Problem contracts cause more losses at nmcn

Grant Prior 4 years ago
Share

Civils contractor nmcn is now expecting to make a pre-tax loss of £16.5m this year following a review of contract performance.

The firm announced in October that losses were likely to be between £13.5m and £15m this year.

But that has now been revised upwards to the new £16.5m figure. 

Nmcn said: “An investigation has verified, subject to audit, that these include £5.3m of prior year contract adjustments pre-tax, to five contracts within the Water business, relating to errors which should have been identified and corrected at the reporting date and information affecting estimates which should have been available.

“Profit before tax for the year ended 31 December 2019 will therefore be restated to £2.1m from £7.4m. 

“Consequently, loss before tax for the current year is expected to be about £11.2m, including £1.2m for the final settlement of the last remaining legacy contract.

“The majority of the net cash flows associated with the forecast loss have already been incurred and the loss to be reported will have limited further impact on the Group’s current cash position.”

The contractor said that “a number of difficult contracts are being brought to a conclusion.”

It added: “This, together with Covid-19 and the AMP project cycle have made for an extremely challenging year.

“Some £20m of secured orders originally scheduled to be completed this financial year have slipped into 2021, due to the effects of coronavirus. This revenue is now reflected within the 2021 budgets.”

Loss making jobs were mainly in the water division but highways was also in the red “due to two poorly performing contracts which are now complete and the final settlements are being pursued.”

Things were better at the telecoms division bu building “has been significantly impacted by Covid-19, with consequent delays, and this has resulted in the division being loss-making this year.”

Nmcn is hoping to have a medium term debt package in place by February.

It added: “In the meantime, the group has taken significant steps to improve debt collection and to operate within its current overdraft facilities of £15m, albeit there has been regrettably some creditor stretch in recent weeks.”

A hunt for a new chief executive after John Homer stepped down in September is due to conclude in the first quarter of next year.

Nmcn has a secured order book of £200m with visibility on a further £100m of framework orders.

Ian Elliott, Acting Chairman, said: “2020 has unquestionably been a difficult year for the Group, with the combination of the Covid-19 constraints, the AMP transition and the consequences of prior year contract adjustments.

“However, I would like to acknowledge the fortitude of everyone within the Group in rising to the challenges we have faced.

We will enter 2021 with many issues already addressed, with an encouraging order book, a strengthened management team and with the optimism of a return to profitability.”

Latest news

Buyers more bullish about prospects for year ahead

Residential "resilient" but commercial work a weak spot
7 hours ago

Council backs first Brutalist car park-to-flats scheme

Newcastle-under-Lyme multi-storey car park to be reborn as pioneering homes scheme
10 hours ago

Hinkley Point C hits peak build with 26,000 jobs

3,000 more workers to join as fit-out work ramps up
9 hours ago

Over 40 firms win Wessex Water M&E minor works deal

Broad sweep of specialists picked for AMP8 programme
10 hours ago

Spencer lands Scottish bridge hat-trick

Steelwork, gantries and bearing upgrades on Kessock, Forth and Tay crossings
1 day ago

Winners revealed for £1.5bn decarbonisation deal

Fusion21 confirms places for 40 firms: Full list
9 hours ago

Cladding firm fined £225,000 after fatal fall

Court hears how cherry picker didn't reach all parts of repair job
10 hours ago

Early call-out for Ebbsfleet Garden City infrastructure

Bidders day to set out plan for Ebbsfleet Central commercial scheme
10 hours ago

Completed buildings caught-up in Gateway 2 chaos

Developer distraught after dealing with Building Safety Regulator
1 day ago

Aviva submits plans for 34-storey City office tower

Subject to planning work to start in autumn 2027
1 day ago

Murphy takes 40% stake in Aussie civils contractor

Firm enters Australasian market with stake in Sydney-based contractor Abergeldie
2 days ago

Moat seeks firm for £420m repairs and maintenance deal

15-year deal to upkeep 20,000 south east homes
1 day ago

Lynch takes over hotel for Sizewell plant operators

Hire giant now in the hotel business to guarantee accommodation for workers
1 day ago

Subcontractors wanted across Scotland

Latest Constructionline event in Glasgow: Register now
1 day ago

Six guilty of £2m bribery over Devon housing site deals

Corrupt building bosses and E.ON project chief and QS sentenced
6 days ago

1,650 former ISG staff launch legal claims

Redundancy Payment Service facing payout of more than £9m
6 days ago

Plans lodged for £1bn cancer research centre in Sutton

London Cancer Hub will deliver around 1m sq ft of lab and research space
5 days ago

London Met Uni seeks firm for £284m estate revamp

Contractor wanted to deliver capital works and FM
5 days ago

Delayed £2bn estate rebuild back on as Berkeley signs deal

Birmingham council development agreement paves way for 2028 Ladywood start
6 days ago

Tilbury Douglas boosts margin to 2.1% as profits double

Firm targets 3.5% margin by 2029 under new business plan
6 days ago

Subbies battle for fastest bricklayer title

Winchmore management team go back on the tools
6 days ago

Green light for revised McLaren Reading revamp

Mixed-use plans to transform Broad Street Mall site
5 days ago

Three arrested in Blu-3 and Mace bribery probe

Serious fraud office swoops over alleged £3m bribes to former Mace associates
7 days ago

Scotland’s most complex A9 dualling job heads to market

Market testing starts for £205m Pitlochry to Killiecrankie 6.4km upgrade
7 days ago

Unite signs £390m student beds JV with Manchester Met

Construction at Cambridge Halls site to start next year
6 days ago

Turkish contractor Limak to build new Luton Town stadium

Construction to start this summer on 25,000-seater venue
1 week ago

Kitchen fitter crushed to death by concrete blocks

House builder goes into liquidation before court case
6 days ago

Mears clinches £230m renewal for key Milton Keynes housing deal

Housing upkeep contractor achieves 100% renewal rate in bust rebid period
6 days ago

Murphy on board at new £32m rail station

Construction to start next year at Golborne station
1 week ago

HS2 engineers finish UK’s heaviest bridge slide early

A46 Kenilworth Bypass reopens 30 hours earlier than planned
1 week ago

Contractor services