Crossrail delayed again until 2022 as costs top £19bn

Grant Prior 4 years ago
Share

Crossrail bosses have confirmed the project will not now be ready until 2022 at the earliest and total costs have broken the £19bn barrier.

The latest update comes as the Crossrail Board said: “Delivery of the Elizabeth line is now in its complex final stages and is being completed at a time of great uncertainty due to the risks and potential impacts of further Covid outbreaks.”

The board said the central section between Paddington and Abbey Wood will be ready to open in “the first half of 2022.”

The line was originally due to open in December 2018.

Latest budget estimates show that the cost to complete the project could be up to £1.1bn above the latest agreed finance package taking the total beyond £19bn.

Crossrail said it is planning to start intensive operational testing “at the earliest opportunity in 2021.”

The board blamed the latest delays on:

  • Routeway: we have had lower than planned productivity in the final completion and handover of the shafts and portals. The shafts and portals form a critical part of the routeway and contain many of the complex operating systems for the Elizabeth line. We have now completed handover of eight of the ten shafts and portals to TfL and will complete handover of the final two this autumn.
  • Stations: as more detailed plans for the completion and handover of the ten central section stations have developed, we have revised our previous schedule assumptions about the pace at which these large and complex stations can be handed over to TfL. The completion and handover of all the stations in the central section is a monumental task – in our updated plan we have phased the transfer of stations to take account the scale of this undertaking.
  • COVID-19: Covid has further exacerbated the schedule pressures due to a pause of physical activity on sites during lockdown to keep the workforce safe and significant constraints on ongoing work and productivity due to the reduced numbers that can work on site to meet strict social distancing requirements. We now have a maximum of around 2,000 people on our sites, less than 50 per cent of our pre-Covid complement.

Crossrail said it is undertaking “a period of intensive construction activity during August and September to complete the remaining construction works in the routeway for Trial Running.”

Mark Wild, Chief Executive, Crossrail Ltd, said: “Our focus remains on opening the Elizabeth line as soon as possible. Now more than ever Londoners are relying on the capacity and connectivity that the Elizabeth line will bring, and we are doing everything possible to deliver the railway as safely and quickly as we can.

“We have a comprehensive plan to complete the railway and we are striving to commence intensive operational testing for the Elizabeth line, known as Trial Running, at the earliest opportunity.

“Delivery of the Elizabeth line is now in its complex final stages and is being completed at a time of great uncertainty due to the risk and potential impacts of further Covid outbreaks.

“We are working tirelessly to complete the remaining infrastructure works so that we can fully test the railway and successfully transition the project as an operational railway to Transport for London.”

Andy Byford, London’s Transport Commissioner, said: “It is very disappointing to receive confirmation from Crossrail Ltd that their plan for opening the Elizabeth Line now has a date of the first half of 2022.

“The line will transform travel across London and is vital to supporting jobs, homes and businesses across the capital. I will now work with my team and the DfT to review Crossrail’s plans.

“I have been very clear that I am committed to getting this railway open safely and reliably as quickly as possible for the benefit of London and beyond.”

Latest news

Steel import delays make Rangers miss kick-off

Construction work at Ibrox will not be finished by start of next season
22 mins ago

Clients under spotlight after bond bombshell

Contractors call for action to avoid project delays
9 hours ago

Amey switches kit supplier to Speedy from HSS

New plant and equipment hire deal worth £25m a year
5 hours ago

M&E specialist Lorne Stewart falls into the red

Parent group suffers £2.8m loss in face of cost inflation and insolvencies
8 hours ago

Four men rushed to hospital after site accident

Eye-witnesses report a wall was knocked over on Edinburgh site
18 hours ago

World’s tallest scissor lift set for UK sites

Hire Safe Solutions partners with Dingli to supply lift with working height of 37 metres
8 hours ago

Barhale wins £36m East London sewer remediation

Northern Outfall Sewer in West Ham runs above railway lines in the city
8 hours ago

Weston Homes thumbs-up for £220m Essex homes scheme

Colchester 600-home Viridis scheme gains outline consent
9 hours ago

Balfour seals £192m deal for trio of Scottish substations

Work to start this summer to enhance electrical transmission in Argyll
1 day ago

Construction bond bombshell as major player quits market

QBE currently provides cover for 20 of the industry's 30 biggest contractors
1 day ago

United Utilities names another 18 winners for £2.7bn water spend

Water giant cuts out large management contractors in latest spending round
2 days ago

Green light for £130m Dundee Eden project

Former gasholder site to be transformed into green house
1 day ago

Four tower scheme in Glasgow gets green light

Go-ahead for major mixed-use scheme at Central Quay
1 day ago

‘Green collar’ construction workers earning £134,000

Cost consultant T&T says insulation and heat pump trades earning £70 an hour in London
1 day ago

£65m Trafford Waters resi blocks approved

X1 Developments plans over 200 homes in 13- and 8-storey blocks
1 day ago

Over 100 firms win £1.5bn ICN housing framework

Great Places Housing Group names key partners for new homes programme
2 days ago

Steelwork firm went down owing £4.5m to suppliers

Subcontractors left holding unpaid invoices from SH Structures
2 days ago

Scottish civils firm to buy stake in piling specialist

Advance Construction in talks for 25% stake in Northern Piling Ltd
2 days ago

RSK secures £500m for fresh acquisitions spree

Acquisitive group aims to buy another 200 businesses by 2030
3 days ago

Beal Homes gets green light for £105m Humber scheme

Work to start on more than 500 homes in North East Lincolnshire
2 days ago

RED wins £20m East London office refurb

Grade II listed Victorian building to be upgraded to Cat A offices
2 days ago

Employee-owned Neilcott staff share £250,000 payout

Employee-owned building contractor sales jump 38% to £139m
3 days ago

Geoffrey Osborne supply chain hit for £26m

More than 500 suppliers and subcontractors left holding unpaid bills
6 days ago

Race for £800m South West Wales framework

Up to 16 firms face fight to renew spots on regional contractors framework
4 days ago

SME contractors agree 4% pay rise for site workers

Workers will also get an extra day of holiday
6 days ago

South East expansion paying off for Meldrum Group

Turnover up to £55m as North East based contractor expands national coverage
3 days ago

Wates boosts paternity leave to 12 weeks

Latest leave benefits apply from first day of working for contractor
3 days ago

Taylor Wimpey chief honoured with CBE

Jennie Daly recognised in King's Birthday honours
5 days ago

Labour to mothball £320m A27 job to fix potholes

Manifesto confirms Arundel Bypass canned as "poor value for money"
6 days ago

Lendlease’s £1.9bn Smithfield Birmingham scheme approved

Initial work to start later this year despite questions over Lendlease's degree of involvement
6 days ago

Contractor services