‘Carbon before capex’ cuts CO2 by two-thirds on school build

Aaron Morby 2 weeks ago
Share

A radical rethink of rebuilding an existing school using a construction model based on reduced carbon has delivered a whole life carbon savings of two-thirds and cut energy consumption in half without a significant cost increase.

Sustainable school with carbon at the centre of the decision making is completely possible without special measures
Sustainable school with carbon at the centre of the decision making is completely possible without special measures

The theorectical industry-led project known as Circular Twin involved digitally building a school that had already been completed.

The school was reworked from start to finish and with help from 250 supply chain partners so that each decision and design choice favoured a lower carbon outcome.

Morgan Sindall Construction led the research team, which also drew in experts from procurement specialist SCAPE, architects HLM and Lungfish and consultant Cundall.

The Circular Twin team discarded conventional industry approaches and collaborated taking decisions based on the modelled lifecycle carbon of the building, not cost.

The findings highlight how the early alliance of designers, clients, contractor, and the supply chain can lead to a significant reduction in Whole Life Carbon for modest capital cost uplift.

In comparison to the original school – built in 2017 – Circular Twin achieved:


  • 67% reduction in Whole Life Carbon
  • 72% reduction in upfront embodied carbon (EC) (48% reduction in lifecycle EC – this achieves the RIBA 2030 and LETI 2030 Embodied Carbon targets)
  • 52% reduction in annual energy consumption
  • 39% reduction in forest consumption (for products and 30-year UK offset)
  • CAPEX delivered within standard budgetary parameters with multiple over asset lifetime

Louise Townsend, director of social value and sustainability at Morgan Sindall Construction, said: “This initiative has uncovered a revelation – that low carbon construction is inhibited by our industry’s reliance on traditional design and procurement approaches.

“The outcomes show that achieving low carbon buildings is possible today.

“Ultimately, Circular Twin represents hard evidence of what can be achieved and is a much needed industry-led response to all the urgent challenges we face that will be highlighted at COP26 and have already been made explicit by the climate emergencies declared by local authorities around the country.”

Circular Twin is believed to be the first in the construction industry to put into practice the strategies of the government’s Construction Playbook.

 

 

Latest news

Domis set for Salford tower for upwardly-mobile

30-floor Clippers Quay tower rises from lower co-living studios to luxury penthouse living
51 mins ago

Tolent boss to leave as losses hit £8.3m

Closure of Southern business two years ago continues to hit bottom line
10 hours ago

Glencar bags 780,000 sq ft Coventry logistics park

Expanding St Albans contractor clinches big job for Bericote Properties
6 hours ago

Cladding panels “dislodged” from McAlpine hotel job

Roads closed around £540m Victoria square development
18 hours ago

£1.7bn Blue Eden project refloats Swansea tidal energy plan

Vast energy park plan for Swansea waterfront with 150 floating homes
16 hours ago

Chancellor to detail £7bn spending pledge for local transport

Around £1.5bn will be new cash for Midlands and Northern metro mayors
17 hours ago

Weston Homes plans £100m London flats scheme

Firm will build 254 flats at former Dylon factory in Sydenham
18 hours ago

New home starts slump 27% amid labour and materials crisis

Third quarter new housing registrations show shift away from apartment living
1 day ago

Liverpool student block developer goes under

Subbies owed millions as Mount Group Student Natex goes into administration
4 days ago

HS2 downsizes Euston station to save costs

Shift from 11 to 10 platforms allows station to be built in one stage rather than two
4 days ago

Naive QSs storing up trouble in chase for lowest bids

Subcontractors say tendering for jobs at the moment is like the "Wild West"
4 days ago

Accountant being investigated over nmcn audit

Regulator launches probe into 2019 accounts which showed healthy profit
4 days ago

Murphy trials AI warning cameras at site danger zones

Smart camera warning system picks up incorrect PPE and workers at risk
4 days ago

£35m Nottingham art school gets green light

Work will start early next year on the nine-storey block
4 days ago

Vinci seals £77m Bristol student accommodation job

Work to start next month on one of largest Passivhaus certified schemes in the UK
5 days ago

Mace chair Pycroft to stand down

Industry veteran calls it a day after nearly 30 years at Mace
5 days ago

Laing O’Rourke on course for float after strong results

Pre-tax profit of £41.4m despite Covid as country's largest private contractor eyes stock market listing
5 days ago

Three in race for latest £500m HS2 contract

Shortlist confirmed for 36 mile section connecting the West Midlands and Crewe
6 days ago

End of timber shortages in sight

Softwood imports catch up with demand but delivery problems persist
5 days ago

Sheffield Hallam University’s £220m city campus gets nod

BAM to start work early next year in first education pain-gain share alliance
5 days ago

London and North West labour rates rise for third month

Two regions becoming fresh pinch points for labour
5 days ago

ISG clinches £21m National Cycling Centre upgrade

Manchester velodrome set for major refit and green upgrade
5 days ago

Keltbray appoints new director to head-up HS2 contracts

Former Carillion and Network Rail director Neil Lindley to lead HS2 works
5 days ago

Furious nmcn subbies left holding £60m in unpaid bills

Suppliers believe they were "strung along" by nmcn management
6 days ago

Battle starts for £600m YORbuild minor works deal

Third generation framework to emphasise offsite and net zero capability
6 days ago

JCB targets first hydrogen diggers by end of 2022

Plant giant is investing £100m in developing super-efficient hydrogen engines
6 days ago

Ringway to replace Kier on Surrey roads deal worth up to £2.5bn

Massive maintenance contract could last up to 21 years
6 days ago

House builders and public bodies get biggest CITB training grants

Housing giants and councils among biggest beneficiaries
6 days ago

BAM Nuttall names new major projects MD

Richard Prime promoted to fill role vacated by Ian Parish who is now Interim MD
6 days ago

Offsite Homes Alliance courts firms for £4bn MMC framework

Alliance of social landlords in the North aims to build 10,000 offsite homes per year.
6 days ago

Contractor services