Costain revamps risk control after problem jobs cause £96.1m loss

Grant Prior 2 years ago
Share

Costain has completely overhauled its approach to contract risk monitoring after problem jobs caused a £96.1m loss for the year to December 31 2020.

Results were hit by £94.7m of charges from two long-standing contracts in relation to the Peterborough & Huntingdon gas station job and and the A465 Heads of the Valleys road road scheme.

Costain also confirmed a one-off charge of £5m in relation to closing out the ASF south highways legacy contract.

The charges led to a pre-tax loss for the year of £96.1m from a £6.6m loss last time on turnover down to £1,070m from £1,175m.

Costain said: “The Group’s contract selection, tender and contract management processes and behaviours have been enhanced over the past 18 months, resulting in lower contract risk and better cost management throughout the lifecycle of our projects.

“To enhance tender governance the Group has updated its policies for commercial expectations and risk appetite for all new contracts, including reducing the acceptable level of downside risk and increasing the minimum level of acceptable profit for all new contracts.

“The Group has also implemented a five-gated approval process prior to signing any contract, including independent risk and assurance review prior to target cost and contract conditions approval.

“In addition, the Group has implemented its ‘Operational Excellence Model’ on all new contracts and existing long-term frameworks.

“The monitoring and administration of scope of works changes to identify and escalate potential cost increases at an early stage have been enhanced, including the rigour of monthly reviews of all contracts in a standard and mandatory format, and detailed measurement of work in progress and cash collection.”

Costain put the cost of Covid to the company at £9.2m and received £2m from the government furlough scheme.

The company has set a medium-term target of 6-7% divisional margins with 55% of profits derived from our higher margin services like consultancy and digital services as it “broadens its offer from purely complex construction.”

Costain added: “Everyone at Costain is focused on ensuring all projects are delivered to plan and project risks are managed effectively. This absolute focus alongside the delivery of our strategic plan is the bedrock to delivering the improved performance we expect next year and over the years ahead.”

The company had a £4.2bn order book at year end and net cash of £102.9m.

Alex Vaughan, chief executive officer, said: “Last year was a challenging year but I am proud of how well everyone at Costain responded and the resilience shown across our business which enabled us to continue to operate effectively with strict Covid-19 safety measures in place.

“The significant charges reported at the half-year relating to two contracts are clearly disappointing, and importantly we have taken robust steps to prevent such issues from reoccurring.

“Last year, we continued to be successful in winning new contracts and preferred bidder positions worth over £2.3bn with an increasing proportion of this work incorporating our broader service offering in line with our strategy.

“The UK Government has provided a clear strategic framework for UK infrastructure investment, underpinned by long-term underwritten investment programmes to support the UK Government’s drive to level-up economic growth and to meet decarbonisation commitments.

“I am confident that Costain is in a good position to capitalise on the opportunities in front of us and to grow our profits in 2021.”

Latest news

£500m Leeds South Bank scheme gets green light

Leeds City Council approves plan for 1,350 flats in mixed-use South Bank development
1 day ago

Galliford Try takes rebid £150m Carlisle Southern Link Road

Main construction works are due to start on 8km road in June
1 day ago

Arup takes stake in graphene-enhanced concrete venture

New concrete additive Concretene™ promises 30% savings in CO2 emissions
16 hours ago

Winners revealed on £1.42bn materials framework

Thirteen builders merchants land places on huge procurement deal for social landlords
16 hours ago

Travelodge eyes plans for another 300 hotels

Hotel giant writes to local councils offering partnership deals with a £3bn investment target
16 hours ago

Balfour Beatty to invest £60m in pop-up EV chargers

New Urban Fox JV will roll out 35,000 charge points across the UK over the next decade.
2 days ago

Leading Channel Isles builder goes bust

Jersey-based construction firm Camerons placed in liquidation
15 hours ago

HS2 Euston needs full design reset as costs set to double

Spending watchdog warns Euston stop-start delay will simply inflate already ballooning costs
2 days ago

Worker dies on major warehouse site in Stafford

Main contractor Glencar halts work while tragedy is investigated
2 days ago

Sellar switches London flats/hotel plan for 444 student rooms

Southwark's King’s Place scheme will comprise five buildings of up to 11 storeys
2 days ago

Bid race starts for Norfolk £30m Long Stratton Bypass

Council hopes to start work on 3.9km bypass in April 2024
2 days ago

GMI to build first warehouse at £200m Teesside business park

Work to start early next month on first shed at airport business park
2 days ago

Skanska Costain Strabag JV sets up own rebar plant

HS2 team now running on-site manufacturing facility to avoid supply chain issues
2 days ago

Bid rigging: Keltbray to appeal and so could Squibb

Both contractors "disappointed" with level of fines
5 days ago

Ten demolition firms fined £60m for bid rigging

Full details of fines with Erith and Keltbray hardest hit
6 days ago

Retail contractor J M Scully files administration notice

£23m turnover Dorset based contractor lodges court notice
5 days ago

Civils specialist M Lambe delivers record performance

Housing civils specialist seeks to diversify in face of challenging housing market
5 days ago

Willmott Dixon clinches £60m Oxford Brookes University job

Preparation work starts on two new buildings at Headington Hill campus
5 days ago

Ferns seals £50m+ Openreach network services deal

Five-year south west deal to provide civils, poling and complex manhole programme
5 days ago

20 firms win £4.5bn Southern construction framework

A dozen new firms secure spots on fifth generation public sector deal
6 days ago

Call grows for bolder 18m second staircase rule for flats

Architects, surveyors and builders professional trade bodies demand lower height threshold than proposed 30m
6 days ago

GRS Roadstone warns staff following cyber attack

Materials giant sends out letters highlighting the extent of the attack
6 days ago

Inland Homes to suspend shares as results delayed again

Auditors need more time to go through embattled house builder's books
6 days ago

Kier wins £73m Southport events centre job

Local supply chain set to benefit from major new project
6 days ago

Multiplex profit rebounds as margin restored to 2.9%

London tower builder predicts return to revenue growth this year as major schemes advance
6 days ago

Upbeat Vistry to re-open mothballed offsite factory

Former Countryside timber panel factories rebranded Vistry Works in revived drive to deliver 5,000 units a year
6 days ago

Builder crushed and blinded in wall collapse

Property owner in court after barn conversion goes horribly wrong
6 days ago

Keltbray bags £140m haul of energy infrastructure work

Specialist secures trio of power frameworks, two battery storage facilities and an energy from waste package
7 days ago

Government awards £1.8bn for energy retrofit schemes – list

Housing and public building decarbonising funds awards to support 20,000 construction jobs
7 days ago

Landmark London scheme switches from flats to student rooms

Regal London rethinks Old Kent Road scheme with 900 student rooms and 220 affordable homes
7 days ago

Contractor services