Balfour facing £50m hit over tower facade problems

Grant Prior 3 years ago
Share

Balfour Beatty has been hit with a liability of up to £50m to fix facade problems on a tower scheme in London.

Construction of the high-rise development was completed in early 2016.

But a structural assessment this June indicated that “the stone panels affixed to the façades will need to be modified, reinforced or replaced to meet performance requirements.”

Balfour said: “The expert’s assessment of the rectification methodology, which will determine the cost of the group’s obligation, is ongoing together with the group’s evaluation of any losses that could be incurred and any potential recovery options from third parties.

“At this stage, the group is not able to estimate with sufficient reliability the cost of its obligation as any estimate is subject to a number of unknown factors including what the proposed rectification solution is, any associated planning consents, sequencing, timeline and the consequential disruption to the development.

“As such there is a wide range of potential outcomes in this specific case. Based on current information, the range of the contingent liability is uncertain and extremely wide but could be as much as £50 million. The group will be pursuing all potential recoveries from third parties.”

The issue has prompted Balfour to pull out of bidding for fixed price residential property projects in central London.

Half year results published by Balfour reveal a number of issues at the UK Construction business which saw it rack-up a £23m underlying loss for the first six months from a turnover of £1,262m.

It said: “UK Construction recorded a £23 million underlying loss from operations in the half year (2020: £23 million loss). Issues at private sector property projects in central London have been exacerbated by Covid-19 disruptions, leading to a lengthening of project schedules.

“This situation has necessitated a reassessment of those contract end forecast positions, triggering write-downs on a small number of contracts.”

Stronger performances at Support Services and the other parts of the construction business helped Balfour to an overall pre-tax profit of £35m from a £26m loss last time on turnover up to £4,154m from £4,118m.

Leo Quinn, Balfour Beatty Group Chief Executive, said: “We continue to reshape Balfour Beatty to play to its strengths. These include leading capability in markets where governments are committed to long-term infrastructure programmes.  

“It means choosing to exclude regions and sectors which cannot provide profitable, low risk growth, in favour of those that can.  Our priority is on executing our already strong order book which will drive attractive cash generation and returns.”

Latest news

Morgan Sindall to build former Willmott Dixon leisure job

New contractor appointed on
15 hours ago

Graham consortium wins £400m Manchester job

Equitix consortium to now work up DBFO plans for University of Manchester’s Fallowfield Campus
11 hours ago

Keltbray looking to sell infrastructure business

£378m turnover rail, energy and highways business up for sale
22 hours ago

Innovative viaduct building method used for first time in UK

HS2 contractors will build nine viaducts in Delta Junction using special cantilevered process
22 hours ago

Unite buys London site to fast-track 444-bed student scheme

£800m to be spent on London development pipeline in next five years
22 hours ago

CITB awards £2.5m of contracts to management consultant

Three outsourced deals in the last year for "project leadership and management consultancy"
22 hours ago

Village centre approved for 6,000-home new town plan

Hampshire's Welborne Garden Village plan has been in the pipeline for two decades.
21 hours ago

£3m fine after cherry picker demolition death

Court rules after tragedy during decommissioning of gas rig
22 hours ago

BAM plans wave of job cuts at UK Construction arm

Co-op Live arena plunges Bam Construction to £19.5m first-half loss
2 days ago

Robot tunnel builder goes into administration

Hypertunnel was hoping to revolutionise how underground structures are built
2 days ago

Wates to build £86m Guildford Council housing scheme

40% of the 248 homes will become council homes under partnership deal
2 days ago

“Scrap CITB” say three quarters of construction firms

Payroll giant Hudson Contract calls for CITB to be absorbed into new Skills England training body
2 days ago

£100m Prestwich Village revival approved

Vinci and Willmott Dixon in chase for Muse-led regeneration scheme
2 days ago

Carbon negative asphalt aggregate trialled on M11

Skanska and Tarmac test CO2 absorbing aggregate material on stretch of Essex motorway
2 days ago

Father and son sentenced over covid construction loan fraud

Bristol builders given suspended jail sentences over bogus Bounce Back Loans
2 days ago

Beck Interiors files administration notice

Supply chain has suffered delayed payments from £139m-turnover luxury fit out specialist
3 days ago

Green light for York Central civil service office hub

£60m office project accelerates York Central goods yard redevelopment
3 days ago

Blenheim House Construction enters administration

Administrators looking at options on present projects
3 days ago

Profits rise at Esh Group with more to come

Contractor confident about year ahead as market conditions move in right direction
3 days ago

Piling specialist Van Elle sees housing orders rise 30%

Mark Cutler says firm on course to deliver 10% annual sales growth
3 days ago

HS2 to spend £100m shutting sites where work never started

Remediation of sites no longer needed for cancelled Phase 2 will take three years
4 days ago

Willmott Dixon wins £61m deal for new Army dog unit

Contractor to revamp Kendrew Barracks in Rutland
3 days ago

Stockport advances 4,000-home Town Centre East plan

Council seeks consultants to steer plan for 280-acre area in the city
3 days ago

ISG sale imminent as buyers set-up UK holding company

South African nutrition entrepreneur and Australian partner primed to take over
4 days ago

CR Construction wins £210m Manchester towers

Construction to start next year on four blocks ranging from nine to 34-storeys
4 days ago

Southern Housing to rationalise supply chain following merger

Firms put on alert for £1.7bn construction framework renewal
4 days ago

Decision delayed on 52-storey Isle of Dogs tower

Hong Kong developer plans 460 flats block next to Millwall Inner Dock
4 days ago

Go-ahead for £850m North London estate rebuild

Flagship Edmonton housing estate redevelopment will deliver 2,000 new homes
4 days ago

Mace lands £184m Oxford Science Park contract

Contractor to build trio of laboratory and office buildings
5 days ago

Worker paralysed in 30ft fall during electricity pylon demolition

Specialist firm fined £240,000 after court hears linesman attached lanyard to a loosened steel section
4 days ago

Contractor services