Client sues design team after Costain project cost nearly doubled

Aaron Morby 4 years ago
Share

Developer Standard Life is suing some of its professional design team on the Newbury Parkway shopping centre and flats scheme after the cost of the project soared from around £77m to £146m.

Newbury Parkway project was completed over six years ago but a legal battle of cost overruns is rumbling on through the courts
Newbury Parkway project was completed over six years ago but a legal battle of cost overruns is rumbling on through the courts

The firm is now locked in a legal battle with its design team – Building Design Partnership, Sutton Griffin Architects, and Cundall – claiming £38m for alleged professional negligence.

Main contractor Costain completed the project back in June 2013 and concluded a final settlement agreement, whereby it agreed to assist Standard Life with any dispute against third parties relating to contract administrators instructions and confirmation of verbal instructions.

Standard Life claims that £50m of the final settlement was made up of £28m from variations to the building contract and nearly £22m from contractor’s loss and expense from delay and disruption.

Project manager Buro Four analysed in detail a sample of over 100 CVIs and CAIs for Standard Life, which represented £14.6m of the extra cost.

Of these, it assessed 49% had arisen because of a “design team issue”, 10% from a “client issue” and 41% were “unclassified”.

This analysis has been used by Standard Life to extrapolate the final claim, which has just been contested by the design firms in the high court before moving to the full case being heard.

The members of the design team, which deny allegations against them, argued that they objected to the full claim going to trial because it was based on the extrapolated £25m variations claim and loss and expense claim.

To avoid lengthy assessment of each of the CVIs and CAIs through the court, Justice Kerr has ruled that Standard Life should select which of the 3,604 individual variations and 280 delay notices it wants to submit to support a fresh claim involving a trial by samples.

BDP will be allowed to selected 80 of these variations, SGA up to 40 others and Cundall 40. Standard Life would be required to set out its case against these.

A similar sample procedure should be used for the client’s loss and expense claim, ruled Justice Kerr.

Judge Kerr accepted that the procedure to reassess the claim may delay the trial date but added: “I think the delay resulting from the current exercise is a price worth paying for enabling the case to be managed properly”

Latest news

Morgan Sindall to build former Willmott Dixon leisure job

New contractor appointed on
14 hours ago

Graham consortium wins £400m Manchester job

Equitix consortium to now work up DBFO plans for University of Manchester’s Fallowfield Campus
10 hours ago

Keltbray looking to sell infrastructure business

£378m turnover rail, energy and highways business up for sale
21 hours ago

Innovative viaduct building method used for first time in UK

HS2 contractors will build nine viaducts in Delta Junction using special cantilevered process
21 hours ago

Unite buys London site to fast-track 444-bed student scheme

£800m to be spent on London development pipeline in next five years
21 hours ago

CITB awards £2.5m of contracts to management consultant

Three outsourced deals in the last year for "project leadership and management consultancy"
21 hours ago

Village centre approved for 6,000-home new town plan

Hampshire's Welborne Garden Village plan has been in the pipeline for two decades.
20 hours ago

£3m fine after cherry picker demolition death

Court rules after tragedy during decommissioning of gas rig
21 hours ago

BAM plans wave of job cuts at UK Construction arm

Co-op Live arena plunges Bam Construction to £19.5m first-half loss
2 days ago

Robot tunnel builder goes into administration

Hypertunnel was hoping to revolutionise how underground structures are built
2 days ago

Wates to build £86m Guildford Council housing scheme

40% of the 248 homes will become council homes under partnership deal
2 days ago

“Scrap CITB” say three quarters of construction firms

Payroll giant Hudson Contract calls for CITB to be absorbed into new Skills England training body
2 days ago

£100m Prestwich Village revival approved

Vinci and Willmott Dixon in chase for Muse-led regeneration scheme
2 days ago

Carbon negative asphalt aggregate trialled on M11

Skanska and Tarmac test CO2 absorbing aggregate material on stretch of Essex motorway
2 days ago

Father and son sentenced over covid construction loan fraud

Bristol builders given suspended jail sentences over bogus Bounce Back Loans
2 days ago

Beck Interiors files administration notice

Supply chain has suffered delayed payments from £139m-turnover luxury fit out specialist
3 days ago

Green light for York Central civil service office hub

£60m office project accelerates York Central goods yard redevelopment
3 days ago

Blenheim House Construction enters administration

Administrators looking at options on present projects
3 days ago

Profits rise at Esh Group with more to come

Contractor confident about year ahead as market conditions move in right direction
3 days ago

Piling specialist Van Elle sees housing orders rise 30%

Mark Cutler says firm on course to deliver 10% annual sales growth
3 days ago

HS2 to spend £100m shutting sites where work never started

Remediation of sites no longer needed for cancelled Phase 2 will take three years
4 days ago

Willmott Dixon wins £61m deal for new Army dog unit

Contractor to revamp Kendrew Barracks in Rutland
3 days ago

Stockport advances 4,000-home Town Centre East plan

Council seeks consultants to steer plan for 280-acre area in the city
3 days ago

ISG sale imminent as buyers set-up UK holding company

South African nutrition entrepreneur and Australian partner primed to take over
4 days ago

CR Construction wins £210m Manchester towers

Construction to start next year on four blocks ranging from nine to 34-storeys
4 days ago

Southern Housing to rationalise supply chain following merger

Firms put on alert for £1.7bn construction framework renewal
4 days ago

Decision delayed on 52-storey Isle of Dogs tower

Hong Kong developer plans 460 flats block next to Millwall Inner Dock
4 days ago

Go-ahead for £850m North London estate rebuild

Flagship Edmonton housing estate redevelopment will deliver 2,000 new homes
4 days ago

Mace lands £184m Oxford Science Park contract

Contractor to build trio of laboratory and office buildings
5 days ago

Worker paralysed in 30ft fall during electricity pylon demolition

Specialist firm fined £240,000 after court hears linesman attached lanyard to a loosened steel section
4 days ago

Contractor services