Rail electrification must speed up to meet UK net zero goal

Aaron Morby 2 weeks ago
Share

Rail contractors and industry bodies have called on the Government to power up electrification plans or risk missing its legally binding 2050 carbon emission targets.

Industry claim it can halve the cost of some project with a planned programme of works
Industry claim it can halve the cost of some project with a planned programme of works

They warn that the Government’s stop-start approach in the face of early cost overruns has hit the programme with just 215km of track last year electrified.

To decarbonise the network, 13,000 single track kilometres – or around 450km a year – of track will need to be electrified by 2050.

In an open letter to the Transport Secretary Grant Shapps, more than 15 rail businesses, and industry groups, are now calling for a programme of rail electrification to begin as soon as possible.

The industry claims that a sustained planned programme would allow the supply-side to cut the cost of some projects by as much as half.

The letter comes on the back of a new report, “Why Rail Electrification?” which sets out why – even with the development of clean new technologies like battery and hydrogen trains – the industry will be unable to decarbonise the rail network to the extent required without significant further electrification.

Civing Engineering Contractors Association chief executive Alasdair Reisner said: “Electrifying rail provides clear benefits to passengers and freight transport as outlined in ‘Why Rail Electrification?’.

“Now, as the UK looks to meet its net-zero targets, there is added urgency to decarbonise the rail network through a rolling programme of electrification. Moving on from a stop-start approach, industry is ready to deliver investment in a way that better retains skills and provides the best value for money.”

Darren Caplan, Chief Executive of the Railway Industry Association, said: “Electrification in the UK can be delivered affordably, at up to 50% the cost of some past projects, if there is a long-term, consistent, profile of work rather than the current situation of boom and bust.

“Crucially, a rolling programme of electrification needs to start now if the Government is to hit its Net Zero obligations, and if the railway industry is not to lose capability and expertise from the current hiatus in activity.

“Also, by committing to electrification immediately, UK rail could be a world leader, creating and sustaining green jobs, investment and economic growth at a critical time for the UK economy as we all seek to build out of the Coronavirus pandemic.”

 

Latest news

Construction output surge sees cost inflation hit record high

Buyers report rises in input costs hit near 25-year high as materials shortages bite
3 days ago

Fire at tower days before Grenfell-style cladding due to be removed

More than 40 people injured during blaze at 19-storey building
3 days ago

Firms shortlisted for £140m Havant reservoir

Balfour, Hochtief and Mackley/Jones JV hunt main reservoir package
3 days ago

Blackstone makes £1.2bn bid for St Modwen

Investment giant set to acquire big name developer
3 days ago

London Chalcots towers £100m reclad out to bid again

Camden Council hopes to let Swiss Cottage estate reclad before the end of this year
3 days ago

Balfour facing strike ballot over “insulting” pay offer

Industrial action ballot planned for workers on £1.5bn Central Rail System Alliance contract
4 days ago

Hill wins 142-home McArthurs Yard job in Bristol

Housing contractor bags first Bristol job at harbourside site
4 days ago

BarhaleDoosan to build organic waste water treatment works

Natural integrated wetland to be built at Clifton wastewater treatment works
3 days ago

London Nine Elms 12-storey office approved

Construction to start this summer at former Royal Mail site
3 days ago

Fresh price hike takes structural steel to £800 per tonne

Seventh price hike since last July sees steel sections rise by £50/t
4 days ago

Barratt problem concrete frames and cladding bill hits £163m

House builder sees demand and construction surge but legacy property charges rise
4 days ago

Materials shortages threatening pace of rebound

RICS survey reveals confidence running high but shortages could put brakes on recovery
4 days ago

Henry Boot rejigs senior management

New MDs appointed to head construction and plant operations
4 days ago

Procure Plus plans £1.3bn low carbon housing framework

Firms wanted to supply or fit solar panels and air and ground source heat pumps
4 days ago

Keltbray sells electrical engineering arm to management

MBO at Keltbray Lagan Power three years after contractor acquired majority stake in business
5 days ago

BAM awards £150m worth of Manchester arena packages

North West subcontractors win top billing at Co-op Live project
5 days ago

Contractor Kilnbridge sold to 800-staff ownership trust

Founder of £90m East London contractor sells to workforce trust
5 days ago

ISG chalks up £48m haul of school wins

Deals include a £12m pathfinder 'net zero' school in Bristol
5 days ago

Green light for £37m Dawlish train rockfall shelter

Work to start on 209m long track protection structure this August
5 days ago

Keltbray posts £9.4m loss due to Covid and restructuring

Specialist contractor confident about future with £25m net cash and £224m order book
6 days ago

Construction start date for £200m Basildon scheme

Work to start this autumn on Essex site being developed by Inland Homes and Homes England
5 days ago

New Buro Happold chief to double staff in six years

James Bruce aims rapidly to grow engineering consultant into a global player
6 days ago

Atkins raids Skanska for new finance director

Jo Jarman returns to consultant as new finance director
6 days ago

Kier wins £15m Braintree enterprise centre

Building work at Great Notley to start later this month
6 days ago

Big name concrete firms miss out on major HS2 deal

Skanska Costain Strabag JV awards major package to Kelly Formwork
6 days ago

Covid shakes-up Top 30 M&E contractors rankings

Several M&E firms grow despite 9% fall in revenue last year among top 30 specialists.
6 days ago

Bylor builds second Hinkley reactor shell a third faster

Next massive prefabricated steel ring section for reactor building lifted in by Big Carl
6 days ago

Plans in for 700-bed Nottingham student scheme

Next phase of The Island Quarter scheme submitted for approval
6 days ago

M Group rebrands Skanska highways arm as Milestone

New business launched as £50m takeover deal signed off
6 days ago

Henry Boot to start £110m Walsall logistics project

Remedial works to start at 620,000 sq ft Phoenix 10 logistics scheme
6 days ago

Contractor services