Costain revamps risk control after problem jobs cause £96.1m loss

Grant Prior 4 years ago
Share

Costain has completely overhauled its approach to contract risk monitoring after problem jobs caused a £96.1m loss for the year to December 31 2020.

Results were hit by £94.7m of charges from two long-standing contracts in relation to the Peterborough & Huntingdon gas station job and and the A465 Heads of the Valleys road road scheme.

Costain also confirmed a one-off charge of £5m in relation to closing out the ASF south highways legacy contract.

The charges led to a pre-tax loss for the year of £96.1m from a £6.6m loss last time on turnover down to £1,070m from £1,175m.

Costain said: “The Group’s contract selection, tender and contract management processes and behaviours have been enhanced over the past 18 months, resulting in lower contract risk and better cost management throughout the lifecycle of our projects.

“To enhance tender governance the Group has updated its policies for commercial expectations and risk appetite for all new contracts, including reducing the acceptable level of downside risk and increasing the minimum level of acceptable profit for all new contracts.

“The Group has also implemented a five-gated approval process prior to signing any contract, including independent risk and assurance review prior to target cost and contract conditions approval.

“In addition, the Group has implemented its ‘Operational Excellence Model’ on all new contracts and existing long-term frameworks.

“The monitoring and administration of scope of works changes to identify and escalate potential cost increases at an early stage have been enhanced, including the rigour of monthly reviews of all contracts in a standard and mandatory format, and detailed measurement of work in progress and cash collection.”

Costain put the cost of Covid to the company at £9.2m and received £2m from the government furlough scheme.

The company has set a medium-term target of 6-7% divisional margins with 55% of profits derived from our higher margin services like consultancy and digital services as it “broadens its offer from purely complex construction.”

Costain added: “Everyone at Costain is focused on ensuring all projects are delivered to plan and project risks are managed effectively. This absolute focus alongside the delivery of our strategic plan is the bedrock to delivering the improved performance we expect next year and over the years ahead.”

The company had a £4.2bn order book at year end and net cash of £102.9m.

Alex Vaughan, chief executive officer, said: “Last year was a challenging year but I am proud of how well everyone at Costain responded and the resilience shown across our business which enabled us to continue to operate effectively with strict Covid-19 safety measures in place.

“The significant charges reported at the half-year relating to two contracts are clearly disappointing, and importantly we have taken robust steps to prevent such issues from reoccurring.

“Last year, we continued to be successful in winning new contracts and preferred bidder positions worth over £2.3bn with an increasing proportion of this work incorporating our broader service offering in line with our strategy.

“The UK Government has provided a clear strategic framework for UK infrastructure investment, underpinned by long-term underwritten investment programmes to support the UK Government’s drive to level-up economic growth and to meet decarbonisation commitments.

“I am confident that Costain is in a good position to capitalise on the opportunities in front of us and to grow our profits in 2021.”

Latest news

Spencer lands Scottish bridge hat-trick

Steelwork, gantries and bearing upgrades on Kessock, Forth and Tay crossings
4 hours ago

Completed buildings caught-up in Gateway 2 chaos

Developer distraught after dealing with Building Safety Regulator
13 hours ago

Aviva submits plans for 34-storey City office tower

Subject to planning work to start in autumn 2027
13 hours ago

Murphy takes 40% stake in Aussie civils contractor

Firm enters Australasian market with stake in Sydney-based contractor Abergeldie
22 hours ago

Moat seeks firm for £420m repairs and maintenance deal

15-year deal to upkeep 20,000 south east homes
12 hours ago

Lynch takes over hotel for Sizewell plant operators

Hire giant now in the hotel business to guarantee accommodation for workers
13 hours ago

Subcontractors wanted across Scotland

Latest Constructionline event in Glasgow: Register now
12 hours ago

Six guilty of £2m bribery over Devon housing site deals

Corrupt building bosses and E.ON project chief and QS sentenced
5 days ago

1,650 former ISG staff launch legal claims

Redundancy Payment Service facing payout of more than £9m
5 days ago

Plans lodged for £1bn cancer research centre in Sutton

London Cancer Hub will deliver around 1m sq ft of lab and research space
5 days ago

London Met Uni seeks firm for £284m estate revamp

Contractor wanted to deliver capital works and FM
5 days ago

Delayed £2bn estate rebuild back on as Berkeley signs deal

Birmingham council development agreement paves way for 2028 Ladywood start
5 days ago

Tilbury Douglas boosts margin to 2.1% as profits double

Firm targets 3.5% margin by 2029 under new business plan
5 days ago

Subbies battle for fastest bricklayer title

Winchmore management team go back on the tools
5 days ago

Green light for revised McLaren Reading revamp

Mixed-use plans to transform Broad Street Mall site
5 days ago

Three arrested in Blu-3 and Mace bribery probe

Serious fraud office swoops over alleged £3m bribes to former Mace associates
6 days ago

Scotland’s most complex A9 dualling job heads to market

Market testing starts for £205m Pitlochry to Killiecrankie 6.4km upgrade
6 days ago

Unite signs £390m student beds JV with Manchester Met

Construction at Cambridge Halls site to start next year
6 days ago

Turkish contractor Limak to build new Luton Town stadium

Construction to start this summer on 25,000-seater venue
6 days ago

Kitchen fitter crushed to death by concrete blocks

House builder goes into liquidation before court case
6 days ago

Mears clinches £230m renewal for key Milton Keynes housing deal

Housing upkeep contractor achieves 100% renewal rate in bust rebid period
6 days ago

Murphy on board at new £32m rail station

Construction to start next year at Golborne station
6 days ago

HS2 engineers finish UK’s heaviest bridge slide early

A46 Kenilworth Bypass reopens 30 hours earlier than planned
6 days ago

Bowmer + Kirkland to build £190m Oxford science scheme

Work to start at end of next month on 180,000 sq ft Fabrica scheme
7 days ago

New BAM leisure centre pool springs a leak

Contractor investigating "technical issues" delaying new £36m green leisure centre
1 week ago

United Living lands £250m HyNet pipeline deal

Firm wins deal to design and build over 34km of pipework to collect CO2
7 days ago

Hydrogen diggers get green light to use roads

JCB hails historic decision for advance of hydrogen-fuelled plant on sites
7 days ago

Go-ahead for McAleer & Rushe Glasgow student job

£100m funding deal paves way for 591-bed student tower
7 days ago

Fly-tippers to get their vehicles crushed

Drones will be used to identify cowboy construction waste operators
7 days ago

Green light for £150m West End office revamp

Shaftesbury Avenue office retrofit retains 75% of original building
1 week ago

Contractor services