Crossrail delayed again until 2022 as costs top £19bn

Grant Prior 4 years ago
Share

Crossrail bosses have confirmed the project will not now be ready until 2022 at the earliest and total costs have broken the £19bn barrier.

The latest update comes as the Crossrail Board said: “Delivery of the Elizabeth line is now in its complex final stages and is being completed at a time of great uncertainty due to the risks and potential impacts of further Covid outbreaks.”

The board said the central section between Paddington and Abbey Wood will be ready to open in “the first half of 2022.”

The line was originally due to open in December 2018.

Latest budget estimates show that the cost to complete the project could be up to £1.1bn above the latest agreed finance package taking the total beyond £19bn.

Crossrail said it is planning to start intensive operational testing “at the earliest opportunity in 2021.”

The board blamed the latest delays on:

  • Routeway: we have had lower than planned productivity in the final completion and handover of the shafts and portals. The shafts and portals form a critical part of the routeway and contain many of the complex operating systems for the Elizabeth line. We have now completed handover of eight of the ten shafts and portals to TfL and will complete handover of the final two this autumn.
  • Stations: as more detailed plans for the completion and handover of the ten central section stations have developed, we have revised our previous schedule assumptions about the pace at which these large and complex stations can be handed over to TfL. The completion and handover of all the stations in the central section is a monumental task – in our updated plan we have phased the transfer of stations to take account the scale of this undertaking.
  • COVID-19: Covid has further exacerbated the schedule pressures due to a pause of physical activity on sites during lockdown to keep the workforce safe and significant constraints on ongoing work and productivity due to the reduced numbers that can work on site to meet strict social distancing requirements. We now have a maximum of around 2,000 people on our sites, less than 50 per cent of our pre-Covid complement.

Crossrail said it is undertaking “a period of intensive construction activity during August and September to complete the remaining construction works in the routeway for Trial Running.”

Mark Wild, Chief Executive, Crossrail Ltd, said: “Our focus remains on opening the Elizabeth line as soon as possible. Now more than ever Londoners are relying on the capacity and connectivity that the Elizabeth line will bring, and we are doing everything possible to deliver the railway as safely and quickly as we can.

“We have a comprehensive plan to complete the railway and we are striving to commence intensive operational testing for the Elizabeth line, known as Trial Running, at the earliest opportunity.

“Delivery of the Elizabeth line is now in its complex final stages and is being completed at a time of great uncertainty due to the risk and potential impacts of further Covid outbreaks.

“We are working tirelessly to complete the remaining infrastructure works so that we can fully test the railway and successfully transition the project as an operational railway to Transport for London.”

Andy Byford, London’s Transport Commissioner, said: “It is very disappointing to receive confirmation from Crossrail Ltd that their plan for opening the Elizabeth Line now has a date of the first half of 2022.

“The line will transform travel across London and is vital to supporting jobs, homes and businesses across the capital. I will now work with my team and the DfT to review Crossrail’s plans.

“I have been very clear that I am committed to getting this railway open safely and reliably as quickly as possible for the benefit of London and beyond.”

Latest news

Wates wins former Daily Mail printworks transformation

British Land advances major cultural venue at London’s Canada Water
19 hours ago

Mace poaches Ramboll chief to be Head of Engineering

Martin Feakes will develop civil and structural engineering offer at Mace
19 hours ago

Subcontractors form alliance for major civils jobs

Trio of specialists join forces to collaborate and offer Tier 1 contractors a turnkey solution
23 hours ago

Fear of supply chain failures boosting collaboration

Procurement survey also reveals project bank account use is rising
22 hours ago

Wates sets up business to target 160,000 mouldy social homes

Healthy Homes service will be offered to social landlords across England
23 hours ago

Higgins wins £75m Peabody Passive House job

Latest phase of Deptford Landings to start construction
23 hours ago

Contractors and unions agree Sizewell C working deal

New deal offers improved sick pay and parental leave over Hinkley Point deal
1 day ago

Competition chiefs win legal fight for more construction raids

High Court rules CMA officials can raid a domestic property as part of investigation
2 days ago

More Osborne companies file administration notices

Three more divisions lodge notices with court
2 days ago

McLaren wins multi-storey urban logistics contract

South London win with British Land is pioneering urban logistics hub
2 days ago

Big social housing schemes at risk over funding uncertainty

Housing associations warn uncertainty over public funding beyond 2026 is curbing new schemes
2 days ago

Kier wins Worcestershire town centre renewal

Firm secures Bromsgrove commercial and cultural hub project
2 days ago

BAM signs Kent school contract at £42m

Sevenoaks school rebuild signed off at £8m more than first estimates
2 days ago

RG Group signs £121m Newcastle rental homes job

Developer Olympian Homes advances 519 flats plan at Pottery Lane site
5 days ago

Geoffrey Osborne files administration notice

Contractor in talks to save parts of the business
5 days ago

Winners named for £260m Manchester Uni framework

B&K, Henry Bros, Graham, Robertson and Vinci among new line-up
5 days ago

Shed specialist Benniman rides out market lull

Worcestershire warehouse builder says industrial and logistics work is picking up again
5 days ago

Another contractor cleared after high profile immigration raid

Adana Construction employees were working legally on site swooped on by Home Office
5 days ago

McAleer & Rushe wants to meet new London suppliers

Contractor holding Meet the Buyer event in London: Register now
5 days ago

McAlpine signs £500m Broadgate dual towers deal

Work to start on iconic 36-storey and 21-storey towers
6 days ago

Worker rescued from collapsed four metre deep trench

Fire crews take six hours to save trapped builder near Blackwall Tunnel
6 days ago

Gove puts another major building scheme on hold

Secretary of State starts another planning fight after M&S defeat
7 days ago

Greenwich University tenders £300m framework

Up to five firms will carry out upgrade and newbuild work at three campuses
6 days ago

Work starts on Manchester 26-storey Obsidian tower

Contractor Domis starts Salboy's 10th Manchester scheme in seven years
6 days ago

Race for £1.3bn West Midlands social homes framework

The Community Housing Group reboots tender race for new build housing
6 days ago

Delancey submits £400m King’s Cross lab plans

200,000 sq ft lab/office project will be built above railway and tube tunnels just 4.5m below
7 days ago

Winners revealed for £150m fire safety framework

New deal will help organisations comply with the Building Safety Act
6 days ago

Sellar plans £500m City tower next to Walkie-Talkie

Consultation starts on London 60 Gracechurch Street tower
7 days ago

Severfield ends year on high with record order book

Orders top £500m with strong future pipeline of opportunities ahead
7 days ago

Second senior director exits National Highways

Commercial director Malcolm Dare set to move on to new role
7 days ago

Contractor services