M+W Group faces £133m claim over Hull energy plant

Aaron Morby 3 years ago
Share

Engineering contractor M&W Group is facing a £133m claim for the late delivery of a £200m green energy plant in Hull.

Hull energy plant at the centre of the court action
Hull energy plant at the centre of the court action

The legal battle has arisen after the group’s subsidiary MW High Tech Projects failed to meet targeted completion and saw its main contract terminated by client Energy Works Hull.

Both firms are now heading for the High Court with claims and counterclaims stemming from failure to deliver the project, termination of the main contract and assignment of a key subcontract package.

Client Energy Works Hull is claiming £133m to cover the cost of rectifying defects, delay damages and added costs to complete works.

MW disputes the claims and has counterclaimed for £46.7m based on the contractual provisions for payment following a termination for convenience.

MW won the contract to design, procure, construct, commission and test the fluidised bed gasification power plant back in November 2015.

It claims delays in commissioning stemmed from the client’s failure to provide refuse derived fuel (RDF) that was compliant with the contractual specification.

This delayed commissioning when the RDF was rejected by MW and led to the failure of commissioning when key subcontractor Outotec’s plant was damaged as a result of the non-compliant RDF.

It also claims that Outotec’splant was delivered late and was defective.

Details of the legal row emerged in a preliminary hearing covering legal points in the complex case.

Outotec’s work was assigned to the client when the main contract was terminated in March after MW failed to achieve targeted completion in April 2018.

In preliminary hearings, its was ruled that the assignment of accrued and future rights to Energy Works Hull prevented MW from seeking an additional claim against Outotec for liquidated damages under the subcontract.

The judge also ruled that other complex issues relating to the legal battle and proportions of damages would be determined at the full trial.

The project has already been the subject of two other courtroom battles.

The most recent saw small specialist pipework firm Premier Engineering Lincoln win a £615,000 payout from MW from contested supply of labour, supervision and materials invoices.

The other saw MW successfully overturn an adjudicator’s ruling in favour of a £368,000 payment to subcontractor Engie Fabricom (UK).

Latest news

Lonsdale went down owing £65m to supply chain

More than 600 firms owed money as reduced credit rating sinks M&E giant
3 days ago

Wates only bidder for £80m Cardiff estate rebuild

Council contacted 20 framework firms but received only one bid for 295-home Channel View estate rebuild
3 days ago

£21m legal battle over flawed concrete at Salford flats job

Developer in compensation battle with Arcadis after new concrete core demolished
3 days ago

Abu Dhabi developer Aldar Properties buys London Square

UAE giant swoops on resi specialist in vote of confidence for London market
3 days ago

Hunt for delivery partner to revive New Hospital Programme

Programme delivery partner to get £600m fee to get plans back on track
4 days ago

Green light for new £780m Essex garden village

3,700 homes and four new schools to be built at Dunton Hills
4 days ago

Laing O’Rourke makes a £288m loss

Rampant inflation on fixed-price jobs and problem contracts blow hole in accounts
4 days ago

Keltbray, OCU and Clancy clinch £1bn electricity network upgrade

Scottish and Southern Electricity Networks awards biggest ever deals for central southern England
5 days ago

G&T enlisted for commercial review of HS2 main civils contracts

Phase 1 Main Works Civils Contracts to come under cost scrutiny
4 days ago

TClarke order books doubles to top £1bn for first time

M&E specialist on track to exceed £500m turnover this year
4 days ago

Wates signs Government safety remediation pact

Private builder belatedly signs fire safety developer remediation contract
4 days ago

Liverpool all-electric industrial park approved

McLaren and Caddick in chase for Sefton 800,000 sq ft Atlantic Park scheme
4 days ago

Former Buckingham Group MD to join John F Hunt

Simon Hyams is new Managing Director for Contracting
5 days ago

Three in race for retendered £150m A9 dualling job

Bidders take another look after client takes on more risk
5 days ago

Clancy tops £300m revenue in fifth year of growth

Civils contractor delivers £13.5m pre-tax from water and energy sector work
5 days ago

Tower crane collapses on Edinburgh resi site

Jib falls onto apartment block under construction: Video
6 days ago

Salboy drops office space from Viadux Phase Two

Developer to focus on Manchester residential towers of 76 and 23 storeys
6 days ago

Warwick Uni plan for science and engineering campus

370,000 sq ft science and engineering precinct submitted for planning
5 days ago

Morgan Sindall chalks up Greater Manchester schools treble

Bury, Stockport and Wythenshawe school jobs will create 1,600 pupil places
5 days ago

Plans in for £65m Blackpool multiversity campus

Council leads plan for Talbot Gateway learning campus
5 days ago

Laing O’Rourke wins first phase of £700m Oxford R&D district

Landmark Red Hall and two labs to be built in phase 1a of Oxford North scheme
7 days ago

Ardmore wins retrofit deal on £200m Chancery Lane office

Building will be transformed to provide 105,637 sq ft of office space
7 days ago

Construction’s “Leading Lights” recognised

More than 50 winners in latest Considerate Constructors Scheme awards
6 days ago

Balfour Beatty clinches £20m Norfolk coastal defence jobs

Firm will install rock armour at Cromer and Mundesley
6 days ago

Architects join construction union Unite

Section of Architectural Workers forms official branch
7 days ago

Boot to build £20m lightweight aviation composites factory

Work starts on Sheffield University's COMPASS R&D facility
6 days ago

GMI secures £27m Leeds City College job

Site clearance underway for new Mabgate campus
7 days ago

Balfour signs deal with Koreans for UK power transmission jobs

Contractor strengthens large-scale onshore power transmission capability
7 days ago

36 storey south London build to rent flats tower approved

Construction to start next year on £220m Croydon scheme
7 days ago

Hunt for firms for £400m volumetric offsite deal

Procurement for Housing aims to expand its pool of firms on major offsite framework
7 days ago

Contractor services