Covid delays push Crossrail surface stations into next year

Aaron Morby 4 years ago
Share

Crossrail has revealed that surface station work to the west and east of central London will no longer be completed by the end of the year.

Walkways have been completed at Acton Mainline Station
Walkways have been completed at Acton Mainline Station

The station projects are being delivered for Network Rail by Hochtief, Graham and VolkerFitzpatrick.

In a monthly update to the London Assembly, Crossrail chief Mark Wild revealed all station completions had now been pushed into next year.

He said that despite recent progress at Romford, West Drayton, Ealing Broadway and Hayes & Harlington, the pandemic site lockdown had impacted the programme.

“As a result of the temporary pause of Network Rail works due to Covid-19, it is likely that these enhanced stations, along with llford, Southall, Acton Main Line and West Ealing, will be completed as soon as possible in 2021.

He added: “Network Rail are also working hard to complete the power supply upgrade on the Great Eastern Route.

“This involves reinforcing power supplies between Liverpool Street and Gidea Park.

“Final work is due to take place from November through to January with the system commissioned by April 2021.

“Completing the outstanding works and commencing intensive operational testing in early 2021 remain our top priorities.”

Latest news

Bid rigging probe launched into school repair work

Firms raided this week with focus on roofing contracts
1 day ago

McLaren hires ex-ISG regional boss for north east expansion

Andrew Beaumont becomes MD of new Yorkshire and North East business
6 hours ago

Government commits to four new prisons in seven years

£2.3bn pledged for new prison build programme
1 day ago

Road and rail delays hit revenue at Van Elle

Turnover drops 5% as markets remain challenging for piling specialist
5 hours ago

Boot reports ‘noticeable improvement’ in planning system

Government planning reforms already unblocking council planning
5 hours ago

Go-ahead to revamp former London city hall

Project will straighten the building's leaning profile with terraces to every level
13 hours ago

United Living to divert Midlands gas pipeline

600m pipeline diversion clears way for M54 to M6 link road construction
4 hours ago

Credit insurance saves Billington from ISG hit

Steel specialist puts on extra shifts at its plants to cope with demand
1 day ago

M&E specialist Dodd doubles profit on retrofit surge

Family-owned Telford specialist delivers record revenue of nearly £250m
1 day ago

Go-ahead for 800-home Croydon dual towers

One Lansdowne Road build to rent scheme to cost £260m to build
1 day ago

Construction inflation set to return raising tender prices

End of 2024 to mark the bottom of present inflationary trough
1 day ago

Start date for vast Balfour and Costain carbon capture power job

£4bn Teesside project to start construction next year creating 3,000 jobs
2 days ago

Plans go in to start revamp of North Finchley town centre

Developer Regal unveils first details of Barnet masterplan
1 day ago

Glencar bags £18m Big Yellow London store

Six-storey stoarage centre to be built at Staples Corner
1 day ago

Plan unveiled for 31-storey London Fenchurch Street tower

Demolition work to start in 2026 for new office tower
2 days ago

Vinci Building buys tower cranes for first time

Contractor invests in two WOLFFKRAN all-electric cranes at £138m Sheffield site
2 days ago

30 local firms land United Utilities £500m framework

Minor works deal win for North West civils and M&E specialists
2 days ago

Restructure pays off as Higgins returns to profit

Housing contractor recovers from £25.9m loss last year
2 days ago

Former Heathrow boss joins Mace in board rejig

Firm completes string NED appointments to expanded group board
3 days ago

Planning officers to get powers to bypass committee stage for housing

Rayner reform plan to cut out local council planning committees
3 days ago

National Insurance hike to delay construction recovery

Arcadis paints varied picture with full recovery delayed until 2026
3 days ago

Gratte Bros rides out cost rises with profit increase

M&E specialist warns of further upward pressure on wage costs
3 days ago

Sellar’s 36-storey London City office tower approved

Demolition work to start in 2026 at 60 Gracechurch Street site
5 days ago

Roofers caught using phone lights to work at night

Roofing boss handed suspended prison sentence for lack of edge protection
3 days ago

£380m North West housing framework out for bid

St Helens-based Torus aims to build 9,000 homes by 2029
3 days ago

Historic property magazine to close

Estates Gazette has been in business since 1858
6 days ago

M&S Marble Arch rebuild approved after three-year planning fight

Plans were delayed when Michael Gove backed carbon campaigners
7 days ago

£191m revamp funding approved for London Barbican Centre

Construction to start in 2027 on five-year programme
7 days ago

RED Construction tops £100m turnover

Builder maintains profit margin at 1.7% as business nearly doubles in size
6 days ago

Timber designs shortlisted for roads ‘footbridge of the future’

Three of five designs for National Highways propose timber structures over busy highways
6 days ago

Contractor services