BAM to pull down entire frame of £65m building

Grant Prior 4 years ago
Share

BAM will have to demolish the entire structural frame of its Faculty of Social Sciences (FoSS) project for the University of Sheffield.

Recent project progress shot highlights how much frame will have to come down
Recent project progress shot highlights how much frame will have to come down

The main contractor announced in May that half the concrete frame will be dismantled following the discovery of piling problems on the £65m project.

But BAM has now confirmed that the partially-built structure will have to be completely torn down after starting partial demolition work last month.

The move has caused anger among local residents hit by the noise of demolition work.

BAM said: “We have concluded that the best solution is to deconstruct the entire building before re-building and have advised the residents that these works will conclude in October.

“Re-piling will be complete in early 2021, after which operations will be much quieter.

“We are doing what we can to offset this inconvenience and are restricting the times we are operating the concrete breaking machine which is the noisiest part of deconstruction.

“The technical difficulties that have led to the present situation are highly unusual.

“Everyone’s aim has been to create a building that the University and surrounding community will be proud of and that improves on what was there before.

“Ultimately we will achieve this, just later than originally planned, and will keep doing what we can to reduce disruption in the meantime.”

Main construction work started on the site in May 2019 after BAM replaced Kier who had signed a pre-construction deal for the project but failed to agree a final price with the university.

In its original statement in May BAM said: “BAM identified that there was settlement occurring in excess of that which would normally be expected in a structure of this nature, prompting us to conduct detailed investigations.

“These confirm a problem involving the piling of the structure, which are unusually complicated.

“We therefore conducted a review together with our client and the expert subcontractors involved: Mott Macdonald – structural engineers – and Cementation Skanska – piling contractor.

“This concluded the best course of action would be to partly dismantle some of the current structural frame – to the north elevation then rebuild it. Those works are now underway.”

Latest news

Construction T Level scrapped due to lack of demand

Courses canned after less than 100 sign-up for latest round
4 hours ago

Bid rigging probe launched into school repair work

Firms raided this week with focus on roofing contracts
1 day ago

McLaren hires ex-ISG regional boss for north east expansion

Andrew Beaumont becomes MD of new Yorkshire and North East business
13 hours ago

Government commits to four new prisons in seven years

£2.3bn pledged for new prison build programme
1 day ago

Road and rail delays hit revenue at Van Elle

Turnover drops 5% as markets remain challenging for piling specialist
12 hours ago

Boot reports ‘noticeable improvement’ in planning system

Government planning reforms already unblocking council planning
12 hours ago

Go-ahead to revamp former London city hall

Project will straighten the building's leaning profile with terraces to every level
20 hours ago

United Living to divert Midlands gas pipeline

600m pipeline diversion clears way for M54 to M6 link road construction
11 hours ago

Credit insurance saves Billington from ISG hit

Steel specialist puts on extra shifts at its plants to cope with demand
2 days ago

M&E specialist Dodd doubles profit on retrofit surge

Family-owned Telford specialist delivers record revenue of nearly £250m
1 day ago

Go-ahead for 800-home Croydon dual towers

One Lansdowne Road build to rent scheme to cost £260m to build
2 days ago

Construction inflation set to return raising tender prices

End of 2024 to mark the bottom of present inflationary trough
2 days ago

Start date for vast Balfour and Costain carbon capture power job

£4bn Teesside project to start construction next year creating 3,000 jobs
2 days ago

Plans go in to start revamp of North Finchley town centre

Developer Regal unveils first details of Barnet masterplan
2 days ago

Glencar bags £18m Big Yellow London store

Six-storey stoarage centre to be built at Staples Corner
1 day ago

Plan unveiled for 31-storey London Fenchurch Street tower

Demolition work to start in 2026 for new office tower
3 days ago

Vinci Building buys tower cranes for first time

Contractor invests in two WOLFFKRAN all-electric cranes at £138m Sheffield site
3 days ago

30 local firms land United Utilities £500m framework

Minor works deal win for North West civils and M&E specialists
3 days ago

Restructure pays off as Higgins returns to profit

Housing contractor recovers from £25.9m loss last year
3 days ago

Former Heathrow boss joins Mace in board rejig

Firm completes string NED appointments to expanded group board
3 days ago

Planning officers to get powers to bypass committee stage for housing

Rayner reform plan to cut out local council planning committees
3 days ago

National Insurance hike to delay construction recovery

Arcadis paints varied picture with full recovery delayed until 2026
4 days ago

Gratte Bros rides out cost rises with profit increase

M&E specialist warns of further upward pressure on wage costs
3 days ago

Sellar’s 36-storey London City office tower approved

Demolition work to start in 2026 at 60 Gracechurch Street site
5 days ago

Roofers caught using phone lights to work at night

Roofing boss handed suspended prison sentence for lack of edge protection
4 days ago

£380m North West housing framework out for bid

St Helens-based Torus aims to build 9,000 homes by 2029
4 days ago

Historic property magazine to close

Estates Gazette has been in business since 1858
6 days ago

M&S Marble Arch rebuild approved after three-year planning fight

Plans were delayed when Michael Gove backed carbon campaigners
1 week ago

£191m revamp funding approved for London Barbican Centre

Construction to start in 2027 on five-year programme
7 days ago

RED Construction tops £100m turnover

Builder maintains profit margin at 1.7% as business nearly doubles in size
7 days ago

Contractor services