buys tower cranes for first time

Contractor invests in two WOLFFKRAN all-electric cranes at £138m Sheffield site
5 days ago

30 local firms land United Utilities £500m framework

Minor works deal win for North West civils and M&E specialists
5 days ago

Restructure pays off as Higgins returns to profit

Housing contractor recovers from £25.9m loss last year
5 days ago

Former Heathrow boss joins Mace in board rejig

Firm completes string NED appointments to expanded group board
6 days ago

Planning officers to get powers to bypass committee stage for housing

Rayner reform plan to cut out local council planning committees
6 days ago

National Insurance hike to delay construction recovery

Arcadis paints varied picture with full recovery delayed until 2026
6 days ago

Gratte Bros rides out cost rises with profit increase

M&E specialist warns of further upward pressure on wage costs
6 days ago

Sellar’s 36-storey London City office tower approved

Demolition work to start in 2026 at 60 Gracechurch Street site
1 week ago

Contractor services